Atlantic Refining Co. v. Continental Casualty Co.

Decision Date07 April 1960
Docket NumberCiv. A. No. 15185.
Citation183 F. Supp. 478
PartiesATLANTIC REFINING COMPANY v. CONTINENTAL CASUALTY COMPANY, Joseph M. Smith, and Greensburg Concrete Block Company, Defendants and United States of America, Intervenor.
CourtU.S. District Court — Eastern District of Pennsylvania

Robert A. Rundle, of Wright & Rundle, Pittsburgh, Pa., for plaintiff.

J. M. McCandless, Pittsburgh, Pa., for defendant, Continental Cas. Co.

Daniel J. Snyder, Asst. U. S. Atty., Pittsburgh, Pa., for the United States, intervenor.

MARSH, District Judge.

The facts as disclosed by the pleadings and stipulated by the parties, except as hereinafter specified, are adopted by the court as if found pursuant to Rule 52, Fed.R.Civ.P., 28 U.S.C.

Atlantic Refining Company, hereinafter called the Owner, on November 8, 1954 and May 16, 1955 entered into two no-lien construction contracts with Joseph M. Smith, hereinafter referred to as Contractor, to furnish labor and materials for the construction of two service stations located, respectively, in Mt. Pleasant, Westmoreland County, Pennsylvania, and Connellsville, Fayette County, Pennsylvania. The contracts were filed of record in the respective counties before visible commencement of work was begun on the ground. A construction and payment bond furnished by Continental Casualty Company, hereinafter referred to as Surety, accompanied each contract.

The Contractor completed the construction of the service stations but failed to pay certain materialmen on each job. As of November, 1956, the balance withheld by the Owner on the contract price was $6,027.68 for the Mt. Pleasant station and $6,626.26 for the Connellsville station, or a total of $12,653.94.

Previously, the United States Internal Revenue Service served on Owner notice of levy and demand for certain taxes owed by the Contractor, assessed in July and December of 1955 and noticed and filed of record on October 28, 1955 and December 30, 1955. The total amount of the assessments was $11,632.06, plus interest, of which sum $1,114.81 was incurred by the Contractor in erecting the two service stations aforementioned.

Greensburg Concrete Block Company, a judgment creditor of the Contractor, served a writ of attachment execution on the Owner, as garnishee, attaching the fund allegedly due to the Contractor to satisfy its judgment of $737.65, with interest and costs.

The Surety claimed the balances withheld on the contract prices by reason of its liability on the bonds to unpaid materialmen.

Faced with these conflicting claims, the Owner on November 15, 1956 filed a "Complaint for Interpleader and Declaratory Relief" against the United States, the Surety Company, Greensburg Concrete Block Company, and the Contractor, and thereupon paid $12,653.94 into the registry of this court.

A default judgment was entered against Contractor Smith and Greensburg Concrete Block Company for failure to appear, answer or plead, and the Owner was discharged from any claim that they might assert against the funds paid into court.

The complaint was dismissed as to the United States, and the United States was permitted to intervene as a party plaintiff. The government's complaint in intervention alleges that the Contractor is indebted to it for certain withholding and F.I.C.A. taxes in the sum of $11,632.06, plus interest, and claims by virtue of the 1955 assessments that it has a prior lien on the fund allegedly due to the Contractor from the Owner. Hence, it demands the funds paid into court by Owner.

By amendment to its complaint, the government also sues the Surety directly on the bonds for all withholding and F.I.C.A. taxes due it from the Contractor in the sum of $11,632.06, plus interest. This suit, however, is pressed only for the sum of $1,114.81, plus interest, that amount being the withholding and F.I. C.A. taxes incurred by the Contractor in the construction of the service stations at Mt. Pleasant and Connellsville (see government's brief, pp. 32-34).

After the fund was paid into court, the Surety paid claims of materialmen on the Mt. Pleasant station in the sum of $6,004.51, leaving a balance of $23.17 unclaimed except by the United States. The Surety paid claims of materialmen on the Connellsville station in the sum of $12,285.53. The Surety took assignments from the materialmen which it paid.

The Surety presses its claim on the following grounds:

(1) The Contractor had no property or property interest in the fund upon which the government liens might attach.

(2) The Surety is subrogated to the rights of the Owner and materialmen in the fund created by the contract between the Owner and the Contractor.

(3) The Surety is entitled to the fund under equitable assignments given by the Contractor to the Surety at the time of the execution of the bonds.1

In my opinion the Surety is entitled to the fund on the first ground, and on the second ground, i. e., because it is subrogated to the rights of the Owner. It is, therefore, unnecessary to discuss the third ground, although I am of the opinion that the Surety's contentions with respect to the effect of its equitable assignments would not, succeed against the federal liens.2

The provisions of the contracts between the Owner and the Contractor are identical except for description of work and prices.

The pertinent provisions thereof are as follows:

(1) "Contractor shall, during the progress of the work, pay all valid charges of all his sub-contractors and other persons furnishing labor and/or materials in the performance or prosecution of the work * * * when and as such charges become payable and in their full amount."
(2) "When the contract has been completed, the Contractor shall deliver to the Owner a full Release of Liens signed by himself and all sub-contractors and other persons who have furnished any materials, labor, or both, in the performance of the contract or prosecution of the work. * * * Such release, with accompanying affidavits, shall be in such form as the Owner may require and its presentation to Owner shall constitute a representation by Contractor that all sub-contractors * * * have joined in the proper execution thereof as having been paid. * * * Until such releases and affidavits are delivered properly executed, the final schedule of payments may be withheld."
(3) "Waiver of Liens and Claims: * * * In the event that notice is given of any claim * * * which is chargeable to the Contractor * * * the Owner shall have the right to retain out of any payment then due, or to become due, an amount sufficient to completely indemnify the Owner against such claim. * * * In the event of * * * the Contractor's failure to have such claims * * * paid * * * the Owner shall have the right to take such action as is necessary to have the same done, charging the cost thereof * * * to the Contractor."
(4) "The Owner shall retain ten percent (10%) pending completion of the job and full compliance with the contract. * * * The final payment shall be made within thirty (30) days after final test and acceptance of the work, provided the Contractor shall have submitted to the Owner a satisfactory Release of Liens showing that all claims and bills for labor and material have been met and paid as hereinbefore provided."

The surety bonds are identical in their material provisions. Each contract was incorporated by reference in the accompanying bond.

Each bond was conditioned upon faithful performance of the contract and upon prompt payment of all just charges for labor and material furnished by Contractor.

No release of liens was furnished the Owner by the Contractor with respect to either job as required by both contracts. The Owner withheld the balances due on the contract prices and interpleaded the claimants thereto.

The Contractor Does Not Have Any Property or Rights to Property in the Withheld Balances of the Contract Prices Upon Which the Liens for Federal Taxes Might Attach.

The United States bases its claim to the fund on §§ 6321 and 6322 of the Internal Revenue Code of 1954.3 As therein provided "if any person liable to pay any tax neglects or refuses to pay same after demand, the amount * * * shall be a lien in favor of the United States upon all property and rights to property * * * belonging to such person."

It was held in United States v. Bess, 1958, 357 U.S. 51, 55, 78 S.Ct. 1054, 1057, 2 L.Ed.2d 1135 that "* * * § 3670 now 26 U.S.C.A. § 6321 creates no property rights but merely attaches consequences, federally defined, to rights created under state law", citing Fidelity & Deposit Co. of Md. v. New York City Housing Authority, 2 Cir., 1957, 241 F. 2d 142, 144. As stated in Morgan v. Commissioner, 1940, 309 U.S. 78, 80, 626, 60 S.Ct. 424, 426, 84 L.Ed. 585, 1035: "State law creates legal interests and rights."

As of the dates the federal liens were assessed (1955), the Contractor was not entitled to receive any money under the terms of the contract, for the Contractor owed materialmen on both jobs. On the Mt. Pleasant job the unpaid amount was practically equivalent to the amount withheld by the Owner, and on the Connellsville job the amount was substantially in excess of the amount withheld.

It must now be determined under the Pennsylvania law whether the Contractor had any "property" or "rights to property" in the balances withheld from the Owner and paid by it into court. Cf. Central Surety and Insurance Corp. v. Martin Infante Co., 3 Cir., 1959, 272 F.2d 231.

It is a general principle that a material failure of performance by one party to a contract not justified by the conduct of the other discharges the latter's duty to give the agreed exchange. Sections 274 and 275, Restatement, Contracts, with which Pennsylvania law is in accord; Wright v. Barber, 1921, 270 Pa. 186, 113 A. 200; City of Farrell to Use of Milarr v. H. Platt Co., 142 Pa. Super. 242, 15 A.2d 718; vol. 8 P.L.E. § 301; Sum.Pa.Jur. Contracts, § 498; cf. vol. 4, Corbin on Contracts, § 901. Also in accord are cases in...

To continue reading

Request your trial
28 cases
  • U.S. Fidelity and Guaranty Co. v. Bass
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • June 25, 1980
    ...any other creditor of the bankrupt and related back to the date of the construction contract with State. We agree with the court in Atlantic Refining Co. (Atlantic Refining Co. v. Continental Casualty Co., 183 F.Supp. 478 (W.D.Pa.1965)) which In the instant case, I conclude that the Contrac......
  • Randall v. Colby
    • United States
    • U.S. District Court — Northern District of Iowa
    • January 10, 1961
    ...Central Surety & Insurance Corporation v. Martin Infante Company, Inc., 3 Cir., 1959, 272 F.2d 231; Atlantic Refining Company v. Continental Casualty Company, D.C.1960, 183 F. Supp. 478; First National Bank In Yonkers v. City of New York, D.C.1959, 177 F.Supp. 175; General Insurance Company......
  • United States v. Commonwealth of Pa., Dept. of Highways, Civ. A. No. 70-3538.
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • October 3, 1972
    ...20 Id. 416 Pa. at 428-429, 206 A.2d at 54-55. See Home Indem. Co. v. United States, 433 F.2d 764, 193 Ct.Cl. 266 (1970). 21 183 F.Supp. 478 (W.D.Pa.1965). 22 Id. 183 F.Supp. at 23 Id. 183 F.Supp. at 482-483. 23a See note 22 and accompanying text infra; In re F. H. Donovan Painting Co., 220 ......
  • In re Harris
    • United States
    • Oklahoma Supreme Court
    • May 7, 2002
    ...(D.Colo.1983); General Elec. Supply Co. v. Epco Constrs., Inc., 332 F.Supp. 112, 115 (S.D.Tx.1971); Atlantic Refining Co. v. Continental Casualty Co., 183 F.Supp. 478, 484 (W.D.Penn.1960); Matter of Evans, 1 B.R. 229-30 (Bkrtcy.S.D.Fla.1979); Maull v. Stokes, 31 Del.Ch. 188, 68 A.2d 200-01 ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT