B & V Ltd. v. All Dade General Const., Inc., 95-1431

Citation662 So.2d 413
Decision Date08 November 1995
Docket NumberNo. 95-1431,95-1431
Parties20 Fla. L. Weekly D2494 B & V LIMITED and B & V Phase I Limited, Appellants, v. ALL DADE GENERAL CONSTRUCTION, INC., Appellee.
CourtCourt of Appeal of Florida (US)

Semet, Lickstein, Morgenstern, Berger, Friend, Brooke & Gordon and Deborah E. Leder, Coral Gables, for appellants.

Hagen & Hagen and Max M. Hagen, Hollywood, for appellee.

Before NESBITT, BASKIN and LEVY, JJ.

PER CURIAM.

B & V Limited and B & V Phase I Limited (collectively "B & V") appeal an order granting the motion of All Dade General Construction, Inc. ("All Dade"), to dismiss B & V's complaint on res judicata grounds. We reverse.

B & V and All Dade entered into several contracts for roof repairs or replacements on a number of different structures. Each contract involves a different building with separate and distinct work specifications. The repair work for each building was memorialized in an individual All Dade contract, specifying the building's address, the work required, and the contract price.

In 1993, All Dade sued B & V to recover damages for breach of contract and for failure to pay for services rendered under the contracts on the following buildings:

110 N.E. 10th Street, Homestead, Florida

929 N.W. 2nd Avenue, Homestead, Florida

930-938 N.W. 1st Avenue, Homestead, Florida

155 N.W. 10th Street, Homestead, Florida

1223 N.E. 1st Avenue, Homestead, Florida

960 N.E. 1st Avenue, Homestead, Florida

55-67 N.E. 9th Court, Homestead, Florida

154-162 N.W. 7th Street, Homestead, Florida

B & V answered the complaint and asserted as an affirmative defense that the work was improperly performed and unsatisfactory. The suit ended with the court's entry of a Stipulated Final Judgment pursuant to settlement.

In 1995, B & V sued All Dade to recover damages for work not completed satisfactorily as required by contracts for the following buildings:

460-480 N.W. 6th Street, Homestead, Florida

521 N.W. 5th Avenue, Homestead, Florida

186-194 N.W. 2nd Street, Homestead, Florida

925 N. Krome Avenue, Homestead, Florida

30100 Old Dixie Highway, Homestead, Florida

150-170 N.W. 10th Street, Homestead, Florida

41 N.E. 3rd Road, Homestead, Florida

107 N.W. 4th Street, Homestead, Florida

125 N.W. 4th Street, Homestead, Florida

114 N.W. 5th Street, Homestead, Florida

All Dade filed a motion to dismiss asserting that res judicata barred the suit. The court granted the motion, dismissing the complaint with prejudice.

We reverse the order dismissing B & V's complaint, and hold that this action is not barred by the doctrine of res judicata. 1 In Albrecht v. State, 444 So.2d 8 (Fla.1984), the Florida Supreme Court explained:

several conditions must occur simultaneously if a matter is to be made res judicata: identity of the thing sued for; identity of the cause of action; identity of parties; identity of the quality in the person for or against whom the claim is made. It is also a settled rule that when the second suit is between the same parties, but based upon a different cause of action from the first, the prior judgment will not serve as an estoppel except as to those issues actually litigated and determined in it.

Albrecht, 444 So.2d at 12 (citations omitted). The test for determining whether a second suit between the parties is based on the same cause of action "is whether the facts or evidence necessary to maintain the suit are the same in both actions." Albrecht, 444 So.2d at 12. It is inconceivable that B & V's suit for breach of ten distinct contracts will require proof identical to All Dade's prior suit based on eight other contracts. Each contract memorialized an agreement as to a particular building, the distinct work that had to be performed, and contained different price quotes. These lawsuits do not litigate one all-encompassing contract for repairs on all the buildings. Although, as All Dade suggests, the contracts may have been the result of contemporaneous negotiations, the parties chose to memorialize each building's work requirement with a separate contract. Moreover, an action for poor workmanship requires a different showing for each building: To argue that improper work was performed on building X requires a showing of what work was required on building X, and what was and what was not done on that building. Such a lawsuit could not be won using evidence of work on building Y and the requirements under the building Y contract. See Super Serv. Prod. Corp. v. North Store Corp., 214 So.2d 664 (Fla. 3d DCA 1968). If All Dade's assertion is carried to its logical conclusion, once All Dade received a judgment in the first action for monies owed on those eight contracts, it would be barred from bringing a later action to recover any future monies owed it by B & V on the other contract. This would not be a correct application of res judicata.

Alternatively, All Dade argues that res judicata bars B & V's lawsuit because the claims should have been raised as compulsory counterclaims to All Dade's suit. A compulsory counterclaim is "any claim which at the time of serving the pleading the pleader has...

To continue reading

Request your trial
3 cases
  • Langer v. Rice
    • United States
    • Hawaii Court of Appeals
    • 28 octobre 2013
    ...two causes of action, even if they overlap in subject matter or derive from the same negotiations. See B & V Ltd. v. All Dade Gen. Constr., Inc., 662 So.2d 413, 415 (Fla. 3d DCA 1995). The same consideration can likewise serve as the basis for separate contracts, each creating a separate ca......
  • Daito International v. Bedrock Amplification, Inc.
    • United States
    • Massachusetts Superior Court
    • 20 mai 1999
    ... ... See ... Londono, 609 So.2d at 20; B&V Ltd. v. All Dade ... Gen. Constr., Inc., 662 So.2d 413, 415 ... ...
  • Wilson v. Kade
    • United States
    • Florida District Court of Appeals
    • 5 avril 2017
    ...for its adjudication the presence of third parties over whom the court cannot acquire jurisdiction"); B & V Ltd. v. All Dade Gen. Constr., Inc. , 662 So.2d 413, 415 (Fla. 3d DCA 1995) (holding that under the logical relationship test, a compulsory counterclaim exists "when the same aggregat......
1 books & journal articles
  • Legal theories & defenses
    • United States
    • James Publishing Practical Law Books Florida Causes of Action
    • 1 avril 2022
    ...2001). 3. Gomez-Ortega v. Dorten, Inc., 670 So.2d 1107, 1108 (Fla. 3d DCA 1996). 4. B & V Limited v. All Dade General Construction, Inc., 662 So.2d 413, 415 (Fla. 3d DCA 1995). 5. Maison Grande Condominium Assoc. Inc. v. Dorten, Inc. , 621 So.2d 762, 764 (Fla. 3d DCA 1993), rev. denied , 63......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT