Ballard v. Industrial Com'n

Decision Date14 July 1988
Docket NumberNo. 3-87-0560WC,3-87-0560WC
Citation526 N.E.2d 675,122 Ill.Dec. 416,172 Ill.App.3d 41
Parties, 122 Ill.Dec. 416 George R. BALLARD, Plaintiff-Appellee/Cross-Appellant, v. The INDUSTRIAL COMMISSION et al. (A.O. Smith Harvester Products, Inc., Appellant and Cross-Appellee).
CourtUnited States Appellate Court of Illinois

George M. Burrier, Jr., Peoria, for A.O. Smith Harvestore Products, inc.

Robert G. Day, Jr., Law Offices of Day and Day, Peoria, for George R. Ballard.

Justice McCULLOUGH delivered the opinion of the court:

Claimant filed an application for judgment for interest and attorney fees under section 19(g) of the Workers' Compensation Act (Act) (Ill.Rev.Stat.1985, ch. 48, par. 138.19(g)) asking that interest be awarded at the statutory rate of 9% under section 2-1303 of the Code of Civil Procedure (Code) (Ill.Rev.Stat.1985, ch. 110, par. 2-1303). The trial court awarded interest at the rate of 6% from the date of the Industrial Commission's (Commission) decision of May 30, 1985, through June 10, 1987, together with attorney fees for vexatious delay in refusing to pay interest. Respondent appeals the award of interest and attorney fees. Claimant cross-appeals, arguing interest should have been set at the Code rate of 9% rather than at 6% pursuant to section 19(n) of the Act (Ill.Rev.Stat.1985, ch. 48, par. 138.19(n)).

The procedural history of this case is straightforward. On November 21, 1980, the arbitrator awarded claimant 17 4/7 weeks temporary total disability for a back injury. Permanent partial disability to the extent of 7 1/2% was also awarded. On review, the Commission reduced the permanent partial disability award to 3% and made a finding there was no causal relationship between claimant's condition and his employment after March 1976. On initial review in 1983, the trial court reversed that latter finding as against the manifest weight of the evidence and remanded. On remand the Commission issued a decision on May 30, 1985, finding claimant was permanently and totally disabled, awarding $128 per week for life from June 7, 1976 forward. The circuit court confirmed the Commission and this court affirmed the circuit court on April 29, 1987. (A. O. Harvestore Products, Inc. v. Industrial Comm'n (April 29, 1987, 3d Dist.Gen. No. 3-85-0774 (order under Supreme Court Rule 23).) The appellate court mandate issued May 26, 1987.

On July 7, 1987, claimant filed his application for judgment for interest. Claimant asked for interest from May 30, 1985, the date of the Commission's second decision through June 10, 1987, at the rate of 9%. The application alleged respondent had tendered the amount due on the underlying award on June 11, 1987, but refused to pay any interest accruing after May 30, 1985. The trial court found claimant was entitled to interest at the rate of 6% on the sum of $31,670.85 representing the value of the unpaid Commission award as of May 30, 1985, through June 10, 1987, the date respondent made its tender without interest. The court also awarded attorney fees in the amount of $10,792 covering the fees incurred at arbitration and on the application for a judgment.

Respondent argues the award of interest and attorney fees under section 19(g) was improper because there was a genuine dispute over whether interest was due claimant.

The pertinent portion of section 19(g) states:

"[E]ither party may present a certified copy of the * * * decision of the Commission when the same has become final * * * providing for the payment of compensation * * * to the Circuit Court * * * whereupon the court shall enter a judgment * * *. In a case where the employer refuses to pay compensation according to such final award or such final decision upon which such judgment is entered the court shall in entering judgment thereon, tax as costs * * * the reasonable costs and attorney fees in the arbitration proceedings and in the court entering the judgment for the person in whose favor the judgment is entered * * *." (Ill.Rev.Stat.1985, ch. 48, par. 138.19(g).)

As a preliminary matter, the parties appear to agree that if section 19(n) has any application to this case, interest would be awarded at 6% given the date of the arbitrator's decision. See Ill.Rev.Stat.1981, ch. 48, par. 138.19(n).

The problems which arise in this case are due largely to the confusion which exists in the case law and the statutory amendments which relate to this intricate issue. (See Aper v. National Union Electric Corp. (1988), 165 Ill.App.3d 482, 116 Ill.Dec. 527, 519 N.E.2d 117; Kuhl v. Industrial Comm'n (1986), 147 Ill.App.3d 519, 101 Ill.Dec. 58, 498 N.E.2d 240.) We are not unmindful of the incongruous results this dilemma often presents (see Bray v. Industrial Comm'n (1987), 161 Ill.App.3d 87, 97, 112 Ill.Dec. 436, 443, 513 N.E.2d 1045, 1052 (Kasserman, J., dissenting)) and this case is no exception.

To properly determine which interest statute applies it is necessary to frame the issue in terms of distinct periods of time. We begin with the period prior to the arbitrator's award of November 21, 1980.

Interest under section 19(n) of the Act applies to all unpaid benefits which have accrued prior to the date of an arbitrator's award. (Folks v. Hurlbert's Wholesale Siding & Roofing, Inc. (1981), 93 Ill.App.3d 19, 48 Ill.Dec. 472, 416 N.E.2d 745.) This remains the date from which interest accrues despite the fact at an intermediate level of review the award was overturned and on further review reinstated (Proctor Community Hospital v. Industrial Comm'n (1971), 50 Ill.2d 7, 276 N.E.2d 342), or increased. (Kuhl v. Industrial Comm'n (1986), 147 Ill.App.3d 519, 101 Ill.Dec. 58, 498 N.E.2d 240.) Therefore, interest is properly assessed at the rate of 6% under section 19(n) if, as of the date of the arbitrator's award, respondent had failed to pay an amount sufficient to cover the temporary total benefits originally awarded by the arbitrator and any permanent total disability benefits which accrued prior to November 21, 1980, by virtue of the Commission's May 30, 1985, decision.

Respondent argues that as of November 21, 1980, it had paid claimant over $29,000 and is entitled to a credit for that amount. We agree. Nevertheless, the question remains whether this sum was sufficient to satisfy respondent's total liability for the benefits to which claimant was entitled as of that date. If it was, no interest under section 19(n) may be awarded because there was no unpaid award existing to which interest might attach. On the other hand, if the sum did not constitute an amount sufficient to cover all benefits due, claimant is entitled to interest at the rate of 6% on any unpaid amount of accrued benefits as of November 21, 1980, from that date through June 10, 1987, the date of respondent's tender.

The next time frame we consider is that between the date of the arbitrator's award and the date of the Commission's second decision on May 30, 1985. Under the rule of Folks v. Hurlbert's Wholesale Siding & Roofing, Inc. (1981), 93 Ill.App.3d 19, 48 Ill.Dec. 472, 416 N.E.2d 745, claimant is not entitled to interest under section 19(n) on any benefits which accrue after the date of the arbitrator's award. Necessarily, weekly total permanent disability benefits which come due after November 21, 1981, cannot have accrued prior to that date. Therefore, section 19(n) does not apply.

Had respondent tendered the amount of benefits due from November 21, 1981, through May 30, 1985, immediately subsequent to the Commission's decision on that latter date, claimant would have no claim for interest on that amount. ( Folks, 93 Ill.App.3d 19, 48 Ill.Dec. 472, 416 N.E.2d 745.) However, following the Commission's decision, respondent refused to pay any further benefits due under the Commission award until its belated tender in June 1987. Despite the fact section 19(n) does not apply, claimant is still entitled to interest on the amount of unpaid benefits accruing after November 21, 1980, calculated from May 30, 1985, through June 10, 1987. Since section 19(n) does not apply, interest is properly taxed at 9% under section 2-1303 of the Code. Proctor Community Hospital v. Industrial Comm'n (1971), 50 Ill.2d 7, 276 N.E.2d 342; Bray v. Industrial Comm'n (1987), 161 Ill.App.3d 87, 112 Ill.Dec. 436, 513 N.E.2d 1045; accord Aper v. National Union Electric Corp. (1988), 165 Ill.App.3d 482, 116 Ill.Dec. 527, 519 N.E.2d 117.

Under the rationale of those cases, section 19(n) of the Act and section 2-1303 of the Code must be considered in pari materia. We agree that...

To continue reading

Request your trial
14 cases
  • Radosevich v. Industrial Com'n
    • United States
    • United States Appellate Court of Illinois
    • 19 d2 Setembro d2 2006
    ...through the day prior to the date of payments." 820 ILCS 305/19(n) (West 2004). Cases such as Ballard v. Industrial Commn., 172 Ill. App.3d 41, 122 Ill.Dec. 416, 526 N.E.2d 675 (1988), and Folks v. Hurlbert's Wholesale Siding & Roofing, Inc., 93 Ill.App.3d 19, 48 Ill.Dec. 472, 416 N.E.2d 74......
  • Ponthieux v. Fernandes
    • United States
    • United States Appellate Court of Illinois
    • 29 d4 Fevereiro d4 1996
    ...award. (Ill.Rev.Stat.1989, ch. 38, par. 138.19(n) (now 820 ILCS 305/19(n) (West 1994))); Ballard v. Industrial Comm'n (1988), 172 Ill.App.3d 41, 44, 122 Ill.Dec. 416, 418-19, 526 N.E.2d 675, 677-78. A claimant is entitled to interest under section 2-1303 of the Code on all amounts which acc......
  • Aurora East School Dist. v. Dover
    • United States
    • United States Appellate Court of Illinois
    • 21 d2 Março d2 2006
    ...under section 19(g)); see also Evans, 207 Ill.App.3d at 303, 152 Ill.Dec. 191, 565 N.E.2d 724; Ballard v. Industrial Comm'n, 172 Ill.App.3d 41, 46, 122 Ill.Dec. 416, 526 N.E.2d 675 (1988). Here, plaintiff concedes that it made only partial payment to defendant. Accordingly, it has no defens......
  • Illinois Graphics Co. v. Nickum, 4-92-0511
    • United States
    • United States Appellate Court of Illinois
    • 24 d3 Março d3 1993
    ...review, modifies the amount of benefits previously awarded by the Commission or an arbitrator. See Ballard v. Industrial Comm'n (1988), 172 Ill.App.3d 41, 122 Ill.Dec. 416, 526 N.E.2d 675. When a dispute arises, the employer has an equal, if not greater, interest in having its liability fin......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT