Atlas Concrete Pipe, Inc., In re

Decision Date18 January 1982
Docket NumberNo. 79-1324,79-1324
Citation668 F.2d 905
PartiesIn re ATLAS CONCRETE PIPE, INC., Bankrupt. ATLAS CONCRETE PIPE, INC., Plaintiff-Appellee, v. ROGER J. AU & SON, INC., Defendant-Appellant.
CourtU.S. Court of Appeals — Sixth Circuit

Edward C. Baran, Baran & Baran, Mansfield, Ohio, G. Cameron Buchanan, Buchanan, Ogne & Jinks, Troy, Mich., Joseph S. Radom, Detroit, Mich., for defendant-appellant.

Dennis M. Haley, Winegarden, Booth, Ricker, Shedd & Haley, Flint, Mich., for plaintiff-appellee.

Before MARTIN and JONES, Circuit Judges, and CELEBREZZE, Senior Circuit Judge.

CELEBREZZE, Senior Circuit Judge.

In this diversity action, Roger J. Au & Son, Inc., defendant-appellant, appeals from a decision of the District Court for the Eastern District of Michigan finding it liable to plaintiff-appellee, Atlas Concrete Pipe, Inc., for breach of a contract for the supply of steel reinforced concrete pipe. Atlas filed this suit over a decade ago, claiming that Au had failed to pay on the contract. Au counterclaimed charging Atlas with delays and defects in the pipe supplied. After several years of proceedings, including three trials, the district court granted summary judgment for Atlas on the issue of liability and assessed damages. Atlas Concrete Pipe, Inc. v. Roger J. Au & Son, Inc., 467 F.Supp. 830 (E.D.Mich.1979). We reverse the summary judgment on liability and remand the case for a trial on the merits.

I.

In early 1968, the Oakland County Department of Public Works submitted four specific contracts for bids for sewer construction projects. Prior to the contract bid date, Atlas, a manufacturer of concrete pipe, sent price information to the contractors who had obtained copies of the sewer project plans. As the low bidder, Au was awarded one of the contracts for the Clinton-Oakland Sewage Disposal System. On July 2, 1968, after Oakland County had formally awarded the contract to Au, Atlas sent the defendant a revised price list for purposes of negotiating a contract. 1

Between July 2 and July 15, 1968, representatives of the two companies met and discussed the terms of the prospective contract. At this meeting, Atlas assured Au that it could deliver 600 feet of pipe per day at the jobsite. Moreover, Atlas informed Au that it had to finance its operations with borrowed capital. In order to minimize its financing expenses, Atlas would require payment within two days after Oakland County made payments to Au. On July 15, 1968, the parties incorporated these provisions, the July 2 price list, and a requirement that the pipe "meet the specifications for the project as drawn by the owner (the Oakland County Department of Public Works)" into a written contract. The effect of this clause was to incorporate Oakland County's specifications into the Atlas-Au contract.

Construction commenced in August, 1968 and Atlas began supplying pipe to Au. In the course of construction, Au discovered defects in the pipe which necessitated repairs. Although Atlas initially delivered pipe at the contract rate of 600 feet per day, it later reduced its delivery rate to match Au's installation rate; the final shipment was not made until August, 1970, approximately twenty months after Atlas was obligated to complete delivery. Au failed to pay the outstanding open account indebtedness for the delivered pipe. Furthermore, the installed pipe was defectively manufactured 2 and failed Oakland County's infiltration-exfiltration tests. 3

On October 6, 1970, Atlas brought this contract action, alleging that Au had failed to pay for pipe which Atlas had manufactured and delivered and that Au had failed to install the pipe at the contract rate. Au counterclaimed and answered, alleging that Atlas failed to deliver the pipe at the contract rate, to remove excess pipe from the jobsite, and to supply pipe which complied with the project's quantity and quality specifications. Atlas filed three separate motions for partial summary judgment addressed to Au's counterclaims and defenses. On October 16, 1973, approximately one month before trial, the district judge granted the three motions for summary judgment. On November 13, 1973, the district judge entered the partial summary judgment order, denied a motion for reconsideration, and started the trial which was confined to the question of damages. The summary judgment ended Au's counterclaims and defenses, disposing of the liability issue altogether. After trial, the district judge died before rendering a decision, leaving the litigation unresolved.

On March 15, 1974, before another district judge could make a final decision, Atlas filed for reorganization under Chapter X of the Bankruptcy Act. The district court assigned to handle the case, sua sponte and without explanation, transferred the action to the bankruptcy court. Au opposed the transfer and sought to return the case to the district court on the grounds that the bankruptcy court lacked jurisdiction. Au made unsuccessful interlocutory appeals to the district court from the bankruptcy court's refusal to set aside the partial summary judgment entered by the original district court and from the bankruptcy court's refusal to transfer the action to the district court for lack of jurisdiction. Pursuant to the parties' stipulations in April, 1976, the case was tried in the bankruptcy court on the basis of the transcripts from the earlier trial and some additional documentary evidence. 4 The bankruptcy court made findings of fact and on October 18, 1977, entered judgment in favor of Atlas for $525,789.31. The bankruptcy court found Au liable based on the original district court's grant of summary judgment and determined damages based on the outstanding open account indebtedness, Au's breach of an implied promise to install the pipe at the rate of 600 feet per day, and consequential damages stemming from interest paid by Atlas for working capital required because of Au's failure to pay the outstanding open account indebtedness.

Au appealed the bankruptcy court's decision to the district court. On March 6, 1979, the district court, in a de novo review, granted partial summary judgment against Au based on the original district court's determination of liability, recomputed the bankruptcy court's assessment of damages, and entered judgment in favor of the plaintiff for the reduced amount of $452,001.86. Au appeals the summary judgment against its counterclaims, as well as the district court's decisions concerning damages and jurisdiction.

II.

The initial issue is the propriety of the district court's granting of partial summary judgment against Au. This issue is considered first because Au's counterclaims were its sole defenses; the partial summary judgment, therefore, disposed of Au's defenses at the outset. Atlas filed three motions for partial summary judgment seeking to dismiss Au's counterclaims which alleged that Atlas failed to deliver pipe at the contract rate, to remove excess pipe from the jobsite, and to supply pipe which met the project's quantity and quality specifications. The original district court granted summary judgment and dismissed Au's counterclaims, finding that the qualitative defects in the pipe supplied did not cause the pipeline to fail the infiltration-exfiltration tests and that the project's quantitative requirements for manhole T's were not enforceable against Atlas because of indefiniteness in the contract terms.

Summary judgment is appropriate only where no genuine issue of material fact remains to be decided and the plaintiff is entitled to judgment as a matter of law. See Willetts v. Ford Motor Co., 583 F.2d 852, 855 (6th Cir. 1978); Felix v. Young, 536 F.2d 1126, 1130 (6th Cir. 1976); Fed.R.Civ.P. 56(c). A court may not resolve disputed questions of fact in a summary judgment decision, see United States v. Articles of Device ... Diapulse, 527 F.2d 1008, 1011 (6th Cir. 1976), and if a disputed question of fact remains, the district court should deny the motion for summary judgment and proceed to trial. 5 See Felix v. Young, supra, at 1030; Bohn Aluminum & Brass Corp. v. Storm King Corp., 303 F.2d 425, 427 (6th Cir. 1962).

Au contends that the district court should not have granted summary judgment on the liability issues because the court had to resolve disputed questions of fact. Our review of the record leads us to conclude that Au is correct and that these issues must be decided in a trial on the merits. The district court improperly granted the plaintiff's first two motions for summary judgment which concerned the delivery of allegedly defective pipe and the failure of the sewage system to meet the infiltration-exfiltration specifications. 6 The district court granted summary judgment even though a clear factual dispute existed as to the cause of the failure to meet the contract specifications. The district court observed that "the failure of the line to meet the infiltration-exfiltration specifications ... can as much be the result of improper installation as of actual infirmities in the pipe itself." Where such a factual dispute remains, summary judgment is improper and the district court should afford the parties a full trial on the merits. 7

Furthermore, the district court judge erred in granting partial summary judgment because he based his decision on the relative credibility of the witnesses. In order to determine whether defective manufacture or installation caused the pipeline to fail the infiltration-exfiltration tests, the district court weighed conflicting testimony. The district court observed that "as between which of the two causes was more likely to have been responsible for the failure ... we observe only that in contrast to the pipe supplied by plaintiff which was inspected and certified by Michigan Testing Engineers, defendant's superintendent in charge of the installation of the pipe had never installed pipe of the diameter and length involved in the...

To continue reading

Request your trial
200 cases
  • Kelley v. Thomas Solvent Co.
    • United States
    • U.S. District Court — Western District of Michigan
    • December 13, 1989
    ...issues of fact on a Rule 56 motion, but is empowered to determine only whether there are issues to be tried. In re Atlas Concrete Pipe, Inc., 668 F.2d 905, 908 (6th Cir.1982). The moving party has a right to summary judgment where that party is able to demonstrate, prior to trial, that the ......
  • Matter of Holly's, Inc.
    • United States
    • United States Bankruptcy Courts. Sixth Circuit. U.S. Bankruptcy Court — Western District of Michigan
    • September 30, 1994
    ...its decision on Kentwood's Summary Judgment/Dismissal Motion. The Sixth Circuit in Atlas Concrete Pipe, Inc. v. Roger J. Au & Son, Inc. (In re Atlas Concrete Pipe, Inc.), 668 F.2d 905 (6th Cir. 1982) provides a succinct statement of the standards governing a court's decision to grant or den......
  • Gwinn Area Community Schools v. State of Mich., M82-199 CA2.
    • United States
    • U.S. District Court — Western District of Michigan
    • September 1, 1983
    ...material fact remains to be decided and the moving party is entitled to judgment as a matter of law. Atlas Concrete Pipe, Inc. v. Roger J. Au & Son, Inc., 668 F.2d 905, 908 (6th Cir.1976). Moreover, the purpose of a summary judgment motion is not to allow the court to decide issues of fact,......
  • Chrysler Workers Ass'n v. Chrysler Corp.
    • United States
    • U.S. District Court — Northern District of Ohio
    • April 16, 1986
    ...765 F.2d 75, 78 (6th Cir.1985), citing, County of Oakland v. City of Berkley, 742 F.2d 289, 297 (6th Cir.1984); In re Atlas Concrete Pipe, Inc., 668 F.2d 905, 908 (6th Cir.1985). A court may not properly resolve disputed questions of fact in a summary judgment decision, and if a disputed qu......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT