Baker v. State
Decision Date | 09 October 1985 |
Docket Number | No. 85-11,85-11 |
Citation | 218 Mont. 235,707 P.2d 20 |
Parties | John R. BAKER, d/b/a J.R. Baker Construction, Plaintiff and Appellant, v. STATE of Montana, Montana State Board of Examiners, Governor Ted Schwinden, Secretary of State Jim Waltermire, and Attorney General Michael T. Greely, as members thereof, and Morris Brusett, Director of the Department of Administration, Defendants and Respondents. |
Court | Montana Supreme Court |
Larry W. Moran, Bozeman, for plaintiff and appellant.
Allen Chronister, Asst. Atty. Gen., Helena, for defendants and respondents.
This is an appeal from an order entered in the District Court of the First Judicial District, in and for the County of Lewis and Clark, dismissing the appellant's complaint for failure to state a claim. The suit was dismissed on the ground that plaintiff lacked standing to sue. This appeal raises important questions concerning standing, and the statutes regulating acceptance of bids and award of public works contracts.
The transaction involved resulted from the issuance by the State of Montana, Division of Architecture and Engineering of an invitation for bids for the construction of the National Guard Armory in Harlowton, Montana. Bids were received on January 18, 1984. J.R. Baker Construction, hereinafter Baker, submitted a bid for $420,740 and Edsall Construction Company, hereinafter Edsall, submitted a bid for $420,300, a difference of $440. Baker protested Edsall's bid on the allegation that Edsall was working beyond the contract time on another public works project and was therefore ineligible to bid on a public project by virtue of section 18-2-311, MCA and section 37-71-203, MCA. A hearing was held before the Board of Examiners on March 13, 1984. The Board of Examiners denied the protest and awarded the bid to Edsall as the low bidder.
In District Court Baker sought to have the action of the State in granting the bid to Edsall declared illegal as a violation of section 18-2-311, MCA and section 37-71-203, MCA. Baker further requested that the District Court determine that Baker was the lowest responsible bidder and was entitled to the award of the contract. Baker sought recovery for lost profits, bidding costs, litigation costs and attorney's fees. Defendants filed a motion to dismiss for failure to state a claim upon which relief can be granted. The District Court granted the motion. It is from that order that Baker appeals.
The decisive issue in this appeal is whether Baker lacked standing to bring this action.
The statute governing the award of construction contracts provides:
"(c) ... under the supervision and with the approval of the board of examiners, solicit, accept, and reject bids and award all contracts to the lowest qualified bidder considering conformity with specifications and terms and reasonableness of bid amount." Section 18-2-103(c), MCA. (Emphasis added.)
The statutes further state that:
"... A public contractor, as defined in 37-71-101, who has been awarded a contract by the state of Montana or any board, commission, or department thereof or by any board of county commissioners or by any city or town council or agency thereof for the construction or reconstruction of a public work and is working beyond the contract time (including any authorized time extensions) shall not submit any additional bids or proposals or enter into any additional contract with any public agency of the state of Montana, county, or city thereof until he has completely executed the contract upon which he is working beyond contract time and all supplemental agreements thereto.
"... A public contractor shall not be considered to be working beyond contract time if the delay is caused by an accident or casualty produced by physical cause which is not preventable by human foresight, i.e., any of the misadventures termed an 'act of God.' " Sections 18-2-311 and 18-2-312, MCA.
Section 37-71-203, MCA provides:
"...
Baker asserts that government agencies must abide by the bidding statutes and where a violation of a statute or regulationgives an advantage to one bidder the courts should allow the aggrieved bidder a right of recovery. Baker further maintains that by inviting offers, and representing that they will be considered pursuant to the competitive bidding statutes, an implied contract exists between the government and the bidders that the government will consider bids fairly and honestly within the statutory procedures.
Baker cannot base his plea for relief on contract theory. It is a well founded principle of contract law that a contract does not exist prior to the acceptance of a bid by an agency 1 Williston on Contracts, § 31 (3rd Ed.1957).
Courts from our sister jurisdictions have likewise held:
King v. Alaska State Housing Authority (Alaska 1981) 633 P.2d 256 at 261.
See also Gulf Oil Corp. v. Clark Cty. (1978), 94 Nev. 116, 575 P.2d 1332.
This authority is most persuasive when read in conjunction with the language of this state's bidding statutes. The department was under a statutory obligation to accept the lowest responsible bidder. The Department's solicitation of bids was not an offer. Nor was Baker's response to the solicitation an offer. Because the Department rejected Baker's bid, no contract ever came into existence. As a result, recovery based upon contract theory cannot be had.
The policy behind the bidding statute also precludes any finding of standing for Baker to bring the action. The statute's primary function is to benefit the citizens. This premise is stated in 72 C.J.S.,...
To continue reading
Request your trial-
ISC Distributors, Inc. v. Trevor
...abusing those requirements. The defendants argue, and the District Court agreed, that because of our prior decisions in Baker v. State (1985), 218 Mont. 235, 707 P.2d 20, and State ex rel. Stuewe v. Hindson (1912), 44 Mont. 429, 120 P. 485, ISC lacks standing to sue for damages under the Mo......
-
Debcon, Inc. v. City of Glasgow
...bring a negligence claim for failure to obtain the award of a public works contract." As authority, the court relied on Baker v. State (1985), 218 Mont. 235, 707 P.2d 20. As to any duty owed by Delta in particular, the court determined that Debcon's negligence claim against Delta "also must......
-
EH OFTEDAL AND SONS, INC. v. State ex rel. Transp. Com'n, 01-022.
...and consideration of advantages or disadvantages to bidders must be secondary to the general welfare of the public. Baker v. State (1985), 218 Mont. 235, 239, 707 P.2d 20, 23; Stuewe v. Hindson (1912), 44 Mont. 429, 437, 120 P. 485, 487. Also see 64 Am.Jur.2d Public Works and Contracts § 82......
-
Ralph L. Wadsworth Const. Co., Inc. v. Salt Lake County
...1059, 89 Cal.Rptr. 320 (1970); Sutter Bros. Constr. Co., Inc. v. City of Leavenworth, 238 Kan. 85, 708 P.2d 190 (1985); Baker v. State, 218 Mont. 235, 707 P.2d 20 (1985); Gulf Oil Corp. v. Clark County, 94 Nev. 116, 575 P.2d 1332 (1978); M.A. Stephen Constr. Co. v. Borough of Rumson, 125 N.......