Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP
Decision Date | 28 January 2016 |
Docket Number | No. 496, Sept. Term, 2014.,496, Sept. Term, 2014. |
Citation | 226 Md.App. 420,130 A.3d 1024 |
Parties | BALFOUR BEATTY INFRASTRUCTURE, INC. v. RUMMEL KLEPPER & KAHL, LLP. |
Court | Court of Special Appeals of Maryland |
Gregory S. Martin (Jennifer G. Craddock, Gregory S. Martin & Assoc. PA, on the brief) Maitland, FL. (Roger Jones, Lucas Webster, Joseph L. Katz, Huddles, Jones, Sorteberg & Dachille PC, on the brief) Columbia, MD, for Appellant.
John A. King (Ronan A. Geronimo, Brett A. Pisciotta, King & Attridge, on the brief) Rockville, MD, for Appellee.
LEAHY, REED, JAMES R. EYLER (Retired, Specially Assigned) JJ.
In this appeal we consider whether the economic loss doctrine applies to shield an engineering firm from tort claims brought by a contractor seeking damages for economic losses suffered in consequence of relying on the firm's allegedly defective designs and projections. Our holding is framed by the fact that, while the engineering firm and the contractor each had separate contracts with the government to perform work on the same design-bid-build construction project, there was no contract between the parties.
The City of Baltimore entered into a contract with Rummel Klepper & Kahl, LLP ("RK & K" or "Appellee"), a design engineering firm, to produce construction designs and associated documents for use by the successful bidder(s) on succeeding proposals for construction of the Patapsco Wastewater Treatment Plant. Fru–Con Construction Corporation, predecessor to Balfour Beatty Infrastructure, Inc. ("BBII" or "Appellant"),1 was the successful bidder on the plant upgrade projects, and entered into Sanitary Contract 852R with the City in November 2009.
Just over four years later, BBII filed a complaint in the Circuit Court for Baltimore City against RK & K, claiming that, during construction, BBII ran into costly delays and complications in reliance on RK & K's allegedly defective designs and negligent misrepresentations concerning project timeline projections. The complaint sounded in tort, supported by the theory that RK & K had a duty to BBII based on the "intimate nexus" between them, and asserted three causes of action: 1) professional negligence, 2) information negligently supplied for the guidance of others under Restatement (Second) of Torts § 552, and, 3 ) negligent misrepresentation.
RK & K filed a motion to dismiss the complaint for failure to state a claim. RK & K's central argument was that the complaint sought recovery for purely economic losses, and, because there was no contractual privity or its equivalent between BBII and RK & K, the economic loss doctrine barred BBII's tort claims. The circuit court granted the motion to dismiss in an order entered on April 10, 2014.
We affirm. We hold that BBII failed to state a claim because, as a matter of law, in the absence of privity, death, personal injury, property damage, or the risk of death or serious personal injury, no duty of care in tort runs from an engineer or architect to a contractor for purely economic losses on a public construction project. In reaching this holding, we determine that Maryland does not expand the "intimate nexus" test to include extra-contractual concepts of duty for the recovery of solely economic losses in public construction cases.
Design-bid-build contracts
Under the "design-bid-build" project delivery method utilized by the City in this case, the owner first enters into a contract with an architect and/or engineer ("A/E" or "design professional") to design the project. Typically, the engineering and design is completed before the owner releases a request for proposals for a general contractor to perform the work.2 1 Bruner & O'Connor Construction Law § 2:11 (2015). Under this method:
(1) the design is fully developed and completed before the pricing of the work, thus, presumably resulting in lowest cost, and (2) selection among responsible and responsive bidders can be made on the basis of price alone ... the contractor is excluded from contributing to the design process ...
Id. The A/E and the contractor each have a contract with the owner, but they have no contractual relationship with each other.
In contrast, integrated delivery methods, such as "design-build," create a single point of responsibility because the A/E and the contractor are bound under a single contract with the owner. Id. at § 2:12. Typically the contractor who is part of a design-build team is involved in aspects of the design of a project from the beginning, and the A/E remains involved—normally in an oversight and advisory role—during the construction phase. Id.; 5 Bruner & O'Connor Construction Law § 17:52 (2015) ( ).3
The traditional design-bid-build model often engenders tensions between the A/E and the construction contractor, as explained in one treatise on the subject:
Robert F. Cushman et al., Proving & Pricing Construction Claims § 9.03[A][1] (3d ed.2015). As discussed further infra, under traditional design-bid-build contracts, especially in the public sector, the contractor normally has a contractual entitlement to recover against the owner for construction delays and other benefit-of-the-bargain damages caused by the A/E's defective specifications and designs.
According to the complaint,4 sometime prior to October 2009,5 the City entered into a contract with RK & K for the design of two interrelated projects to upgrade the plant, termed the "Enhanced Nutrient Removal Facilities." According to BBII, the City's contract with RK & K specified that RK & K was to produce accurate, complete, and correct construction designs and drawings for use by the successful bidder(s) who would construct the plant upgrades. RK & K's duties and responsibilities allegedly included, but were not limited to:
Thus, in addition to its pre-construction/design phase responsibilities, RK & K was allegedly assigned several construction-phase responsibilities, including: 1) evaluating and approving "various submittals" from the contractor related to the work and RK & K's design; 2) inspecting the contractor's work during construction to assure conformance with RK & K's design intent and design; and, 3) review, evaluation, and, if acceptable, certification of the contractor's work to the City.
Construction work for the projects under Sanitary Contract 852R ("SC 852") and Sanitary Contract 845R ("SC 845")6 was to be completed at the same time, although SC 852 was let out for bid prior to SC 845. After it was pre-qualified by the City as capable of performing the work, Fru–Con Construction Corporation (predecessor in interest to BBII) bid on the SC 852 project, directly relying upon RK & K's documents and designs.7
On November 20, 2009, Fru–Con Construction Corporation and the City entered into a contract for the SC 852 project ("Contract"). Several years later, on January 1, 2014, the City agreed to an assignment of the Contract from Fru–Con Construction, LLC, to BBII.8 Under the Contract, BBII was to, "among other things," construct thirty-four "[d]enitrification filter cells (‘DNF cells') adjacent to the existing wastewater facility." DNF cells are "enormous, concrete tubs that hold massive amounts of wastewater to be treated." The Contract also required BBII to construct pipes and pipe support systems for the SC 852 project.
In its complaint filed on January 6, 2014, BBII related that RK & K designed the DNF cells to expand or contract at keyed joints located in their concrete walls to accommodate fluctuating water pressure. BBII constructed the DNF cells in accordance with RK & K's designs, but, when the water retention integrity of the DNF cells was tested, BBII learned that the cells were leaking due to cracks in the expansion and contraction joints. BBII alleged that these cracks and the associated leaks were a...
To continue reading
Request your trial-
Neal v. United States
...however, is held to the standard of care that prevails in his or her profession." Balfour Beatty Infra., Inc. v. Rummel Klepper & Kahl, LLP , 226 Md. App. 420, 438, 130 A.3d 1024, 1035 (2016)."It is a basic principle that ‘[n]egligence is not actionable unless it is a proximate cause of the......
-
Bel Air Carpet, Inc. v. Korey Homes Bldg. Grp., LLC
...firm and a third-party investor, see Walpert , 361 Md. at 693-94, 762 A.2d 582." Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP , 226 Md. App. 420, 447, 130 A.3d 1024 (2016). In addition, our Courts have analyzed whether an intimate nexus existed in other scenarios, inclu......
-
Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP
...Special Appeals affirmed the dismissal of Contractor's complaint based on lack of privity. Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP , 226 Md.App. 420, 130 A.3d 1024 (2016). It held that the economic loss doctrine barred Contractor's negligence and negligent misrepre......
-
Chassels v. Krepps
...Father or Child did rely on that statement, and (5) Child suffered injury as a result. Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP , 226 Md.App. 420, 457–58, 130 A.3d 1024 (2016), aff'd , 451 Md. 600, 155 A.3d 445 (2017) ; Flaherty v. Weinberg , 303 Md. 116, 135, 492 A......
-
Claims and Disputes
...v. Rummel Klepper & Kahl, LLP, 451 Md. 600, 155 A.3d 445 (2017). [74] Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP, 226 Md. App. 420, 453, 130 A.3d 1024, 1040 (2016).[75] Balfour Beatty Infrastructure, Inc., 451 Md. at 625, 155 A.3d at 459.[76] Id. at 626, 155 A.3d at 4......
-
Negligence Actions
...Nat'l Bank of Md., 307 Md. 527, 515 A.2d 756 (1986)).[69] Id.[70] Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP, 226 Md. App. 420, 130 A.3d 1024 (2016).[71] Id. at 453, 130 A.3d at 1043.[72] Id. at 452, 130 A.3d at 1043.[73] Balfour Beatty Infrastructure, Inc. v. Rummel ......