BEN C. GERWICK, INC. v. Commissioner, Docket No. 38089

Decision Date31 March 1954
Docket NumberDocket No. 38089,39045.
Citation13 TCM (CCH) 314
PartiesBen C. Gerwick, Inc. v. Commissioner.
CourtU.S. Tax Court

Gordon Johnson, Esq., A. Barlow Ferguson, Esq., and Robert L. Bridges, Esq., for the petitioner. T. M. Mather, Esq., for the respondent.

Memorandum Findings of Fact and Opinion

HARRON, Judge:

The Commissioner has determined deficiencies for the years 1945 and 1946, as follows:

                  Docket
                    No.    Year             Tax           Deficiency
                  38089    1945    Income ..............  $ 15,959.12
                                   Declared Value Excess
                                     Profits ...........     1,172.48
                                   Excess Profits ......   546,811.90
                  39045    1946    Income ..............    84,749.54
                

The question to be decided is whether income from a contract with the Navy for the construction of three submarine and destroyer drydocks at Hunters Point, California, which is attributable to work completed and paid for before the end of 1945, is includible in petitioner's income for 1945.

The deficiency for 1946 results from including the income from the same contract in petitioner's income for 1946 solely to protect the Government's interests against the running of the statute of limitations. The parties are agreed that the decision of the question relating to 1945 will enable the parties to dispose of petitioner's income tax liability for 1946 under Rule 50.

The petitioner filed its returns for 1945 and 1946 with the collector for the first district of California.

Findings of Fact

The facts which have been stipulated are found as facts. The stipulations of facts and the attached exhibits are incorporated herein by this reference.

Petitioner is a California corporation, incorporated on January 25, 1926, with its principal office in San Francisco. Since its incorporation, it has been engaged in the construction contracting business, specializing in the construction of piers, wharves, docks, terminals, and foundations for industrial facilities.

Petitioner has at all times regularly and consistently kept its books and reported its income from long-term contracts on the basis provided by Regulations 111, section 29.42-4(b), and the same subsection of prior regulations.

On May 13, 1943, petitioner filed a bid with the Navy Department, Bureau of Yards and Docks, for the construction of three drydocks at the Naval Drydocks at Hunters Point, San Francisco, on a lump sum contract basis. Petitioner's bid was accepted by the Navy, and on June 11, 1943, the United States Government entered into a lump sum contract with petitioner in the amount of $3,684,000. The contract was designated Contract NOy-6183. Under the original contract, petitioner agreed to furnish all necessary material and equipment, and perform all work for providing and securing the construction of three submarine and destroyer drydocks, known as Drydocks Nos. 5, 6, and 7, and auxiliary facilities.

The parties to the original contract understood that the entire project was not covered by plans and specifications completed at the time the contract was signed but that as soon as additional and necessary plans and specifications for the entire contract project were prepared and approved they would be incorporated into and made part of the contract under the "Change Order" procedure. When the contract was signed, only the plans and specifications for foundations and basic drydock structures had been prepared. As the work progressed, the Navy Department issued the so-called "change orders" which called for the progressive construction of the basic project and for the necessary auxiliary facilities such as steam, electric, and air power, closure gates, access to the docks from the shore, and so forth. Forty-three change orders were entered into which amended the original contract and increased the total consideration under the contract to $6,710,290.08.

All of the work under the original contract and most of the change orders was completed before the end of 1945. Work which was not completed was work under Change Order "T", and the work under that order was 92 per cent complete by the end of 1945. The work designated as Change Order "T" was usably complete at the end of 1945 but delay in the completion was occasioned by the unavailability of valves, fittings, and materials, which was beyond petitioner's control. By October 22, 1945, all of the work under the contract had been completed, and 90 per cent of the work under Change Order "T" had been completed. The work under Change Order "T" was completed February 21, 1946.

In the contract and change orders, the price to be paid for each part of the progressive work was stated separately.

Prior to October 22, 1945, payments received by petitioner amounted to $6,510,535.08. By the end of 1945, petitioner had been paid $6,661,490.08 which was the total consideration for the original contract and all change orders except $48,800 representing the balance of the contract price under Change Order "T" in the amount of $30,000, and retained percentages of $18,000. The sum of $48,800 was paid to petitioner on September 5, 1946 under a final voucher dated August 5, 1946. On August 7, 1946, the entire contract work was accepted by the Officer in Charge of Construction.

Under date of August 14, 1945, the Officer in Charge of Construction for the Navy, pursuant to petitioner's request, in its letter of July 30, 1945, accepted the work which had been completed, up to August 14, 1945, relieving petitioner from responsibility and releasing the retained percentage of the moneys previously withheld on such completed work.

Petitioner, in its letter of July 30, 1945, requesting the acceptance of completed work, stated as follows:

"The following resume of the subject contract as amended from time to time is presented herewith with the end in view of immediate final formal acceptance by the Navy Department of all work accomplished to date and also release of Ben C. Gerwick, Inc., of all responsibility for these various constructions now in use by the Federal Government.

"RESUME OF CONTRACT NOy 6183— SUBMARINE AND DESTROYER DRYDOCKS—HUNTERS POINT

                    *Board Report Signed and Sent to
                      Bureau Yards and Docks for Approval
                      of Change
                   **Approximate Only—Board Report Not
                      Complete
                  ***Board Report about Complete
                   Original Contract.........  $3,684,000.00
                   Change `A' —
                     Additional Dredging            7,632.00
                   Change `B' —
                     Dykes and Grading              6,600.00
                   Change `C' —
                     Extend Plug ............      13,500.00
                   Change `D' —
                     Redesigned Motor
                       Generators ...........       2,350.00
                   Change `E' —
                     Terrado Control.........       3,250.00
                   Change `F' —
                     Reinforcing Steel.......      13,200.00
                   Change `G' —
                     Maint. Dredging.........      40,500.00
                   Change `H' —
                     Acceleration of Contract
                       ......................     150,000.00
                   Change `I' —
                     Repair Fender System
                       ......................      11,300.00
                   Change `J' —
                     Dredge Harbor Pier
                       33 ...................      13,200.00
                   Change `K' —
                     Galvanizing ............       4,800.00
                   Change `L' —
                     Ladder Rungs ...........         158.00
                   Change `M' —
                     Pin Markers ............       1,260.00
                   Change `N' —
                     Increase Size of Elec
                       Man Holes ............         500.00
                   Change `O' —
                     Reinforcing Steel By
                       Gov't ................      14,480.12
                   Change `P' —
                     Closure Gates...........     287,200.00
                   Change `Q' —
                     Pressure Cells..........       6,555.00
                   Change `R' —
                     Temp. Elec. Connection
                       ......................         830.00
                   Change `S' —
                     Reinforcing Steel.......       4,350.00
                  *Change `T' —
                     Steam Power Plant            376,000.00
                   Change `U' —
                     Reinforcing Steel.......      12,900.00
                   Change `V' —
                     Mechanical Revisions          55,900.00
                   Change `W' —
                     Torredo Control.........       2,000.00
                   Change `X' —
                     Buy and Equip Barge            8,500.00
                   Change `Y' —
                     Temporary Sewer
                       Connection ...........         460.00
                   Change `Z' —
                     Electrical Work ........     117,600.00
                   Change `A-2' —
                     Temporary Track.........       4,000.00
                   Change `B-2' —
                     Replace Gate Fenders             215.00
                   Change `C-2' —
                     Handrail on Altars             4,400.00
                   Change `D-2' —
                     `A' Changes ............      49,800.00
                   Change `E-2' —
                     Increase in Time
                       Only .................      
                   Change `F-2' —
                     Crane Rental ...........      12,079.80
                   Change `G-2' —
                     Miscellaneous ..........         700.00
                   Change `H-2' —
                     Trackage, Drainage
                       & Paving .............     383,000.00
                   Change `I-2' —
                     Four Misc. Items........       2,610.00
                   Change `J-2' —
                     Rent Bridge ............       4,500.00
                   Change `K-2' —
                     Elec.-Mech. Services
                       South of D. D.'s......     707,000.00
                   Change `L-2' —
                     Purchase Steel Piling        716,400.00
                   Change `M-2' —
                     Erect Two Portal
                       Cranes ...............      35,825.00
                ***Piling Resume—Creosote
                     & Green.................      36,100.00
                ***Gov't. Furnished Material
                     ........................      20,400.00
                 **Furnish Closure Gate
                     Connections ............         400.00
                                               _____________
                   Total Approximated
                     Contract Price..........  $6,708,835.08 sic
                                               =============
                
"The work of the original contract in the amount of $3,684,000.00, merely for the drydock structures devoid of the utilities and services necessary for operation, was completed well within the contract time for completion as twice amended by formal changes. Also completed within this same time was considerable of the additional work now part of the many times amended contract, additional work such as utilities, services, closure gates and approaches, without which the use of the drydocks was
...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT