Assurance Co. v. U.S.

Decision Date10 March 1987
Docket NumberNo. 86-1350,86-1350
Citation813 F.2d 1202
Parties33 Cont.Cas.Fed. (CCH) 75,181 ASSURANCE COMPANY, Appellant, v. The UNITED STATES, Appellee. Appeal
CourtU.S. Court of Appeals — Federal Circuit

Ron A. Stormoen, Richard Corona & Associates, San Diego, Cal., argued for appellant.

Frank B. Flink, Commercial Litigation Branch, Dept. of Justice, Washington, D.C., argued for appellee. With him on the brief were Richard K. Willard, Asst. Atty. Gen., David M. Cohen, Director, Thomas W. Petersen, Asst. Director and M. Susan Burnett, Asst. Director. Col. Bruce R. Houston, Chief Trial Atty. and John Q. Adams, Office of Chief Trial Atty., Dept. of the Air Force, Air Force Contract Law Center, Wright-Patterson AFB, of counsel.

Before FRIEDMAN and DAVIS, Circuit Judges, and BENNETT, Senior Circuit Judge.

DAVIS, Circuit Judge.

We are asked to overturn a decision of the Armed Services Board of Contract Appeals (ASBCA or Board) awarding appellant very much less of an equitable adjustment than had been sought. We affirm.

I.

In April 1975 appellant Assurance Company (Assurance) was awarded by the Air Force a fixed-price contract to make improvements to 1,569 family housing units at Travis Air Force Base. Assurance was a joint venture which subcontracted the plumbing and heating work to another joint venture composed of Longhorn Mechanical Company and A-1 Plumbing & Heating Company--the real party in interest. 1 The claims now on appeal are (1) the so-called "crawl space claim"--extra excavation under the houses (to install ductwork and piping) where the vertical crawl space clearances shown on the contract documents were insufficient, and (2) the "A-5 unit plenum claim"--the amount of markup allowable for modifying ductwork. At an earlier stage the ASBCA sustained appellant's entitlement to an equitable adjustment for those two claims and remanded for consideration of the amount of the award. Appeal of Assurance Company, ASBCA No. 25254, 83-2 BCA p 16,908 (Oct. 17, 1983). 2 On remand, the contracting officer made a small award and appellant again sought review by the Board. In the decision now on appeal, the ASBCA denied any award for the "crawl space claim," negating the contracting officer's small award, and reduced the contracting officer's award on the "A-5 unit plenum claim." This appeal ensued.

II.

On the "crawl space claim," the Board refused to grant any award because, in its view, Assurance had wholly failed to show that it (or its subcontractor joint venture) had suffered any injury because of the change in the amount of available "crawl space." There was admittedly an entire absence of proof from books, records, or documentation, and no adequate explanation was offered for their absence. The Board said: "This lack of proof of payment makes it impossible to determine if the workmen who actually performed the work were paid any additional amount for any extra work caused by diminished crawl space. Likewise, on this record we cannot determine if appellant made any additional payment to the subcontractor because of the diminished crawl space irrespective of whether the subcontractor paid any additional amount to the workers who actually performed the work."

Assurance argues that it presented testimony giving estimates of the increased amount of work (e.g., extra hours of labor performed) and that was enough, where written documentation is missing, for a "jury verdict" or fair approximation of the amount of the equitable adjustment. That may well be true if there is proof that the contractor was in fact injured by the Government's change or breach. WRB Corp. v. United States, 183 Ct.Cl. 409, 425 (1968) ("we have allowed so-called 'jury verdicts' if there was clear proof that the contractor was injured and there was no more reliable method for computing damages ...") (emphasis added); Electronic & Missile Facilities, Inc. v. United States, 189 Ct.Cl. 237, 416 F.2d 1345, 1358 (1969) ("where responsibility for damage is clear, it is not essential that the amount thereof be ascertainable with absolute exactness or mathematical precision ...") (emphasis in original); S.W. Electronics & Mfg. Corp. v. United States, 228 Ct.Cl. 333, 655 F.2d 1078, 1088 (1981) (same). In Joseph Pickard's Sons Co. v. United States, 209 Ct.Cl. 643, 532 F.2d 739, 743 (1976), the Court of Claims said:

* * * there is a clear distinction between the measure of proof necessary to establish the fact that petitioner had sustained some damage, and the measure of proof necessary to enable the jury to fix the amount. The rule which precludes the recovery of uncertain damages applies to such as are not the certain result of the wrong, not to those damages which are definitely attributable to the wrong and only uncertain in respect of their amount. [209 Ct.Cl. at 650, 532 F.2d at 743 (emphasis in original) (citation omitted).] [Quoting Story Parchment Co. v. Paterson Parchment Paper Co., 282 U.S. 555, 562, 51 S.Ct. 248, 250, 75 L.Ed. 544 (1931).] 3

Here, the critical point is that the Board permissibly found that there was no real proof of any damage, i.e., that Assurance and its subcontractor had not shown that in fact they had suffered any monetary injury as a result of the "crawl space claim." There is good reason to believe that labor costs were not increased since the workers doing the ductwork (underneath the houses) appear to have been paid on a piecework basis (rather than by the hour), and there was absolutely no evidence to the contrary, or that workmen were paid additional money. 4 There were no extra small tool costs because the workers provided their own tools. There was no acceptable evidence of additional equipment costs. Also, there is nothing substantial to show that extra overhead or other additional costs were incurred. Appellant's witnesses never testified that Assurance or its subcontractors actually incurred or had to pay monetary expenses. The result is that, on this record, the ASBCA could properly view the case as one in which the very "fact of damage" had not been proved as to the "crawl space claim." In that situation, all the precedents hold that no award need have been made. 5

As for the "A-5 unit plenum claim," the Board simply determined that the $39.35 per unit cost for each of the 58 A-5 plenum units included all costs and markups. That decision was based on appellant's original claim, and that claim (by Assurance itself) was undoubtedly substantial evidence that that was all that Assurance asked from the Government.

III.

Both of the claims before us involve the legal question whether the Board can reduce awards made by the contracting officer to the contractor. For the "crawl space claim," the contracting officer awarded $5,565.31 while the Board awarded nothing. On the "A-5 unit plenum claim," the contracting officer awarded $3,440.19 which was reduced by the ASBCA to $2,282.30 (plus interest). We hold that the Board had the authority to reduce or nullify these awards of the contracting officer.

...

To continue reading

Request your trial
20 cases
  • Seaboard Lumber Co. v. U.S., 88-1486
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • May 17, 1990
    ...the facts, as well as the law, are decided de novo by the board or the court. See id.; 41 U.S.C. Sec. 605(a); Assurance Co. v. United States, 813 F.2d 1202, 1206 (Fed.Cir.1987). At the time the CDA became effective, and at the time all but four of the contracts at issue were executed, a dir......
  • Wilner v. U.S., 92-5161
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • May 26, 1994
    ...Claims, the action proceeds "de novo in accordance with the rules of the ... court." 41 U.S.C. Sec. 609(a)(3). In Assurance Co. v. United States, 813 F.2d 1202 (Fed.Cir.1987), this court addressed the question of the status of a contracting officer's decision under the CDA. The issue in Ass......
  • E. Coast Repair & Fabrication, LLC v. United States
    • United States
    • U.S. District Court — Eastern District of Virginia
    • August 9, 2016
    ...case is a de novo proceeding and the Contracting Officer's decision is not entitled to any deference. See Assurance Co. v. United States, 813 F.2d 1202, 1206 (Fed.Cir.1987) ; 41 U.S.C. §§ 7102(d), 7104(b).B. Pass-through Claims—Subcontractors The Government asserts that ECR has failed to de......
  • Novelty Textile Mills, Inc. v. CT Eastern, Inc.
    • United States
    • U.S. District Court — Southern District of New York
    • July 18, 1990
    ...is responsible for making, were otherwise. 282 U.S. at 563, 51 S.Ct. at 250 (emphasis added); see also, e.g., Assurance Co. v. United States, 813 F.2d 1202, 1205 (Fed. Cir.1987); S.W. Electronics & Mfg. Corp. v. United States, 655 F.2d 1078, 1088, 228 Ct.Cl. 333 (1981); Joseph Pickard's Son......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT