Black Diamond Development, Inc. v. Thompson
Decision Date | 10 August 2007 |
Docket Number | No. 1060334.,1060334. |
Citation | 979 So.2d 47 |
Parties | BLACK DIAMOND DEVELOPMENT, INC. v. Patrick G. THOMPSON. |
Court | Alabama Supreme Court |
Rodney E. Nolen and Anthony R. Smith of Sirote & Permutt, P.C., Birmingham, for appellee.
Black Diamond Development, Inc. ("BDD"), appeals from a judgment in favor of Patrick G. Thompson, in Thompson's breach-of-contract action against BDD. We affirm.
On May 19, 1997, the parties in this case executed a document purporting to be an "Agreement for Purchase of Interest" in a condominium "development project in Mt. Crested Butte, Colorado," which BDD was contemplating at that time (hereinafter referred to as "the sell-back agreement"). The sell-back agreement stated, in pertinent part:
(Emphasis added.) The sell-back agreement was signed by Thompson and by Steve McCay, as president of BDD.
The next day, Thompson sent BDD $38,000 (hereinafter referred to as "the first installment"). McCay used the money to reimburse himself for his expenditures in procuring engineering reports, soil tests, and plans and specifications, and in traveling in connection with the contemplated condominium-development project. On July 8, 1997, Thompson sent BDD an additional $62,000 (hereinafter referred to as "the second installment"). McCay used the money from the second installment in a manner similar to the first installment. Both transactions were brokered by Gordon Berlant, who is not a party in this case.
In conjunction with the second installment, Thompson and BDD executed a second document purporting to evidence the parties' agreement as to their respective rights and responsibilities arising out of BDD's receipt and use of the $62,000 (hereinafter referred to as "the July document"). The parties have been unable to produce the original of the July document, or even a legible copy of the original. In the only copy produced in this case, approximately one-third of the text is illegible.
BDD never broke ground on the condominium project. According to McCay, the project was ultimately abandoned when another developer purchased property in Mt. Crested Butte that BDD considered key to the financial success of the project. On April 8, 2004, Thompson wrote a letter to McCay; that letter stated, in pertinent part:
(Emphasis added.) On July 27, 2004, Thompson sued BDD, alleging breach of contract and seeking damages in the amount of $206,259.96. Specifically, he sought the return of the $100,000 principal, plus interest at the rate of 15%. The case was tried without a jury on the basis of documentary evidence and oral testimony.
At trial, counsel for BDD objected to introduction of the July document, arguing that, because of its illegibility, it had no probative value. More specifically, he stated:
The trial court stated: (Emphasis added.) Ultimately, the trial court awarded Thompson $235,950, which included the principal and interest thereon at the rate of 15% through the date of the judgment, and BDD appealed.
As BDD frames the issues on appeal, this Court is faced with two issues. The threshold issue concerns the construction of a key phrase in the sell-back agreement relating specifically to the first installment. An issue regarding recovery of the second installment arises only if the phrase in the sell-back agreement is construed adversely to BDD.
It is undisputed that the parties agreed that Thompson would be entitled to repayment of his first installment of $38,000, plus interest at the rate of 15%, if his request for repayment was made "during the construction process." In other words, it is undisputed that Thompson would be entitled to repayment of his first installment at 15% interest if the sell-back agreement was triggered by BDD's work in procuring engineering reports, soil tests, and plans and specifications, and in traveling in connection with the contemplated condominium-development project. BDD, however, contends that the sell-back agreement was never triggered, because, it insists, "construction" on the project was never begun. According to BDD, the phrase "during the construction process" does not include such activities as procuring engineering reports, soil tests, and plans and specifications, and traveling. The resolution of this issue thus involves a matter of contract construction.
"`[W]e apply a de novo review to a trial court's determination of whether a [written] contract is ambiguous and to a trial court's determination of the legal effect of an unambiguous contract term.'" Young v. Pimperl, 882 So.2d 828, 830 (Ala. 2003) (quoting Winkleblack v. Murphy, 811 So.2d 521, 525-26 (2001)). "[A] contract is not ambiguous simply `"because the parties allege different constructions of [it]."'" Avis Rent A Car Systems, Inc. v. Heilman, 876 So.2d 1111, 1122 (Ala.2003) (quoting Ex parte University of South Alabama, 812 So.2d 341, 345 (Ala.2001), quoting in turn Yu v. Stephens, 591 So.2d 858, 859 (Ala.1991)). A contract is ambiguous only if it is "susceptible of more than one reasonable meaning," FabArc Steel Supply, Inc. v. Composite Constr. Sys., Inc., 914 So.2d 344, 357 (Ala.2005) (emphasis added), and "`it is presumed that parties intend to make reasonable contracts.'" BellSouth Mobility, Inc. v. Cellulink, Inc., 814 So.2d 203, 216 (Ala.2001) (quoting Weathers v. Weathers, 508 So.2d 272, 274 (Ala.Civ.App.1987) (emphasis added in Cellulink)).
According to BDD, the phrase is not ambiguous, and we agree, although we disagree with BDD's interpretation of it. BDD argues that the verb "construct" means "`to form by assembling or combining parts; build.'" BDD's brief, at 18 (quoting The American Heritage Dictionary 394 (4th ed.2006)). Because no ground was ever broken on the condominium-development project, BDD insists, construction never began; therefore, BDD argues, the sell-back agreement was never triggered.
However, BDD ignores the second word in the phrase, "process," which The American Heritage Dictionary defines as "[a] series of actions, changes, or functions bringing about a result." Id. at 1398. The parties did not use the phrase "during construction," or even "during the construction phase"; they used the phrase "during the construction process." (Emphasis added.) See generally Kweku Bentil, Fundamentals of the Construction Process 6 (1989) (the "construction process" is ordinarily composed of five phases, including (1) "pre-bid," (2) "contract procurement," (3) "contract award," (4) actual "construction," and (5) "operating and maintenance"). The word "process" must be regarded as adding something of substance to the phrase. Courts will not presume that the parties "make use of words in their contracts to which no meaning is attached by them." McGoldrick v. Lou Ana Foods, Inc., 649 So.2d 455, 458 (La. Ct.App.1994). In other words, "parties to a contract will not be imputed with using language that is meaningless or without effect." Id. See also Royal Ins. Co. of America v. Thomas, 879 So.2d 1144, 1154 (Ala.2003) ("" . The use of the word "process" broadens the scope of the phrase in the sell-back agreement.
Indeed, courts have stated that the term "construction process includes more than bricks and mortar," and that "the term `construction delays' ... is broad enough to include design, planning, and other facets of bringing the [project] to fruition." Brewhouse, Ltd. v. New Orleans Pub. Serv., Inc., 614 So.2d 118, 124 (La.Ct.App. 1993). For example, acquiring a "`permanent first mortgage loan'" is an essential part of the "`construction process, because it finances a substantial proportion, if not all, of the cost of development, including site preparation and sometimes the actual cost of acquiring the raw land.'" Bonniecrest Dev. Co. v. Carroll, 478 A.2d 555, 559 n. 5 (R.I.1984) (quoting...
To continue reading
Request your trial-
Stewart v. Hartford Life & Accident Ins. Co., Case No. 2:17-CV-01423-KOB
..."presume that the parties 'make use of the words in their contracts to which no meaning is attached by them.'" Black Diamond Dev., Inc. v. Thompson, 979 So. 2d 47, 51 (Ala. 2007) (quoting McGoldrick v. Lou Ana Foods, Inc., 649 So. 2d 455, 458 (La. Ct. App. 1994)). Courts presume "that every......
-
Scrushy v. Tucker
...on those findings will not be reversed unless the judgment is palpably erroneous or manifestly unjust.” ’ ” Black Diamond Dev., Inc. v. Thompson, 979 So.2d 47, 52 (Ala.2007) (quoting New Props., L.L.C. v. Stewart, 905 So.2d 797, 799 (Ala.2004), quoting in turn Philpot v. State, 843 So.2d 12......
-
Pavilion Development v. Jbj Partnership
... ... , an Alabama general partnership ("Pace"), sold Gallop Enterprises, Inc. ("Gallop"), approximately 22 acres of unimproved real property located in ... See Godfrey v. Black, 240 Ala. 151, 154, 197 So. 892, 894 (1940) (holding that a redemptioner ... ...
-
Scrushy v. Tucker
...on those findings will not be reversed unless the judgment is palpably erroneous or manifestly unjust."'" Black Diamond Dev., Inc. v. Thompson, 979 So. 2d 47, 52 (Ala. 2007) (quoting New Props., L.L.C. v. Stewart, 905 So. 2d 7 97, 7 99 (Ala. 2004), quoting in turn Philpot v. State, 843 So. ......