Bell v. Westinghouse Elec. Corp.

Decision Date30 October 1984
Docket NumberNo. 84-133.,No. 84-134.,84-133.,84-134.
Citation483 A.2d 324
PartiesPatricia Ann BELL, Appellant, v. WESTINGHOUSE ELECTRIC CORPORATION, Appellee. WESTINGHOUSE ELECTRIC CORPORATION, Appellant, v. Patricia Ann BELL, Appellee.
CourtD.C. Court of Appeals

Charles C. Parsons, Washington, D.C., for appellant.

Philip J. Walsh, Washington, D.C., for appellee.

Before PRYOR, Chief Judge, and NEBEKER and TERRY, Associate Judges.

PRYOR, Chief Judge:

These are cross-appeals from a final judgment following an order granting a new trial in a personal injury action. Plaintiff seeks to reinstate a $65,000 jury verdict in her favor. Defendant has cross-appealed.1 We conclude that the trial court abused its discretion in granting a new trial. Hence, we remand for reinstatement of the jury verdict.

On April 9, 1979, the plaintiff, Mrs. Patricia A. Bell, suffered injuries when her foot suddenly became caught in Escalator Number Five at the Eastern Market Metrorail Station, causing her to fall. Escalator Number Five was manufactured by Westinghouse Electric Corporation ("Westinghouse"), which purportedly maintained the apparatus pursuant to a service contract with Washington Metropolitan Area Transit Authority ("WMATA"). On November 9, 1979, plaintiff commenced a civil action (No. 14410-79) against both WMATA and Westinghouse seeking to hold both defendants jointly and severally liable for the injuries she sustained in the escalator incident. WMATA filed an answer to the complaint and a cross-claim against Westinghouse; Westinghouse also answered but never filed any cross-claim against WMATA. On December 2, 1981, the initial date set for trial, WMATA moved to dismiss the complaint against it for lack of jurisdiction. Westinghouse did not oppose this motion. The court granted WMATA's motion on the ground that the United States District Court for the District of Columbia had exclusive jurisdiction over actions brought against WMATA. On January 25, 1983, trial commenced on plaintiff's personal injury claim against Westinghouse as sole defendant. Westinghouse interposed no objection to the action commencing solely against it.

On January 26, 1983, this court rendered its decision in Qasim v. Washington Metropolitan Area Transit Authority, 455 A.2d 904 (D.C.1983), holding that in addition to the specific grant of original jurisdiction found in the Washington Metropolitan Area Transit Authority compact, the Superior Court for the District of Columbia also has jurisdiction over actions brought against WMATA. Westinghouse immediately moved for a mistrial which the court denied without prejudice. The next day, the jury returned a $65,000 verdict for plaintiff against Westinghouse.

After trial, Westinghouse filed a timely motion seeking, in the alternative, a judgment n.o.v., a new trial, or a remittitur. Among other things, Westinghouse argued that a new trial was appropriate because it had been "prejudiced" by the absence of WMATA at trial. The trial court agreed and granted a new trial. The court did this before plaintiff had had an opportunity to oppose the motion. After plaintiff moved for reconsideration of the trial court's ruling, the court entered an order reaffirming its earlier grant of a new trial. Since plaintiff took no steps to have WMATA reinstated as a defendant, and since Westinghouse did not file a third-party complaint against WMATA, the action proceeded to a second trial against Westinghouse alone. At the second trial, Mrs. Bell put on minimal evidence and a directed verdict resulted against her. These cross-appeals followed.

On appeal, Mrs. Bell seeks reversal of the order granting a new trial and reinstatement of the jury verdict. She asserts that Westinghouse was not prejudiced by the dismissal of WMATA before trial because WMATA was not an indispensable party. Westinghouse claims that it was prejudiced so as to justify a new trial. It also asserts that the trial court should have granted a new trial because the jury had been improperly instructed on the doctrine of res ipsa loquitur.

I

Super.Ct.Civ.R. 59 broadly sets forth the criteria for granting a new trial:

(a) GROUNDS. A new trial may be granted to all or any of the parties and on all or part of the issues (1) in an action in which there has been a trial by jury, for any of the reasons for which new trials have heretofore been granted in actions at law in the courts of the United States or of the District of Columbia. . . .

New trials may be granted, for example, where the verdict is against the weight of the evidence, damages are excessive, the trial was unfair, or there was a prejudicial legal error in the proceedings. Baber v. Buckley, 322 A.2d 265, 266 (D.C. 1974); 11 WRIGHT & MILLER, FEDERAL PRACTICE AND PROCEDURE § 2805, at 37-38 (1978).

It is generally held that a trial court has the power to order a new trial when such action is needed to "prevent injustice." 11 WRIGHT & MILLER, supra, § 2805, at 38. The granting of such a motion is within the discretion of the trial court and the scope of appellate review is limited to determining whether there has been an abuse of discretion.2 Baber v. Buckley, supra, 322 A.2d at 266. Notwithstanding this broad grant of discretion we conclude that the trial court's grant of a new trial was error.

A.

Westinghouse asserted in its motion for a new trial, and continues to assert on appeal, that it was prejudiced by WMATA's dismissal, as that dismissal relates to plaintiff's use of the doctrine of res ipsa loquitur.3 Westinghouse and WMATA were alleged to be joint tortfeasors. Westinghouse argues that had WMATA been a party to the first trial the jury could have considered the respective liabilities of both WMATA and Westinghouse under the res ipsa loquitur doctrine. Joint tortfeasors, however, are precluded from using res ipsa loquitur against each other, as a basis for indemnification or contribution. Washington Sheraton Corp. v. Keeter, 239 A.2d 620, 622 (D.C.1968). Therefore, if Westinghouse institutes a separate action against WMATA for indemnity or contribution, it will be required to prove a specific act of negligence on the part of WMATA in order to recover.4 We conclude that this claim of prejudice is without basis. Any benefit Westinghouse would have received from plaintiff's use of res ipsa loquitur against WMATA was a tactical benefit arising from plaintiff's election to sue both joint tortfeasors. Losing this tactical benefit did not amount to denial of a legal right, and, accordingly, does not constitute the kind of prejudice which justifies setting aside a jury verdict and granting a new trial.

Indeed, this approach would preclude a plaintiff in a negligence action, where more than one tortfeasor is allegedly involved, from using the res ipsa loquitur doctrine unless all tortfeasors were joined in the litigation. We have never held that use of the doctrine should be limited in this way. Cf. Washington Sheraton Corp. v. Keeter, supra, 239 A.2d at 622, citing Greet v. Otis Elevator Co., 187 A.2d 896, 898 (D.C.1963). The impact of Westinghouse's position would be to alter the long-standing rule that it is a plaintiff's prerogative to choose among tortfeasors in deciding whom to sue. See, e.g., Ewald v. Lane, 70 App.D.C. 89, 104 F.2d 222 (1939); Gale v. Independent Taxi Owners Ass'n, 65 App.D.C. 396, 84 F.2d 249 (1936).

Westinghouse's subtantive right of indemnification or contribution has in no way been affected by Mrs. Bell's jury verdict. See Hall v. General Motors Corp., 207 U.S.App.D.C. 350, 360, 647 F.2d 175, 185 (1980) (pre-trial settlement between plaintiff and one joint tortfeasor does not deprive other tortfeasor of genuine contribution); Knell v. Feltman, 85 U.S.App. D.C. 22, 24, 174 F.2d 662, 664 (1949) (joint judgment against tortfeasors not a prerequisite to contribution between them). Westinghouse has not articulated to this court what it believes its rights are against WMATA. Since we do not know whether Westinghouse's theory of recovery sounds in tort or contract we do not have to reach the issue raised in General Elevator Co. v. District of Columbia, 481 A.2d 116 (D.C. 1984).

B.

Secondly, Westinghouse moved for a new trial on a general assertion of prejudice. To date, Westinghouse implies but has never directly asserted that WMATA was an indispensable party, under Super.Ct.Civ.R. 19(a),5 at the first trial.6 If WMATA had been an indispensable party, its improper dismissal from the case before trial would constitute the kind of prejudicial legal error that would justify granting Westinghouse a new trial. It is an established rule, however, that joint tortfeasors are not indispensable parties. See Super.Ct.Civ.R. 19(a); Stabilisierungsfonds Fur Wein v. Kaiser Stuhl Wine Distributors Pty. Ltd., 207 U.S.App.D.C. 375, 647 F.2d 200 (1981); Debbis v. Hertz Corp., 269 F.Supp. 671 (D.Md.1967); cf. 3A MOORE, FEDERAL PRACTICE ¶ 19.07 [1] (3d ed.1979) ("Rule 19 must be read together with Rule 14 which quite clearly permits the defendant to implead a person who may be liable to him for all or part of any judgment against him but does not require that he do so." (Emphasis added)).

A party is prejudiced at trial when a legal ruling adversely affects its legal rights. Since WMATA was not an indispensable party, Westinghouse had no right to have WMATA joined as a defendant. Accordingly, WMATA's dismissal from the case7 was not an error which prejudiced Westinghouse.

We observe that in its order the trial court stated:

[T]he inconvenience and expense of a new trial is outweighed by the prejudice suffered by the defendant Westinghouse through the initial dismissal of WMATA as a party, and the eventual single defendant trial.

This balancing was inadequate since the trial court neglected to also weigh the plaintiff's very significant interest in not having her jury verdict set aside. Moreover, as previously stated, Westinghouse...

To continue reading

Request your trial
28 cases
  • Wash. Metro. Area Transit Auth. v. Davis
    • United States
    • D.C. Court of Appeals
    • April 3, 1992
    ...Accordingly, we hold that the trial judge erred by denying the District's motion for a new trial. Accord, Bell v. Westinghouse Electric Corp., 483 A.2d 324, 328-29 (D.C. 1984) (in reversing grant of new trial, court distinguished between prejudicial legal error and loss of a tactical benefi......
  • Bell v. Westinghouse Electric Corporation
    • United States
    • D.C. Court of Appeals
    • April 14, 1986
    ...trial court ruled incorrectly, we reverse and remand. I The facts of the underlying action are recited in Bell v. Westinghouse Electric Corp., 483 A.2d 324, 326 (D.C. 1984) (Bell I). We summarize only the procedural history pertinent to this second On January 27, 1983, a jury awarded appell......
  • LYONS v. BARRAZOTTO
    • United States
    • D.C. Court of Appeals
    • October 31, 1995
    ...verdict if it is against the clear weight of the evidence. See Washington, supra, 584 A.2d at 545; see also Bell v. Westinghouse Elec. Corp., 483 A.2d 324, 327 & n. 2 (D.C. 1984). A new trial may also be granted if "damages are excessive, the trial was unfair, or there was a prejudicial leg......
  • Twyman v. Johnson
    • United States
    • D.C. Court of Appeals
    • March 13, 1995
    ...Otis Elevator Co. v. Tuerr, 616 A.2d at 1258; Otis Elevator Co. v. Henderson, 514 A.2d 784, 785-86 (D.C.1986); Bell v. Westinghouse Elec. Corp., 483 A.2d 324, 329 (D.C.1984).6 That principle was neither pled nor presented to the jury in this case, and our holding that Twyman failed to link ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT