Bank of America Nat. Trust and Sav. Ass'n v. Hotel Rittenhouse Associates

Decision Date26 April 1988
Docket NumberNo. 87-1322,No. 87-1323,87-1323,Nos. 87-1322,87-1322,s. 87-1322
Citation844 F.2d 1050
PartiesBANK OF AMERICA NATIONAL TRUST AND SAVINGS ASSOCIATION, a national banking association, Appellee in, v. HOTEL RITTENHOUSE ASSOCIATES, a Pennsylvania limited partnership, Wolgin, Jack L., Jack L. Wolgin Associates, Inc., a Pennsylvania corporation, both general partners of Hotel Rittenhouse Associates, and Wolgin, Jack L. and Wolgin, Muriel, husband and wife v. NILSI, N.V. Abohar Investments, N.V. and Khalid Y. Al-Marzook, Jassim Y. Al-Marzook, Faisal Y. Al-Marzook, Fab III Concrete Corporation, proposed intervenor, Appellant in. FAB III CONCRETE CORPORATION, Appellant in, v. BANK OF AMERICA NATIONAL TRUST AND SAVINGS ASSOCIATION, Appellee in.
CourtU.S. Court of Appeals — Third Circuit

Leonard J. Bucki (argued), Wolf, Block, Schorr and Solis-Cohen, Philadelphia, Pa., for appellant FAB III Concrete Corp. in Nos. 87-1322 and 1323.

Joseph C. Kohn (argued), Harold E. Kohn, Kohn, Savett, Klein & Graf, P.C., Philadelphia, Pa., for appellee Bank of America Nat. Trust and Sav. Ass'n in Nos. 87-1322 and 1323.

Before SLOVITER, BECKER, and COWEN *, Circuit Judges.

OPINION OF THE COURT

BECKER, Circuit Judge.

These consolidated appeals, arising out of a bitterly contested battle over the demise of a building project, raise two discrete procedural questions. The first question we will address is whether a suit by a contractor to enforce an arbitration award against the developer and the bank that financed the project renders the developer an indispensable party pursuant to Fed.R.Civ.P. 19. We hold that, given that the arbitration award is joint and several, the contractor may sue the bank alone and that the developer is not an indispensable party.

Second, we must determine whether the contractor may intervene as of right in a foreclosure action by the bank against the developer two years after a final settlement was reached in the action (although the district court retained jurisdiction to settle any disputes arising from the agreement). We hold that given the contractor's diligence in trying to unseal an agreement between the bank and the developer, maintained by the court under seal, the intervention cannot be deemed untimely when the ultimate unsealing gives rise to further proceedings. Nevertheless, we express doubts as to the contractor's underlying ability to intervene as of right, and remand this question to the district court to consider the contractor's status in relation to certain escrow accounts held pursuant to the sealed agreement between the bank and the developer.

I. FACTS AND PROCEDURAL HISTORY

To understand the questions on appeal and the procedural history of the two separate actions that are consolidated before us, it is necessary to review briefly the legal history of the collapse of the Hotel Rittenhouse project, a luxury hotel-apartment project in Center City Philadelphia. 1 Hotel Rittenhouse Associates (HRA), a partnership operated by Jack Wolgin, was the developer for the building project. FAB III Concrete Corporation (FAB) served as a concrete contractor for the project. Bank of America National Trust and Savings Association (the Bank) financed the project. As the project experienced financial difficulties, FAB and other contractors began to receive late payments from HRA. In early 1982 the Bank signed a letter with FAB assuring that it would pay FAB directly for its work. In August, 1982 all payments from the Bank to FAB ceased.

A. Bank v. HRA Action

In June, 1983 the Bank sued to foreclose on the project and HRA counterclaimed alleging, inter alia, conspiracy and fraud surrounding the demise of the project. That first suit, which we will call Bank v. HRA, was settled, and as part of the court sponsored and supervised settlement, the terms were kept secret. FAB requested that the terms of the agreement be made public. The district court refused, but this court overturned the ruling and required that the terms of the agreement between the Bank and HRA be made public. Bank of Am. Nat'l Trust and Sav. Ass'n v. Hotel Rittenhouse Assocs., 800 F.2d 339 (3d Cir.1986). When the agreement became public, nearly two years after it was entered into, FAB learned that the Bank had agreed to fund an escrow from which HRA would pay its contractors. In return, HRA promised to indemnify the Bank against contractors' claims. According to this secret agreement, whatever HRA did not pay to the contractor and subcontractors would revert to Jack Wolgin personally. Wolgin also would receive a $1 million bonus for obtaining releases from all subcontractors. 2 FAB contends that during an arbitration arising out of a separate action (the FAB v. Bank case discussed below), HRA made claims that have been proved false by the unsealing of the secret agreement in the Bank v. HRA litigation. Specifically, FAB argues that: (1) HRA "pled poverty" when in reality a fund existed to pay contractors and that fund has been earning interest; and (2) it is clear from the secret agreement that HRA (contrary to its assertions in arbitration) had never incurred substantial interest claims to the Bank so that its claim against FAB in arbitration to recoup delay damages that HRA allegedly owed the Bank was fraudulent.

On February 17, 1982, five days after it received access to the secret agreement between the Bank and HRA, FAB moved to intervene in the Bank v. HRA case in order to claim an equitable right to interest that had been accruing on the escrow fund set aside for the benefit of contractors and subcontractors (including FAB). FAB estimates that the accrued interest exceeds $120,000. FAB particularly desires to intervene in this action because the escrow, upon which FAB wishes to obtain interest, was established pursuant to a negotiated agreement supervised by the court in this case, and the district court retained jurisdiction for all purposes connected with the agreement to settle any disputes arising out of the agreement. The district court denied the motion to intervene as untimely and FAB appeals that denial.

B. FAB v. Bank Action

At the same time that FAB was attempting to unseal the secret agreement in the Bank v. HRA case, FAB initiated a separate suit against the Bank for money still due for its contracting work. This second case, which we will call FAB v. Bank, did not include HRA, whose presence in the action would have deprived the court of diversity jurisdiction. See 28 U.S.C. Sec. 1332 (1982). When the suit was brought, the Bank made a motion for the inclusion of HRA as an indispensable party. That motion however was never ruled upon. 3 Instead, the district court stayed the FAB v. Bank action pending arbitration. At the arbitration proceeding all three parties were present. The Bank and HRA were represented by the same attorney. The arbitrator awarded FAB over $848,000 against the Bank and HRA, plus 6% interest from the date of the award to the date of payment. The Bank refused to pay the award until FAB signed a release of all claims, including state court claims for conspiracy and abuse of process that are still pending. FAB refused to sign a general release and instead returned to the district court to enforce its arbitration award against the Bank. The Bank, however, argued that FAB could not bring suit in federal court to enforce the arbitration award without including HRA because HRA was an indispensable party. The district court agreed and dismissed the action. The district court noted that FAB had brought claims in Pennsylvania state court and that it could enforce the arbitration award in that forum against both the Bank and HRA.

As a chronological matter we discussed the intervention question first; however, in our legal analysis, we will first address the Rule 19 indispensable party question. We will consider two questions: (1) Can FAB sue the Bank alone to enforce its arbitration award or is HRA an indispensable party to the FAB v. Bank litigation?; and (2) Can FAB intervene in the Bank v. HRA litigation?

II. DISMISSAL FOR FAILURE TO JOIN HRA

FAB argues that the district court abused its discretion in holding that HRA is an indispensable party needed for just adjudication of the FAB v. Bank action enforcing the arbitration award. We agree.

Rule 19 of the Federal Rules of Civil Procedure governs joinder of necessary and indispensable parties. 4 Rule 19(a) determines whether a party is a necessary party who should be joined in the action. If the answer to that first question is yes then the court must do so if feasible. If the answer to the first question is no, however, then the inquiry need go no further. See Abel v. American Art Analog, Inc., 838 F.2d 691, 695 (3d Cir.1988) (foreclosing any further inquiry once the panel "conclude[d] that [absentees] are not necessary parties pursuant to Rule 19(a)").

Rule 19(b) governs the situation in which the court determines that a party must be joined but that joinder cannot be effectuated (as, for example, in our case, where the joinder of HRA would destroy diversity). Where joinder of a Rule 19(a) necessary party is not feasible, the court must decide whether the absent party is "indispensable," and hence that the action cannot go forward.

Even assuming that HRA is a Rule 19(a) necessary party for a just adjudication, which should be joined if feasible, 5 it is clear that HRA cannot be deemed an "indispensable" party.

We note that the equities of the case and the situation of the parties have changed dramatically since the original Rule 19 motion was made. When that motion was first made in the spring of 1984, before the case was stayed for arbitration, the question of liability was still at issue. Now, after the arbitration, the only issue left is enforcement of the award. We agree with FAB that the district court mistakenly decided the 19(b) question as if it were faced with...

To continue reading

Request your trial
64 cases
  • Coca-Cola Bottling of Elizabethtown v. Coca-Cola Co.
    • United States
    • U.S. District Court — District of Delaware
    • August 2, 1988
    ...Jet Traders Investment Corp. v. Tekair, Ltd., 89 F.R. D. 560 (D.Del.1981); see also Bank of America National Trust and Savings Ass'n v. Hotel Rittenhouse Associates, 844 F.2d 1050, 1056-57 (3d Cir.1988) (dispute between developer and bank concerning failed building project perhaps did not g......
  • School Dist., Pontiac v. Secretary, Us. Dept. Educ.
    • United States
    • U.S. Court of Appeals — Sixth Circuit
    • October 16, 2009
    ...v. United Bhd. of Carpenters & Joiners of Am., 685 F.2d 164, 166 (6th Cir.1982); see also Bank of Am. Nat'l Trust & Sav. Ass'n v. Hotel Rittenhouse Assocs., 844 F.2d 1050, 1054 n. 5 (3d Cir.1988) ("We observe that the advisory committee note to Rule 19(a) indicates that the question of `com......
  • In re NJ Affordable Homes Corp.
    • United States
    • U.S. Bankruptcy Court — District of New Jersey
    • November 8, 2013
    ...from an absent . . . party does not render that absentee indispensable pursuant to Rule 19." Bank of Am. Nat'l Trust & Sav. Ass'n v. Hotel Rittenhouse Assocs., 844 F.2d 1050, 1054 (3d Cir. 1988) (citation omitted). The Defendants claim to be harmed by the Amended PIO Order, which prevents s......
  • Huber v. Taylor
    • United States
    • U.S. District Court — Western District of Pennsylvania
    • April 27, 2007
    ...that of the public in avoiding repeated lawsuits on the same essential subject matter." Bank of Am. Nat'l Trust & Says. Assoc. v. Hotel Rittenhouse Associates, 844 F.2d 1050, 1055 n. 5 (3d Cir. 1988) (citing Fed.R.Civ.P. 19(a) Advisory Committee note to the amended As plaintiffs correctly p......
  • Request a trial to view additional results
1 books & journal articles
  • EXPLORING THE INDISPENSABLE PARTY: A SURVEY OF COMMON CONTEXTS FOR RULE 19 CLAIMS.
    • United States
    • Environmental Law Vol. 50 No. 3, June 2020
    • June 22, 2020
    ...even though other partners presumably sought the same outcome). (157) Bank of Am. Nat. Tr. & Sav. Ass'n v. Hotel Rittenhouse Assocs., 844 F.2d 1050, 1054 (3d Cir. 1988) ("A defendant's right to contribution or indemnity from an absent non-diverse party does not render that absentee indi......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT