BINGHAMTON CONST. CO. v. United States
Decision Date | 07 October 1952 |
Docket Number | No. 48525.,48525. |
Citation | 123 Ct. Cl. 804,107 F. Supp. 712 |
Parties | BINGHAMTON CONST. CO., Inc. v. UNITED STATES. |
Court | U.S. Claims Court |
Jerome Beaudrias, Yonkers, for the plaintiff.
James J. Sweeney, Washington, D. C., Holmes Baldridge, Asst. Atty. Gen., for the defendant.
The Court, upon the evidence, the report of Commissioner William E. Day, and the briefs and argument of counsel, makes the following
Special Findings of Fact.
1. Plaintiff is, and at all times material herein has been, a corporation organized and existing under the laws of the State of New York with its principal office and place of business at Binghamton, New York. Since its formation in 1929, it has been engaged in business as a general contractor.
2. On March 29, 1941, defendant, acting by and through the War Department's Corps of Engineers' Office at Binghamton, New York, invited bids for the construction of Flood Protection Project (Section No. 1) along the north bank of the Chemung River, within the limits of the city of Elmira, Chemung County, New York. In response to said invitation, plaintiff submitted a bid based upon a unit price applied to the various operations involved in the performance of the work in the total sum of $232,669.30. This bid was accepted by defendant on May 14, 1941. On that date plaintiff and defendant entered into a written contract, No. W-321-eng-261, which was approved June 3, 1941. On June 5, 1941, defendant gave plaintiff a formal notice to proceed with the work. Actual work commenced on the site of the job on June 3, 1941.
3. The contract was performed by plaintiff, and it has been paid the contract price, as adjusted, for change orders with the exception of $100 which plaintiff instructed the District Engineer to withhold, and plaintiff has refused to accept said $100 from defendant on advice of its counsel.
4. Plaintiff sues for the sum of $37,317.19, the total of three separate claims, as follows:
Claim for reimbursement of wage rates paid to carpenters laborers, and concrete puddlers ... $15,597.38 Claim as regards measuring of sheeting and shoring .............. 14,785.55 Claim for finishing of concrete 6,934.26 __________ Total .......................... $37,317.19 Each claim will be discussed separately
Wage Rates
5. Before bidding, plaintiff was furnished a copy of the specifications. Section 1-31 of such specifications reads, insofar as here pertinent, as follows:
* * * * * *
6. Article 17 of the contract reads as follows:
7. On October 22, 1940, the Elmira business agent of the United Brotherhood of Carpenters and Joiners of America, Local 532, wrote to the United States Engineer's Office in Binghamton, New York, to inform it that the wage scale for carpenters would be increased as of January 1, 1941, from $1 per hour to $1.125 per hour. On October 29, 1940, the District Engineer acknowledged receipt of this letter.
8. On January 31, 1941, the Secretary of Labor furnished to the Corps of Engineers at its request, for inclusion in the contract specifications, the schedule of minimum wages in the Elmira area. Such schedule, which is set out in finding 5, was included in the specifications which were furnished to plaintiff prior to the computation of its bid. As stated in finding 2, invitations for bids were issued on March 29, 1941, and plaintiff's bid was accepted on May 14, 1941.
9. On March 4, 1941, the Secretary of Labor furnished to the Public Buildings Administration of the Federal Works Agency a schedule of minimum wages in the Elmira area for inclusion in the bidding specifications and contract for a Federal Housing Project in Elmira, New York. The prevailing wage rates shown therein, in pertinent part, were as follows:
Classification Hourly rate Carpenters, Journeymen ......... $1.125 Laborers, unskilled ............ 0.55
10. Plaintiff employed only union labor on this project. At the time plaintiff began work on the site on June 3, 1941, it had to pay $.625 per hour for laborers and $1.125 per hour for carpenters. The carpenter wage rate had been put into effect by the union on January 1, 1941, and the laborer wage rate on April 1, 1941.
11. On June 16, 1941, plaintiff advised the District Engineer (who was the contracting officer) that the minimum wage rates provided in the contract specifications were less than the rates currently prevailing in the Elmira locality for carpenters, laborers (unskilled), laborers (concrete puddlers), and truck drivers.
12. The District Engineer replied on June 27, 1941, stating that the minimum wage rates were determined in strict accordance with the applicable law and regulations, and that he could not afford relief for any differences between wage rates then prevailing in the area and the minimum rates required by the contract specifications.
13. Plaintiff protested this decision to the Chief of Engineers under date of July 10, 1941, and on August 5, 1941, plaintiff's appeal was denied by the Chief of Engineers in part as follows:
"There is no authority in law for this office to question the correctness of any determination made by the Secretary of Labor pursuant to the provisions of the above cited act 49 Stat. 1011. Therefore, I find that the wage rates as established by the Secretary of Labor, and incorporated in the contract specifications, were the minimum wage rates applicable in the locality for the labor classifications anticipated to be used on the work.
14. Plaintiff under date of February 20, 1943, asked defendant to reconsider its appeal regarding minimum wage rates, and this was responded to by letter dated April 13, 1943, from the Chief of Engineers, in part as follows:
15. Paragraph 1-12 of the Standard Government Form of Invitation for Bids, a copy of which was furnished to plaintiff, provides as follows:
...
To continue reading
Request your trial-
United States v. Idlewild Pharmacy, Inc.
...571 (1957); Arcole Midwest Corporation v. United States, 113 F.Supp. 278, 125 Ct.Cl. 818 (1953); Binghamton Construction Company, Inc. v. United States, 107 F.Supp. 712, 123 Ct.Cl. 804 (1952). In Bell v. Lamborn, 2 F.2d 205, 206 (4th Cir. 1924), the Court said that one may be adjudged guilt......
-
United States v. Binghamton Const Co
...but from economic conditions which are ordinary contingencies contemplated under the terms of the contract.' 8. 107 F.Supp. 712, 716, 123 Ct.Cl. 804, 810—811: 'If plaintiff's president had investigated wage rates, he could have ascertained that the prevailing rate for carpenters was $1.125 ......
-
Arcole Midwest Corp. v. United States, 49761.
...11, 40 S.Ct. 423, 64 L.Ed. 735; Potashnick v. United States, 105 F.Supp. 837, 123 Ct. Cl. 197, 218; Binghamton Construction Co. v. United States, 107 F.Supp. 712, 123 Ct. Cl., 804, 836-837. We are, therefore, of the opinion that plaintiff is entitled to recover of the defendant the amount i......
-
Farwell Co. v. United States, 282-52.
...the meaning of Article 15, Bell Aircraft Corp. v. United States, 100 F.Supp. 661, 120 Ct.Cl. 398, 462-463; Binghampton Construction Co. v. United States, 123 Ct.Cl. 804, 839; and that consequently the decision of the head of the department upon this issue did not become final and conclusive......