Biggs v. Clapp
Decision Date | 30 September 1874 |
Citation | 1874 WL 9136,74 Ill. 335 |
Parties | SAMUEL BIGGS et al.v.WILLIAM A. CLAPP et al. |
Court | Illinois Supreme Court |
OPINION TEXT STARTS HERE
APPEAL from the Superior Court of Cook county; the Hon. JOHN A. JAMESON, Judge, presiding.
Messrs. FULLER & SMITH, for the appellants.
Mr. STEPHEN F. BROWN, for the appellees.
This was a petition filed by appellants, in the Superior Court of Cook county, as sub-contractors, against appellees to enforce a mechanic's lien under the act of 1869.
A trial was had before a jury, which resulted in a verdict against appellants. The court overruled a motion for a new trial, and rendered judgment upon the verdict.
To reverse this judgment appellants have prosecuted this appeal, relying mainly upon the ground that the court erred in giving appellees' third instruction, and refusing the first, second and fourth asked by them.
It appears from the evidence contained in the record, that on the 12th day of July, 1872, appellees entered into a contract with J. B. Smith & Son, by which the latter were to furnish the material and erect a certain building for appellees, for $13,300. The building was to be completed on or before the 1st day of September, 1872. By the contract appellees were to pay Smith & Son $1,000 when the walls of the basement were all up and the joists in; $1,500 when the walls of the principal story were up, the iron work set and the joists all in; $1,800 when the walls of the second and third stories were all up and joists all in; $2,000 when the walls were all up, joists all in, partitions set, cornices set and roof on; $2,000 when the floors were all laid and plastering completed; and the balance upon the completion and acceptance of the entire building.
The appellants contracted with J. B. Smith & Son to furnish certain cut stone for the building; appellants furnished the stone as they agreed to do, and there is a balance due them from J. B. Smith & Son, of $1,675. On the 12th of September, 1872, appellants served appellees with notice, under the statute, of a mechanic's lien as sub-contractors; at the time the notice was served, appellees had paid to J. B. Smith & Son, on the contract, $6,300; on the 3d day of October, 1872, by written permission of appellants, appellees paid J. B. Smith & Son, the further sum of $2,000; upon receiving this payment J. B. Smith & Son abandoned the work and appellees were compelled to complete it at an additional cost of $5,500, which made a sum exceeding $500 paid by appellants to complete the building over and above the original contract price.
At the request of appellees, the court gave to the jury an instruction as follows:
It is insisted that the seventh section of the mechanics' lien act of 1869 was entirely ignored by the court by this instruction to the jury.
In other words, as we understand the position of appellants, they claim that under the seventh section, when the original contractor abandons the work and the rights of sub-contractors are involved, the owner is required to pay the full value of the work actually done, deducting only what has been paid, regardless of what it may cost to complete the building under the...
To continue reading
Request your trial-
Fossett v. The Rock Island Lumber & Manufacturing Company
... ... failure to fulfil a contract should be deducted from the ... contract price, and the balance prorated among the ... subcontractors. And in Biggs et al. v ... [92 P. 839] ... Clapp et al. , 74 Ill. 335, the same clause of the ... Illinois statute was construed in a case where the ... ...
-
People v. Race
...to the two sections of statute above cited, Frink et al. v. King, 3 Scam. 144; Stribbling et al. v. Prettyman, 57 Ill. 371; Biggs et al. v. Clapp et al. 74 Ill. 335; Patterson v. Winn. 11 Wheat. 385; Dubois v. McLean, 4 McLean, 489; United States v. Collins, 3 Blatch. 325; Potter's Dwarris ......
- Graham v. Meehan
- Cruse v. Aden