Bedrock Foundations, Inc. v. Geo. H. Brewster & Son, Inc.

Decision Date09 November 1959
Docket NumberNo. A--2,A--2
Citation155 A.2d 536,31 N.J. 124
PartiesBEDROCK FOUNDATIONS, INC., a corporation of New York, and Saul T. Grand (Joint Venture), Plaintiffs-Respondents, v. GEO. H. BREWSTER & SON, INC., a corporation of New Jersey, Defendant-Appellant and Third-Party Plaintiff-Respondent (Morris Goodkind, Karl T. Thomas, Curtis D. Weller and Lawrence Peterson, Third-Party Defendants-Appellants).
CourtNew Jersey Supreme Court

John J. Breslin, Jr., Hackensack, argued the cause for defendant-appellant and third-party plaintiff-respondent (Breslin & Breslin, Hackensack, attorneys).

David M. Satz, Jr., Deputy Atty. Gen., argued the cause for third-party defendants-appellants (David D. Furman, Atty. Gen., attorney).

Joseph Bigel, Newark, argued the cause for plaintiffs-respondents (Bruck & Bigel, Newark, attorneys).

The opinion of the court was delivered by

JACOBS, J.

The Law Division denied motions for summary judgment by the defendant Geo. H. Brewster & Son, Inc. and the third-party defendants Morris Goodkind et al. Their appeals, pursuant to leave, are now before this court.

In March 1955 the State Highway Department entered into a contract with the corporate defendant (Brewster) for certain construction on Route 42, Section 12--B, North-South Freeway, from Station 212 to Route U.S. 130. In May 1955 Brewster subcontracted to the plaintiffs (Bedrock) the job of installing pilings in conjunction with three bridge projects along the route. The subcontract incorporated by reference the conditions of the main contract between Brewster and the Highway Department and the Department's Standard Specifications and Supplementary Specifications for Road and Bridge Construction. Bedrock began its pile driving operations using a No. 1 Vulcan Steam Hammer and when it had driven the timber piles to a depth of 15 feet it states that it reached a point of 'practical refusal' which it defines as the point the piles could not longer be struck by the hammer without splintering and 'brooming.' The third-party defendant Goodkind, who was then Director and Chief Bridge Engineer of the State Highway Department, was of the opinion that the safety of the bridge being constructed required a penetration of 25 feet rather than 15 feet. He directed that if necessary to obtain such penetration, a water jet in combination with the pile hammer be used. That was done, the penetration of 25 feet was obtained, and the work was completed.

Bedrock claimed that the extra penetration of 10 feet entailed additional labor and materials not contemplated by its subcontract with Brewster and for which it was entitled to extra compensation. Brewster submitted the claim to the Highway Department which rejected it in a letter dated March 23, 1956. Thereafter Bedrock filed a complaint in the Law Division against Brewster. In its first count it sought recovery of $20,917.63 on a book account. This amount was subsequently paid and the count was dismissed. In its second count it sought a contract or Quantum meruit recovery of $58,502.71 for the extra work done and extra material furnished to obtain the increased penetration. In its third and fourth counts it repeated its claim of $58,502.71 alleging that Brewster had 'illegally, arbitrarily and fraudulently' required it to perform the extra work and furnish the extra material and had arbitrarily, illegally and fraudulently conspired with representatives of the Highway Department to prevent it from completing its contract until it performed the extra work and furnished the extra material. On April 24, 1957 Bedrock filed an amended complaint which undertook to specify the alleged illegal, arbitrary and fraudulent conduct and which designated the representatives of the Highway Department as Morris Goodkind, aforementioned, Karl T. Thomas, Senior Bridge Inspector, Curtis D. Weller, District Bridge Engineer, and Lawrence Petersen, Director and Chief Bridge Engineer.

Brewster filed an answer and counterclaim in which it alleged that Bedrock had not performed its subcontract and had instituted its action maliciously and without foundation. Thereafter Bedrock moved for an order granting summary judgment and striking the counterclaim but its motion was denied. Brewster then moved for leave to file a third-party complaint against Goodkind, Thomas, Weller and Petersen alleging that the extra work done and extra material furnished by Bedrock was at their insistence and that they should consequently pay any judgment which might be entered in favor of Bedrock against Brewster. The motion to file the third-party complaint was granted and was followed by a motion for summary judgment by the third-party defendants. The trial court denied their motion and leave to appeal was granted to them by the Appellate Division. While their appeal was pending, this court certified it on its own motion and suggested that Brewster move for summary judgment in the trial court. Brewster did so but its motion was denied and it thereafter took an appeal which has been argued in this court along with the appeal of the third-party defendants.

Brewster contends that under the terms of the subcontract, Bedrock was not entitled to any extra compensation for the penetration from 15 to 25 feet. It refers primarily to Article 4.4.3 of the Standard Specifications which reads, in part, as follows:

'Foundation piles have been designed to carry a certain load, and a certain pile length, based on available information of the subsurface conditions, has beem assumed in preparing the estimate of quantity. All piles, however, unless otherwise directed, shall be driven to practical refusal as determined by the Engineer, and the contractor shall determine the actual length of untreated timber piles required by driving test piles of greater length than that assumed in the estimate.'

Brewster points out that Bedrock's subcontract lists the various linear footages which are the total lengths of the various types of piling called for by the contract and that by dividing this figure by the number of piles to be driven the approximate length of the piles is readily computed to be approximately 25 feet; and it stresses the Engineer's determination that the contemplated penetration of 25 feet was necessary for the safety of the bridge. On the other hand Bedrock points out that Article 4.4.3 provides that 'Timber piles shall be driven with a gravity or a steam hammer or, if permitted by the Engineer with a combination of hammer and water jet' and that the timber piles in the instant matter were driven by hammer to 15 feet, a point of practical refusal; it contends that the Engineer did not determine that the 15 feet was not a point of practical refusal but directed a deeper penetration notwithstanding that practical refusal had been obtained.

Brewster places additional reliance on provisions in the Supplemental Specifications which Bedrock contends are inapplicable. It refers to Article 4.4.3 which contains a provision that 'All concrete piles are to be driven with a steam hammer having a capacity sufficient to produce a penetration satisfactory to the Engineer,' and also a provision that 'If the required penetration cannot be obtained by the use of a hammer the contractor shall provide for jetting at his own expense.' Bedrock contends that these provisions apply only to concrete piles and have no application to timber piles. Article 4.4.4 provides that 'The contractor shall not make any claim for additional compensation due to any increase or decrease in listed quantity of bearing piles or due to the use of water jets in driving piles.' Bedrock contends that this Article was merely intended to prevent extra compensation if water jet was used to perform the terms of the contract; thus, if water jet were used to reach practical refusal it could not seek added compensation but, it urges, it would be entitled to compensation for proceeding beyond practical refusal 'whether water jet, hammer or pick or shovel were used.'

Although Bedrock urges that practical refusal, as used in the Specifications, means the point at which the piles could no longer be struck by the hammer without brooming, the Attorney General advances a different meaning. He states that practical refusal if done with a hammer 'might mean one particular depth as a result of tests determining a certain minimum penetration with a given number of blows' whereas if jetting is used 'practical refusal can be reached at any depth.' He suggests that Article 4.4.3 'calls for penetration to the point of practical refusal as a mere adjunct to the overall requirement of penetration to the particular depth as required by needs of safety.' Unfortunately, the Specifications contain no definition whatever of practical refusal and the materials before us on the motions for summary judgment do not embody suitable testimony as to the pertinent trade customs, usages and meanings. Brewster contends that the provision in Article 4.4.3 to the effect that the piles shall, 'unless otherwise directed,' be driven to practical refusal as determined by the Engineer placed on Bedrock the responsibility of making, without claim for extra compensation, additional penetration when directed by the Engineer; Per contra it has been urged that the responsibility of Bedrock under Article 4.4.3 was to reach practical refusal although the Engineer might direct a lesser penetration when he found that sufficient.

The Law Division judge suggested that under Brewster's contention Bedrock assumed 'an apparently limitless performance in consideration of a fixed sum.' He raised question as to whether that was the design and expressed the view that the Specifications were ambiguous and that 'the intent of the parties must be left to factual determination.' He concluded that final disposition of the matter on motion for summary judgment would be inappropriate and (except as hereinafter indicated) we see...

To continue reading

Request your trial
43 cases
  • Snyder v. American Ass'n of Blood Banks
    • United States
    • New Jersey Supreme Court
    • June 4, 1996
    ...functions, protecting it from liability "providing what [it] do[es] is done in good faith." Bedrock Foundations, Inc. v. Geo. H. Brewster & Son, Inc., 31 N.J. 124, 142, 155 A.2d 536 (1959) (quoting Johnson v. Marsh, 82 N.J.L. 4, 85 A. 761 (Sup.Ct.1912)). See also Bombace v. City of Newark, ......
  • Matter of Bevill, Bresler & Schulman Asset
    • United States
    • U.S. District Court — District of New Jersey
    • October 23, 1986
    ...the introduction and examination of extrinsic evidence of intent as an aid in interpretation. Bedrock Foundations, Inc. v. Geo. H. Brewster & Son, Inc., 31 N.J. 124, 133, 155 A.2d 536 (1959); 67 Wall Street Co. v. Franklin National Bank, 37 N.Y.2d 245, 248-49, 371 N.Y.S.2d 915, 333 N.E.2d 1......
  • Buckley & Co., Inc. v. State
    • United States
    • New Jersey Superior Court
    • July 30, 1975
    ...59:13--3. There appear to be no reported New Jersey decisions passing on these issues (cf. Bedrock Foundations, Inc. v. Geo. H. Brewster & Son, Inc., 31 N.J. 124, 137, 155 A.2d 536 (1959)); but, except for the question of statutory interpretation, to be discussed presently, they have been r......
  • Hickox v. Christie
    • United States
    • U.S. District Court — District of New Jersey
    • September 2, 2016
    ...by the New Jersey courts. See Valentine v. Englewood , 76 N.J.L. 509, 71 A. 344 (E. & A.1908) ; Bedrock Foundations, Inc. v. George H. Brewster & Son, Inc. , 31 N.J. 124, 155 A.2d 536 (1959).Id. This section appears to apply directly to quarantine decisions like the one taken here.19 The im......
  • Request a trial to view additional results
1 books & journal articles
  • Qualified and Absolute Immunity at Common Law.
    • United States
    • Stanford Law Review Vol. 73 No. 6, June 2021
    • June 1, 2021
    ...Gray, supra note 160, at 342 & n.246 (collecting cases); see also, e.g., Bedrock Founds., Inc. v. Geo. H. Brewster & Son, Inc., 155 A.2d 536, 544-45 (N.J. 1959) (retaining the common law's qualified immunity good-faith defense while expressly rejecting the approach taken during that......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT