Board of Com'Rs v. Bill Harbert Constr. Co.
Decision Date | 31 July 2009 |
Docket Number | 1041091. |
Citation | 27 So. 3d 1223 |
Parties | BOARD OF WATER & SEWER COMMISSIONERS OF the CITY OF MOBILE v. BILL HARBERT CONSTRUCTION COMPANY and Federal Insurance Company. |
Court | Alabama Supreme Court |
E.J. Saad and James H. Crosby of Crosby Saad, LLC, Mobile; and James E. Atchison of The Atchison Firm, Mobile, for appellant.
Edward P. Meyerson, Susan S. Wagner, and James H. White of Baker, Donelson, Bearman, Caldwell & Berkowitz, PC, Birmingham, for appellees.
James G. Wyly III and Kyle S. Moran of Phelps Dunbar, LLP, Gulfport, Mississippi; and Richard O. Kingrea of Bonner Landreau Kingrea LLC, Foley, filed a brief on behalf of ATC Group Services, Inc.
The Board of Water & Sewer Commissioners of the City of Mobile("the Board") appeals from a summary judgment in favor of Bill Harbert Construction Company("Harbert") and Harbert's surety, Federal Insurance Company("Federal").The summary judgment, which the trial court certified as final under Rule 54(b), Ala. R. Civ. P., adjudicated claims made by the Board arising out of Harbert's performance of two construction projects for the Board, as hereinafter discussed.1
In 1992, the Board retained BCM Converse, Inc.("BCM"),2 to perform engineering and related consultation services for two projects associated with the Board's Clifton C. Williams Wastewater Treatment Plant.One project ("Project 15") involved in part, the construction of a large reactor basin known as reactor basin # 2.3The other project ("Project 16") involved modifications and improvements to a sludge-treatment facility.BCM prepared the plans and specifications for the projects, and the Board then requested bids for the construction of the projects.
Harbert bid upon and was awarded the construction contracts for both Project 15 ("Contract 15") and Project 16 ("Contract 16").Pursuant to the contracts, Harbert agreed to complete the respective projects in accordance with the plans and specifications prepared by BCM and in accordance with the Board's "Standard Specifications for Water Mains, Sanitary Sewers and Sewage Pumping Stations"("the standard specifications").The price for performing the work under Contract 15 was approximately $11,106,963, and the price for performing the work under Contract 16 was approximately $1,298,125.Taking into account extensions granted by the Board, the work under Contract 15 was required to be completed on or before December 26, 1996, and the work under Contact 16 was required to be completed on or before May 2, 1996.4Federal agreed to act as Harbert's surety for both contracts, and Harbert and Federal executed and delivered surety bond documents in favor of the Board for each project.
The primary issue in the present appeal concerns whether the Board's terminations of Contract 15 and Contract 16 were proper and the effect of those terminations on the Board's claims against Harbert that were adjudicated by the summary judgment.
As a preliminary matter, we note that the standard specifications describe BCM's role in the projects, including the following:
The standard specifications further provided, however:
We also note that subsection 8.11 of the standard specifications, entitled "Default of Contract," provided for notices of default and termination.Subsection 8.11 states:
Contract 15 required that reactor basin # 2 be constructed to satisfy certain pressure tests.To help maintain pressure in the reactor basin, the plans and specifications for Project 15 required the use of the Sikadur-Combiflex System ("the Combiflex system"), manufactured by Sika Corporation("Sika").The Combiflex system consisted of strips of foam "glued or welded" over seams that existed at joints between the concrete slabs and T-sections that were used to construct the reactor basin.
After Harbert entered into Contract 15, it entered into a subcontract with Spiderman's Professional Services, Inc.("Spiderman"), pursuant to which Spiderman agreed to install the Combiflex system on reactor basin #2.5Spiderman purchased the Combiflex system from a supplier.In October 1996, after Harbert had constructed reactor basin # 2, Spiderman completed the installation of the Combiflex system, allegedly in accordance with the plans and specifications for Contract 15 and in accordance with on-site directions of a representative from Sika.6
In October 1996, both Sika and Spiderman issued their respective warranties as to any defects in material and or workmanship associated with the Combiflex system.Subsection 7.14 of the standard specifications provided that Harbert "shall accept final responsibility for completion and final acceptance of the overall Project including work done by subcontractors and material and equipment provided by vendors and suppliers."
After Spiderman installed the Combiflex system, construction continued on the rest of Project 15.Disputes arose between Harbert and some of its subcontractors, on the one hand, and BCM, on the other, as to certain requirements under Contract 15, including whether the plans and specifications called for the installation of certain "interlock controls."Harbert requested that BCM approve a change order for the interlock controls.During the dispute over the interlock-control change order, BCM requested that Harbert provide the Board with an updated schedule for completing Project 15, particularly when it became apparent that Project 15 would not be completed by the scheduled completion date.
On April 10, 1997, Harbert sent a letter to Joseph N. Asarisi,...
To continue reading
Request your trial-
Knight v. Knight
... ... 226 So.3d 690 Bill G. Hall and Catherine E. Garland of Bill G. Hall, P.C., ... Nix , 460 So.2d 1346, 1347 (Ala.Civ.App.1984).'))." Board of Water & Sewer Comm'rs of City of Mobile v. Bill Harbert Constr. Co. , 27 So.3d 1223, 1254 (Ala.2009). The husband has not ... ...
-
South Dallas Water Auth. v. the Guarantee Co. of North Am.
... ... , the South Dallas Water Authority's (South Dallas) board of directors held a meeting with the officers of Wainwright ... Bill Harbert Constr. Co., 27 So.3d 1223 (Ala.2009) (Board ... ...
-
Merchants FoodService v. Rice
...for an appellant." Gibson v. Nix, 460 So.2d 1346, 1347 (Ala. Civ. App. 1984).’) )."Board of Water & Sewer Comm'rs of City of Mobile v. Bill Harbert Constr. Co., 27 So.3d 1223, 1254 (Ala. 2009).15 In its appellate brief, Merchants complains about the fact that Rice converted the wages he ear......
-
McConico v. Patterson
... ... the foreman of a Jefferson County grand jury as a True Bill. That, in and of itself, defeats the plaintiff's malicious ... "In Alabama Department of Transportation v. Harbert International, Inc., 990 So.2d 831, 83940 (Ala.2008) ... Board of Trs. of Univ. of Alabama, 288 Ala. 20, 23, 256 So.2d ... River Road Constr., Inc., 858 So.2d 257, 261 (Ala.2003).' " Cooper v ... ...