Austin Company v. United States

Decision Date06 March 1963
Docket NumberNo. 177-61.,177-61.
PartiesThe AUSTIN COMPANY v. The UNITED STATES.
CourtU.S. Claims Court

Leward C. Wykoff, Cleveland, Ohio, for plaintiff. Thomas V. Koykka, Edward C. Adkins and Arter, Hadden, Wykoff & Van Duzer, Cleveland, Ohio, were on the briefs.

Alfred H. O. Boudreau, Jr., Washington, D. C., with whom was Acting Asst. Atty. Gen. Joseph D. Guilfoyle, for defendant.

Before JONES, Chief Judge, and WHITAKER, LARAMORE, DURFEE and DAVIS, Judges.

LARAMORE, Judge.

This case is being heard on plaintiff's motion and defendant's cross-motion for summary judgment, and involves interpretation of a contract which plaintiff says was later found to be impossible of performance.

The Austin Company, plaintiff, entered into a contract with the United States on August 11, 1954, to design, manufacture, test and deliver a Digital Data Recording and Transcribing System, for the contract price of $177,500. This was to be a system, incorporating the use of a servo-mechanism, to gather data from remote locations aboard a ship, amplify the information so gathered, and transmit it to a central point where it was to be converted to digital form suitable for use in a computer and finally recorded on magnetic tape. No system of this kind had ever been previously manufactured or developed.

Before execution of the contract, the plaintiff reviewed the defendant's specifications and determined that the system as so described could not be manufactured with the required precision set forth in the specifications because of the inherent time lag involved in the operation of the servo-mechanism. The plaintiff then studied the problem, and on June 1, 1954 submitted a technical proposal embodying modifications of the defendant's specifications, including an implementation designed to compensate for the characteristic error of the servomechanism. The plaintiff's proposal also contemplated a system having greater accuracy than that outlined in the defendant's specifications. After conferring with the defendant's representatives, the plaintiff further supplemented and revised its proposal. Both the defendant and the plaintiff believed the plaintiff's proposal sound and workable and would result in a more precise system. Therefore, the plaintiff's proposal was incorporated into the specifications of the contract which was then signed on August 11, 1954.

The plaintiff diligently proceeded to attempt to develop and manufacture the contracted-for system, and incurred expenditures of $290,000 to this end. However, due to a phenomenon called "jitter", which is noise of electrical or mechanical origin caused by vibrations and other disturbances, and which sometimes occurs in highly sensitive electronic systems, it was discovered that it was impossible for plaintiff to manufacture the called-for system, as specified, with the desired precision. After granting plaintiff several extensions of time to produce the system, the defendant finally terminated the contract when it became apparent that plaintiff could not make the system as required.

The main question before the court is whether, under the termination provisions of the contract, the plaintiff is entitled to recover the expenditures, not in excess of the contract price, which it incurred in its effort to manufacture the contracted-for system. Plaintiff's primary claim is that it is entitled to recover such expenditures because its nonperformance was, in the words of the contract, "due to causes beyond the control and without the fault or negligence of the Contractor."

The aforementioned clause is further implemented by another provision of the contract, which reads as follows:

"(b) The Contractor shall not be liable for any excess costs if any failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes include, but are not restricted to, acts of God or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather, and defaults of subcontractors due to any of such causes * * *."

Other termination provisions of the contract provide that when the contractor's failure to perform is due to causes beyond the control of the contractor, as determined in the above-quoted provision, the contract shall be considered terminated for the convenience of the Government and the contractor may recover its costs, not in excess of the contract price, incurred while attempting to perform.

The facts here indicate that plaintiff's failure to perform was solely...

To continue reading

Request your trial
20 cases
  • Sun Oil Co. v. United States
    • United States
    • U.S. Claims Court
    • February 22, 1978
    ...circumstances, it was not unreasonable for the Secretary to require plaintiffs to abide by their own plan. See Austin Co. v. United States, 314 F.2d 518, 520-21, 161 Ct.Cl. 76, 81, cert. denied, 375 U.S. 830, 84 S.Ct. 75, 11 L.Ed.2d 62 (1963).32 After all, plaintiffs' plan of development ha......
  • Eastern Air Lines, Inc. v. McDonnell Douglas Corp.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • May 17, 1976
    ...words expressly stating that the general provision included but was not restricted to those events. Austin Co. v. United States, Ct.Cl., 1963, 314 F.2d 518, 520, 161 Ct.Cl. 76, cert. denied, 375 U.S. 830, 84 S.Ct. 75, 11 L.Ed.2d 62. In our view, this decision merits the criticism it has rec......
  • Nager Electric Company v. United States
    • United States
    • U.S. Claims Court
    • June 14, 1968
    ...Ct.Cl. ___ (Jan. 1968). The issue was apparently not raised in Kennedy v. United States, 164 Ct.Cl. 507 (1964), or Austin Co. v. United States, 314 F.2d 518, 161 Ct.Cl. 76, cert. denied, 375 U.S. 830, 84 S.Ct. 75, 11 L.Ed.2d 62 4 See, e. g., Argus Indust. Inc., 66-2 B.C.A. ¶ 5711 (ASBCA No.......
  • Owens-Corning Fiberglas Corporation v. United States
    • United States
    • U.S. Claims Court
    • December 12, 1969
    ...Univ. Law Center, Government Contracts Monograph No. 4, at 21. 18 Note 17 supra, 111 F.Supp. at 286, 124 Ct.Cl. at 684. 19 314 F.2d 518, 161 Ct.Cl. 76, cert. denied, 375 U.S. 830, 84 S.Ct. 75, 11 L.Ed. 2d 62 (1963). 20 Austin, note 19 supra, affirmed a decision of the Armed Services Board o......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT