Attorney General v. Public Service Com'n, Docket Nos. 95494

Decision Date05 February 1988
Docket NumberDocket Nos. 95494,95495
Citation165 Mich.App. 230,418 N.W.2d 660
PartiesATTORNEY GENERAL and Association of Businesses Advocating Tariff Equity (ABATE), Plaintiffs-Appellees, v. PUBLIC SERVICE COMMISSION, Defendant-Appellee, and The Detroit Edison Company, Intervening Defendant-Appellant. The DETROIT EDISON COMPANY, Plaintiff-Appellant, v. PUBLIC SERVICE COMMISSION, Attorney General and Association of Businesses Advocating Tariff Equity (ABATE), Defendants-Appellees. 165 Mich.App. 230, 418 N.W.2d 660
CourtCourt of Appeal of Michigan — District of US

[165 MICHAPP 232] Frank J. Kelley, Atty. Gen., Louis J. Caruso, Sol. Gen., and Hugh B. Anderson, Asst. Atty. Gen., for Attorney General.

A. Robert Pierce, Jr., and Solomon Bienenfeld, Detroit, for Detroit Edison Co.

Hill, Lewis, Adams, Goodrich & Tait by Roderick S. Coy and Timothy M. Perrone, Lansing, for the Ass'n of Businesses Advocating Tariff Equity.

Frank J. Kelley, Atty. Gen., Louis J. Caruso, Sol. Gen., and Don L. Keskey and James A. Ault, Asst. Attys. Gen., for the Michigan Public Service Comn.

Before DANHOF, C.J., and McDONALD and THOMAS, * JJ.

PER CURIAM.

The Detroit Edison Company appeals as of right from the Ingham Circuit Court's order affirming an order of the Michigan Public Service Commission. Although Detroit Edison raises eight issues on appeal, the basis of most of [165 MICHAPP 233] its arguments is that the interest it must pay on customer refunds is excessive. We affirm the order of the PSC.

This case began in 1975 when the PSC ordered that Detroit Edison could not impose a surcharge upon its customers to recover fuel costs. The order was eventually upheld. Detroit Edison Co. v. P.S.C., 82 Mich.App. 59, 266 N.W.2d 665 (1978), lv. den. 403 Mich. 823 (1978), lv. gtd. on motion for reconsideration 403 Mich. 853 (1978), aff'd. by equally divided court 416 Mich. 510, 331 N.W.2d 159 (1982), reh. den. 417 Mich. 1133 (1983). However, Detroit Edison had already surcharged its customers, so the dispute began again over the issue of the proper interest rate Detroit Edison should pay when refunding the money.

Hearings before the PSC began on September 7, 1983. Detroit Edison argued for several different interest rates, all with quarterly compounding. The PSC recommended use of the authorized rate of return on common equity, with interest compounded quarterly. Both the Attorney General and the Association of Businesses Advocating Tariff Equity (ABATE) recommended use of the average monthly prime rate in effect from time to time, as published in the Federal Reserve Bulletin, with interest compounded monthly. On June 13, 1984, the PSC ordered that interest should be calculated on the basis of the authorized rate of return on common equity, without compounding. Detroit Edison was satisfied with this order because it resulted in having the money it had already refunded exceed the amount of its obligation.

The Attorney General and ABATE sought a rehearing on the issue of the method of compounding interest. Rehearing was denied and the Attorney General and ABATE filed suit in Ingham Circuit Court. After hearing testimony, the circuit [165 MICHAPP 234] court ordered that the case be stayed while the PSC considered different or additional evidence according to M.C.L. Sec. 462.26(c); M.S.A. Sec. 22.45(c). On remand before the PSC, the Attorney General and ABATE argued for use of the average prime rate compounded monthly. In the alternative, the Attorney General argued for use of the prime rate compounded quarterly or the rate of return on common equity compounded daily, monthly, or quarterly. Detroit Edison argued that the use of simple interest was appropriate.

On March 11, 1986, the PSC ordered, as it ordered in 1984, that interest should be calculated on the basis of the authorized rate of return on common equity, but that interest should be compounded quarterly. This would result in Detroit Edison owing its customers money in addition to that already refunded. Detroit Edison filed suit in Ingham Circuit Court. Finding that most of Detroit Edison's arguments had been previously waived, the Ingham Circuit Court affirmed the order of the PSC because it was not unlawful or unreasonable.

The first issue raised by Detroit Edison is whether it is estopped from challenging the interest rate set by the PSC's 1984 order. The circuit court ruled that most of the arguments raised by Detroit Edison were waived because it did not appeal from the 1984 order. We disagree. Under M.C.L. Sec. 462.26(c); M.S.A. Sec. 22.45(c) an altered, modified, or amended order of the PSC takes the place of its original order. Under Sec. 26(a), an interested party may appeal from "any order" of the PSC. Therefore, the 1986 order took the place of the 1984 order and became an order from which Detroit Edison could appeal. Although the rate of interest ordered did not change from 1984 to 1986, and Detroit Edison did not appeal from the interest [165 MICHAPP 235] rate ordered in 1984, we will consider the issues raised by Detroit Edison insofar as they pertain to the 1986 order.

Detroit Edison's next argument is that the circuit court has plenary power to order equitable relief. Detroit Edison makes no argument as to what would be the consequence of acceptance of this statement. However, we will consider it along with Detroit Edison's other arguments regarding whether the PSC has the authority to order payment of interest in excess of five percent, compounded quarterly.

The PSC has complete power to regulate public utilities and their rates or other charges. M.C.L. Sec. 460.6; M.S.A. Sec. 22.13(6). Accordingly, M.C.L. Sec. 462.26(e); M.S.A. Sec. 22.45(e) provides that a party aggrieved by an order of the PSC bears the burden of proving by clear and satisfactory evidence that the order is unlawful or unreasonable. Const.1963, art. 6, Sec. 28 is also applicable and it provides that final agency orders must be authorized by law and supported by competent, material and substantial evidence. "Unlawful" has been defined as an erroneous interpretation or...

To continue reading

Request your trial
25 cases
  • Midland Cogeneration Venture Ltd. Partnership v. Public Service Com'n
    • United States
    • Court of Appeal of Michigan — District of US
    • 19 Abril 1993
    ...interpretation or application of law, and unreasonable when it is unsupported by the evidence. Attorney General v. Public Service Comm., 165 Mich.App. 230, 235, 418 N.W.2d 660 (1987). Any factual determinations must be supported by competent, material, and substantial evidence on the whole ......
  • Ass'n of Businesses Advocating Tariff Equity v. Mich. Pub. Serv. Comm'n, Consumers Energy Co. (In re For)
    • United States
    • Court of Appeal of Michigan — District of US
    • 12 Julio 2018
    ...by competent, material, and substantial evidence on the whole record. Const. 1963, art. 6, § 28 ; Attorney General v. Pub. Serv. Comm. , 165 Mich.App. 230, 235, 418 N.W.2d 660 (1987). Agencies have the authority to interpret the statutes that they administer and enforce. Clonlara, Inc. v. S......
  • In re Detroit Edison Application
    • United States
    • Court of Appeal of Michigan — District of US
    • 3 Julio 2007
    ...by competent, material, and substantial evidence on the whole record. Const. 1963, art. 6, § 28; Attorney General v. Pub. Service Comm., 165 Mich. App. 230, 235, 418 N.W.2d 660 (1987). Consistently with the law regarding appellate review of an administrative agency's decisions, we give due ......
  • In re Review of Consumers Energy Co. Renewable Energy Plan
    • United States
    • Court of Appeal of Michigan — District of US
    • 12 Julio 2011
    ...by competent, material, and substantial evidence on the whole record. Const. 1963, art. 6, § 28; Attorney General v. Pub. Service Comm., 165 Mich.App. 230, 235, 418 N.W.2d 660 (1987). “An agency's interpretation of a statute, while entitled to ‘respectful consideration,’ ‘is not binding on ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT