Basin Operating Co., Ltd. v. Valley Steel Products Co.

Decision Date20 July 1981
Docket NumberNo. 20504,20504
Citation620 S.W.2d 773
PartiesBASIN OPERATING CO., LTD., et al., Appellants, v. VALLEY STEEL PRODUCTS CO., Appellee.
CourtTexas Court of Appeals

Tom B. Ramey, Jr., Mike Hatchell, Ramey, Flock, Hutchins, Jeffus, McClendon & Crawford, Tyler, for appellants.

James A. Kilgore, Kilgore & Kilgore, Dallas, for appellee.

Before GUITTARD, C. J., and AKIN and STOREY, JJ.

GUITTARD, Chief Justice.

This litigation began as a suit by Valley Steel Products Company against Basin Operating Company, Ltd. for a debt arising from Basin's purchase of certain pipe used in drilling oil and gas wells. This claim is not disputed except with respect to Basin's liability for prejudgment interest. The principal question in the case arises from Basin's counterclaim for breach of warranty with respect to other pipe purchased by Basin from a third party, which, in turn, ordered it from Valley. Certain individuals designated "third-party plaintiffs" (although they are more nearly in the position of intervenors) joined with Basin in the counterclaim, apparently on the theory that as investors and owners along with Basin of the well in which the warranted pipe was used, they were the real parties in interest in purchasing the warranted pipe and in claiming damages for breach of the warranty. A jury trial on the issues raised by the counterclaim resulted in a verdict favorable to Basin and its investors. The court rendered judgment for Valley against Basin on the main claim, together with prejudgment interest, but disregarded certain jury findings and rendered judgment for Basin and its investors in an amount unsatisfactory to them. Valley has filed cross-points asserting that all recovery on the counterclaim should be denied. We conclude that the court erred in disregarding the jury findings. Consequently, we reverse the judgment and remand the cause with instructions to render judgment on the verdict.

Factual Background

The principal controversy is raised by disputed inferences and opinions based on facts established without dispute. Basin is a limited partnership which undertook the drilling of a well in the Douglas Field in Nacogdoches County. The "third-party plaintiffs" had invested in this enterprise, but were not members of the limited partnership. Because of the depth of the proposed well and certain techniques anticipated for fracturing the gas-bearing formation, Basin required pipe capable of withstanding high internal pressures. It ordered the pipe from Bell Supply Company, which, in turn, ordered it from Valley. On a direct inquiry by Basin's engineer, Valley's representative gave assurance that the pipe ordered was a grade of pipe capable of withstanding high internal pressures. Valley delivered the pipe directly to Basin. Each joint of pipe was stenciled "Test 7,000."

After the well was drilled to the prescribed depth, the pipe was cemented in the hole. When a preliminary pressure test was made, one joint of the pipe burst at approximately 4,400 pounds per square inch. At some expense the failed joint, which was above the cemented section, was cut out and the pipe was reconnected. Another test was undertaken, with similar results. Basin then removed and replaced most of the pipe above the cement, but decided that since it could not remove the cemented pipe, the high-pressure fracturing operation could not be safely carried out. Accordingly, it undertook a diminished fracturing operation at a lower pressure. This operation was not successful in obtaining production in paying quantities. Consequently, Basin abandoned operations at that depth and completed a shallower well producing a relatively small volume of gas. The counterclaim asserts damages for the cost of repairing the damages caused by the failure of the pipe on the two tests and also for its loss of the income which it would have realized from the well if the fracturing operation had been accomplished as originally planned.

In response to special issues, the jury found that Valley failed to test the pipe at seven thousand pounds per square inch pressure before delivering it to Basin (issue seven), that the bursting of the pipe on the pressure tests was a proximate cause of Basin's inability to complete the well as a commercial gas well at the depth originally planned (issue eight), that $150,000 would reasonably compensate Basin for its inability to complete the well as a commercial gas well at that depth (issue nine), and that the reasonable and necessary cost to Basin of the remedial work done on the well as a proximate result of the bursting of the pipe was $61,000 (issue ten).

Valley filed a "motion for relief with respect to judgment," asserting that the jury's findings in answer to issues seven, eight, and nine should be disregarded for lack of evidence to support them and, accordingly, that Basin and its investors be denied recovery of the $150,000 damages found. The motion prays that any recovery of damages because of the remedial work be limited to approximately $56,000.

The trial court granted Valley's motion, denied recovery of the $150,000 damages found by the jury, but rendered judgment for Basin and its investors in proportion to their interests for $54,634.23 and for an attorney's fee in an amount found by the court. The damages of the individual investors were trebled under the Deceptive Trade Practices Act. Valley was awarded judgment against Basin for $24,907.40, the uncontested amount of the original debt, with interest from January 1, 1976. Basin and its investors have appealed, and Valley has filed cross-points complaining of the trebling of the damages awarded to the investors.

Evidence Supporting Findings

Basin and its investors contend that the court erred in disregarding the jury's findings to issues seven, eight and nine because there is evidence to support these findings. Valley responds that these issues were properly disregarded because there is no evidence of a causal relation between its failure to test the pipe, if it did fail, and Basin's failure to obtain commercial production as a result of the fracturing operation. We recognize that there is no direct evidence of Valley's failure to test the particular joints of pipe that burst, of the causal relation between the failure of the pipe and the failure of the well, or of the value of the well if a fracturing operation had been carried out as originally planned. The findings rest on inferences and opinions, but we cannot say that these inferences and opinions, when contrary inferences and opinions are disregarded, do not form a reasonable basis for the findings. Garza v. Alviar, 395 S.W.2d 821, 824 (Tex.1965). Consequently, we hold that there was at least some evidence to support the jury's findings. In this connection we note that Valley does not complain that the charge did not submit the correct measure of damages.

Valley urges certain "counter-points and cross-points" asserting that the court correctly disregarded the findings in answer to issues seven, eight and nine because these findings were "against the great weight and preponderance of the evidence." Valley's counsel argues that these points are proper under the following provision of rule 324 of the Texas Rules of Civil Procedure When judgment is rendered non obstante veredicto or notwithstanding the findings of a jury on one or more special issues, the appellee may bring forward by cross-point contained in his brief filed in the Court of Civil Appeals any ground which would have vitiated the verdict or would have prevented an affirmance of the judgment had one been rendered by the trial court in harmony with the verdict, including although not limited to the ground that one or more of a jury's findings have insufficient support in the evidence or are against the overwhelming preponderance of the evidence as a matter of fact, ....

However, Valley does not pray that the cause be remanded for a new trial on these grounds, and on oral argument, counsel expressly disavowed any request for a new trial.

In this state of the record, we cannot consider any of these cross-points. If there is some evidence (more than a scintilla) supporting the jury's finding, the trial judge cannot properly disregard it in rendering...

To continue reading

Request your trial
16 cases
  • Darisse v. Nest Labs, Inc.
    • United States
    • U.S. District Court — Northern District of California
    • 15 Agosto 2016
    ...133417, at *7 (Nov. 3, 1989); Collins Co., Ltd. v. Carboline Co., 532 N.E.2d 834, 834 (Ill. 1988); Basin Operating Co. v. Valley Steel Prods. Co., 620 S.W.2d 773, 777 (Tex. Civ. App. 1981). The reliance element of a claim for breach of express warranty also differs across the states. In Cal......
  • Fazio v. Cypress/GR Houston I, L.P.
    • United States
    • Texas Court of Appeals
    • 5 Abril 2013
    ...v. Brummerhop, 840 S.W.2d 624, 628 (Tex.App.-Houston [14th Dist.] 1992, writ denied); Basin Operating Co. v. Valley Steel Prods. Co., 620 S.W.2d 773, 776 (Tex.Civ.App.Dallas 1981, writ ref'd n.r.e.). In applying these standards, I would hold that the trial court improperly granted the JNOV.......
  • Cathey v. Meyer
    • United States
    • Texas Court of Appeals
    • 4 Agosto 2003
    ...whether there is more than a mere scintilla of evidence to support the jury's finding. Basin Operating Co. v. Valley Steel Products, 620 S.W.2d 773, 776 (Tex.Civ.App.-Dallas 1981, writ ref'd n.r.e.); see Farias v. Laredo Nat'l Bank, 985 S.W.2d 465, 470 (Tex.App.-San Antonio 1997, no writ); ......
  • Control Solutions, Inc. v. Gharda USA, Inc.
    • United States
    • Texas Court of Appeals
    • 29 Noviembre 2012
    ...cross-points showing grounds for a new trial. M.N. Dannenbaum, Inc., 840 S.W.2d at 628;Basin Operating Co. v. Valley Steel Prods. Co., 620 S.W.2d 773, 776 (Tex.Civ.App.-Dallas 1981, writ ref'd n.r.e.); see also Beckman, 305 S.W.3d at 15–16 (holding that we must uphold jury's verdict and not......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT