B & R Associates v. Dependable Ins. Co., Inc.

Decision Date23 December 1987
Docket Number87-1070,Nos. 87-1058,s. 87-1058
Citation835 F.2d 526
PartiesRICO Bus.Disp.Guide 6846 B & R ASSOCIATES, a District of Columbia Limited Partnership, Plaintiff-Appellant, v. DEPENDABLE INSURANCE COMPANY, INC., a Florida Corporation, Defendant-Appellee, v. MERIDIAN ELECTRIC CORPORATION, a Delaware Corporation, Third Party Defendant-Appellee, and Peter R. Taylor, Sr., Third Party Defendant. B & R ASSOCIATES, a District of Columbia Limited Partnership, Plaintiff-Appellee, v. DEPENDABLE INSURANCE COMPANY, INC., a Florida Corporation, Defendant-Appellant, v. MERIDIAN ELECTRIC CORPORATION, a Delaware Corporation, Third Party Defendant-Appellant, and Peter R. Taylor, Sr., Third Party Defendant.
CourtU.S. Court of Appeals — Fourth Circuit

Francis Samuel Brocato (Brocato & Keelty, Baltimore, Md., on brief), for plaintiff-appellant.

Andrew Jay Graham (Kramon & Graham, P.A., Gordon C. Murray, Baltimore, Md., on brief), for defendant-appellee.

Before WIDENER, HALL, and MURNAGHAN, Circuit Judges.

K.K. HALL, Circuit Judge:

B & R Associates ("B & R") appeals from an order of the district court staying proceedings in a contract action while compelling arbitration of all claims arising out of a contract between B & R and Meridian Electric Corporation ("Meridian"). B & R brought its initial complaint against Dependable Insurance ("Dependable"), as surety, for breach of a performance bond and labor and material bond, which the surety wrote with Meridian as principal/obligor, to the benefit of B & R, as obligee. Following Dependable's Petition for an Order for Stay Pending Arbitration and for an Order Directing Arbitration, the district court ordered, in part, that all claims arising out of the contract between B & R and Meridian should be submitted to arbitration and that further proceedings in this case be stayed pending arbitration. Dependable cross-appeals. We reverse and remand for further proceedings.

I.

In May, 1984, B & R entered into a contract 1 with Meridian for the performance of electrical work on a construction project. Dependable provided performance and labor and material bonds relative to Meridian's obligations on the project. Meridian then commenced work on the project in June of 1984. In April of 1985, B & R and Meridian negotiated the cost of certain extra work authorizations which were submitted to the surety as soon as their values were finalized. On April 30, 1985, Meridian ceased work on the project claiming that it had not been sufficiently paid under the contract. After receiving notification from B & R that Meridian was in default, Dependable proposed that B & R pay Meridian $106,904 and that B & R negotiate changes in the contract with Meridian. B & R declined to conduct negotiations. Dependable subsequently notified B & R that the bond had been negated and was no longer in force because B & R had supposedly violated provisions of the surety bond by failing to notify Dependable of any modifications or change orders. B & R brought suit in federal district court against Dependable, as surety, for breach of the performance bond and the labor and material bond. Meridian was named as a party defendant whose interests might be affected but was later dismissed to retain diversity jurisdiction. Dependable subsequently filed a motion for an order directing arbitration, an order staying proceedings pending arbitration and a motion to file a counter claim 2 against B & R. The counter claim asserted breach of contract; failure of payment; tortious interference and breach of contract; and RICO fraud, among other claims. The district court conducted a hearing on the arbitration motions and the motion to file a counter claim.

In a bench opinion, the district court ruled that there had been no waiver of the arbitration clause; the RICO claim, along with all other arbitrable claims, would be submitted to arbitration; and the litigation of any non-arbitrable claims would be stayed pending the outcome of the arbitration. In addition, the district court ruled that the motions to compel discovery and to file a counterclaim were rendered potentially moot and denied without prejudice. This appeal followed.

II.

The question of jurisdiction is at issue in this appeal. Dependable argues that this Court lacks jurisdiction because the district court's order compelling arbitration cannot be construed as a final order under 28 U.S.C. Sec. 1291. B & R contends that orders to stay underlying proceedings pending arbitration, when joined with an order to proceed with arbitration, are appealable under 28 U.S.C. Sec. 1291. In the alternative, B & R argues that the stay order is subject to the interlocutory appeal allowed by 28 U.S.C. Sec. 1292(a)(1) and the Enelow-Ettelson doctrine. 3 Although there is case law which would suggest that jurisdiction would lie under 28 U.S.C. Sec. 1291, e.g. County of Durham v. Richards & Assoc., Inc., 742 F.2d 811 (4th Cir.1984), we need not decide this issue because appellate jurisdiction clearly lies under 28 U.S.C. Sec. 1292(a)(1). This Court has recognized jurisdiction over interlocutory appeals from denials of motions to compel arbitration when such motions were raised as equitable defenses in underlying federal litigation between the parties. See Fraser v. Merrill Lynch Pierce, etc., 817 F.2d 250 (4th Cir.1987); Garner Lumber Co. v. Randolph Valensi, Lange, Inc., 513 F.2d 1171 (4th Cir.1975). We, therefore, turn to the merits of this dispute.

On appeal, B & R contends that all claims are not arbitrable and, therefore, the district court erred when it failed to specifically set out which issues were to be submitted to arbitration. On cross-appeal, Dependable contends that if this Court remands for an amendment of the district court's order, then the language of its proposed order be adopted for submission to the arbitrator. 4 We find B & R's position persuasive.

The district court ordered all claims arising out of the contract be submitted to arbitration. It is clear, however, that the court anticipated that some of the claims might not be arbitrable when it reserved jurisdiction over any claims or issues not resolved by the arbitrator. There can be no doubt that the court must sever and compel arbitration of all arbitrable claims and reserve jurisdiction of any non-arbitrable claims. Atkinson v. Sinclair Refining Co., 370 U.S. 238, 82 S.Ct. 1318, 8 L.Ed.2d 462 (1962); AT & T Technologies, Inc. v. Communication Workers of America, 475 U.S. 643, 106 S.Ct. 1415, 89 L.Ed.2d 648 (1986); Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. 213, 105 S.Ct. 1238, 84 L.Ed.2d 158 (1985). In light of the district court's failure to specify which claims were to be submitted to arbitration and which claims were not subject to compelled arbitration, the arbitration order must be reversed and this matter remanded for further proceedings consistent with this opinion. We reject, however, Dependable's position on cross-appeal. On remand, the district court is under no requirement to accept Dependable's order. It is in the district court's sound discretion whether to accept a proposed order from a party. Andre v. Bendix Corp., 774 F.2d 786 (7th Cir.1985).

REVERSED AND REMANDED.

MURNAGHAN, Circuit Judge, concurring in part and dissenting in part:

Though I concur with the majority in its decision that we have jurisdiction under 28 U.S.C. Sec. 1292(a)(1) and the Enelow-Ettelson doctrine, I part company with the majority in its decision on the merits. The majority incorrectly in my view settles an important issue of law in the Fourth Circuit. The issue is who, federal trial judge or arbitrator in the circumstances of such a case as the present one, decides the scope of an arbitration clause. I would adopt the rule of the Second Circuit that the arbitrator should decide what disputes fall within the arbitration clause when the clause is broadly worded and the court should make the determination as to arbitrability when the clause is narrowly worded. 5

Interpretation of arbitration clauses is a matter of contract interpretation and involves discernment of the parties' intent....

To continue reading

Request your trial
4 cases
  • Central States, Southeast and Southwest Areas Pension Fund v. Central Cartage Co.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (7th Circuit)
    • May 28, 1996
    ...a legal proceeding; the refusal of the injunction thus provides a basis for appellate jurisdiction. See e.g. B & R Assoc. v. Dependable Ins. Co., 835 F.2d 526, 528 (4th Cir.1987) (citing cases). However, our court refused to extend the doctrine to include orders refusing to compel arbitrati......
  • J.J. Ryan & Sons, Inc. v. Rhone Poulenc Textile, S.A.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (4th Circuit)
    • December 13, 1988
    ...has the practical effect of denying an injunction, although it is not expressed in such terms. See B & R Assocs. v. Dependable Ins. Co., 835 F.2d 526, 528 (4th Cir.1987); Garner Lumber Co., 513 F.2d at There can be no doubt that a court's refusal to give effect to an arbitration clause has ......
  • Kansas Gas & Elec. Co. v. Westinghouse Elec. Corp., 88-2012
    • United States
    • United States Courts of Appeals. United States Court of Appeals (4th Circuit)
    • November 22, 1988
    ...28 U.S.C. Sec. 1292(a)(1) "over interlocutory appeals from denials of motions to compel arbitration...." B & R Associates v. Dependable Ins. Co., 835 F.2d 526, 528 (4th Cir.1987) (citing cases). In Gulfstream Aerospace Corp. v. Mayacamas Corp., --- U.S. ----, 108 S.Ct. 1133, 99 L.Ed.2d 296 ......
  • Derosa v. J.P. Walsh & J.L. Marmo Enters., Inc.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (4th Circuit)
    • September 26, 2013
    ...and compel arbitration of all arbitratable claims and reserve jurisdiction of any non-arbitratable claims." B & R Assocs. v. Dependable Ins. Co., 835 F.2d 526, 528 (4th Cir. 1987). Here, the district court twice rejected Marmo's contention that patent infringement was not subject to arbitra......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT