Beltline, Inc. v. Powell

Decision Date06 June 1979
Citation371 So.2d 920
PartiesBELTLINE, INC. v. Clarence POWELL. Civ. 1473.
CourtAlabama Court of Civil Appeals

Richard W. Moore of Marr & Friedlander, Mobile, for appellant.

Thomas M. Galloway, Jr. of Collins, Galloway & Smith, Mobile, for appellee.

BRADLEY, Judge.

This appeal arises from a jury verdict assessing damages in the amount of $6,221 for the plaintiff-appellee, Clarence Powell.

A complaint was filed by Powell consisting of two counts. The first count claimed the defendant-appellant, Beltline, Inc. (hereinafter Beltline) and Ray Sumlin Construction Company owed him $6,506 for work and labor done and materials supplied at the defendants' request at Place Levert. Count two claimed he was owed $350 for work and labor done and materials supplied at the defendants' request at 160 South McGregor Avenue, Mobile Alabama. These allegations were answered as untrue and the defendants claimed they were not indebted.

Beltline filed a counterclaim demanding $6,500 as damages. The counterclaim stated Powell and Beltline entered into a contract and Powell agreed to put in asphalt driveways in Place Levert and Beltline agreed to pay $4,682 for the work. Furthermore, Beltline averred Powell agreed to do work according to plans furnished; Beltline paid Powell $4,000; and Powell either failed or refused to complete the work, or so damaged the property that extensive repairs must be done to complete the job according to the plans.

Oral testimony reveals there was an oral contract between Beltline and Powell for the asphalt paving of a parking lot at Place Levert, a condominium project. Ray Sumlin, a major stockholder in Beltline, said the agreed price for the work was between $4,700 and $4,800. Powell testified the agreed price for the Place Levert job was $4,853. Powell also agreed to pave a driveway at Dr. Martinson's residence for $305.

Powell testified he never saw any plans or specifications for the Place Levert job. Mr. Sumlin testified he did not know whether plans had been delivered; but said Powell had access to the plans and Skelton, supervisor of the project, claimed there were plans on the jobsite.

Powell claimed Skelton called all the shots on the blue top hubs that were set for the grading of the parking lot at the Place Levert job, and when the hubs were set he graded to the hubs. Skelton claimed he set only a few and was relieved of responsibility by his employer. Powell remembered nothing about Skelton being relieved and claims Skelton was with him the entire job.

Skelton said catch basins for water drainage were in Before Powell began the job. Powell said that after he had graded one way, the catch basins were put in and he had to then totally change the grade.

Skelton testified curbs around a parking island were put in After Powell first paved the lot. Powell testified one or two days after he paved the lot the first time, cement trucks came in to put the curbs in and the asphalt gave way, thus causing ruts in the asphalt. Skelton testified the curbs were not put in the day after the initial paving because there is a certain waiting period for the asphalt; however, Skelton did not have any idea as to how long the waiting period was.

Powell said he fixed the places where the trucks had been and all the holes that were driven in the asphalt by "two by four" stakes used to make the curbs around the island. He further testified he had to go over the entire job a second time at Beltline's request, and used about the same amount of asphalt for the second job. Skelton testified Powell merely patched places where water stood in the lot.

A check from Beltline in the amount of $4,000, dated July 18, 1974, made payable to Powell, was received by Powell after the work was done. Powell did not question the amount of the check at that time; although Powell testified he expected to be paid for the extra work he did. It is undisputed Powell never sent Sumlin an invoice for the amount of the extra work done.

Sumlin testified after Powell finished the job, there were water drainage problems. Water stood in the parking lot anywhere from an inch to an inch and a quarter. Beltline added another catch basin and pipe to help the drainage problem after Powell paved the lot the second time.

Powell's opinion as to the reasonable value of his services performed in the "repairing" of the lot at Place Levert was that of the original contract price, namely, $4,853.

In regard to the Martinson paving job, Sumlin testified he did not pay Powell for it because Powell did a bad job. Powell said the job was done in a workmanlike manner and his men went back to put sealer over the job and to make a few changes.

An estimate of the costs for Beltline to fix the asphalt so it would drain correctly was set at $6,500.

At the close of the defendant's evidence, Powell moved for a directed verdict. Such motion was denied.

The trial court gave instructions to the jury. Part of the instructions stated:

The Plaintiff has sued on a contract and for work and labor done. And, the Defendant has filed a counterclaim in the case.

. . . If the Plaintiff performed this contract in a good and workmanlike manner then he would be entitled to recover the Contract price agreed upon between the parties. The Plaintiff would Also be entitled to recover extras ; that is, extra work done by him. If such work was done either at the request of the Defendant or by actions or conduct of the Defendant necessitating extra work and accepted by the Defendant. Of course, the Plaintiff would not be entitled to recover for any extra work done by him, if the work should have been done in the first instance under any contract. (Emphasis added.)

He also told the jury they were entitled to award interest for either the plaintiff or the defendant at the rate of six percent per annum. An objection was made by the defendant, Beltline, to the instruction that a "suit had been filed for a contract . . . and for work and labor done." The ground for objection was that the only count in the case was for work and labor done. Further objection was made to the charge that the "jury . . . could return a verdict . . . on the agreed price of the contract." Ground for the second objection was the correct measure for work and labor cases is a reasonable value of the services performed.

Two issues come before us for review: (1) whether the trial court's charge to the jury that the plaintiff had sued on a contract and for work and labor done was reversible error; and (2) whether the jury verdict was excessive and against the great weight of the evidence.

Beltline claims the instruction given the jury is erroneous and misleading. Beltline argues the complaint failed to allege contract and was never formally amended; therefore, the only count upon which Powell could recover is for "work and labor done." Beltline further argues a special contract is not admissible to prove the reasonable value for work and labor done beyond the terms of the contract. Lastly, Beltline claims the instruction was correct as to the Martinson job...

To continue reading

Request your trial
3 cases
  • Johnson v. Kersh
    • United States
    • Alabama Court of Civil Appeals
    • 1980年11月19日
    ...393, 304 So.2d 187 (1974). We find reversible error only if the charge is prejudicial when viewed in its entirety. Beltline, Inc. v. Powell, 371 So.2d 920 (Ala.Civ.App.1979). We find no such prejudice in this Defendants charge error in the instruction of the court as to the measure of damag......
  • Johnson v. Gary L. Jester, P.C.
    • United States
    • Alabama Court of Civil Appeals
    • 2006年5月5日
    ...claim based on the theory of quantum meruit is the reasonable value to the benefactor of the services provided. Beltline, Inc. vs. Powell, 371 So.2d 920, 924 (Ala.Civ.App.1979). "(1) [Johnson] knowingly accepted the legal services provided to her by [Jester]. There is no issue of fact with ......
  • Harbert Intern., Inc. v. Sunbelt Safety & Barricade, Inc.
    • United States
    • Alabama Court of Civil Appeals
    • 1995年8月25日
    ...for similar services is a proper matter to consider in ascertaining the reasonable value of work and labor." Beltline, Inc. v. Powell, 371 So.2d 920, 924 (Ala.Civ.App.1979). Based on the foregoing, we reverse the trial court's judgment and remand the case for a determination of damages base......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT