Borden, Inc. v. Gulf States Utilities Co.

Decision Date11 April 1989
Docket NumberNo. 88,88
Citation543 So.2d 924
PartiesBORDEN, INC. v. GULF STATES UTILITIES COMPANY. CA 0320. 543 So.2d 924
CourtCourt of Appeal of Louisiana — District of US

B. Richard Moore, Jr., Carolyn Parmenter, New Orleans, R. Gordon Kean, Baton Rouge, for Borden, Inc., Monochem, Inc. and Uniroyal Chemical Company, Inc.

William Shaddock, Lake Charles, for Gulf States Utilities Co.

Before CARTER, LANIER and LeBLANC, JJ.

CARTER, Judge.

This is a suit arising out of a contract for electric service.

FACTS

Borden, Inc. (Borden) and Uniroyal Chemical Company, Inc. (Uniroyal) own and operate separate chemical manufacturing facilities on adjacent tracts of land in Geismar, Louisiana. Monochem, Inc. (Monochem), a nonprofit service corporation jointly owned by Borden and Uniroyal, supplies services and utilities, including electricity, to Borden and Uniroyal for use in their chemical manufacturing processes. Monochem purchases electricity from Gulf States Utilities Company (GSU) for its own use and that of Borden and Uniroyal. 1

Prior to 1981, GSU provided Monochem electricity pursuant to a 1961 agreement. The 1961 agreement contained a fifteen-year term and an "evergreen provision," which provided that after the fifteen-year term of the contract, either party to the contract could cancel by giving a two-year notice. Sometime during 1978, GSU exercised its option to cancel the contract. The parties then began negotiating a new contract for electric service, which resulted in the 1981 agreement.

The 1981 agreement consists of a printed form contract used by GSU, several riders, and a transmittal letter, dated May 27, 1981. The form contract permitted the customer to select the type of electric service needed, namely standard service or auxiliary or standby service. 2 Standard service or firm power service is electric service which GSU is obligated to provide and which the customer requires on a regular and continuous basis. Standby or auxiliary service is electric service that is provided on an "as needed" basis. The form contract was for standard service only.

The form contract also contained the following pertinent provisions:

[C]ustomer's obligation to pay facilities charges is unconditional, and such charges are payable regardless of such Customer's inability or failure to take service for any reason, and minimum charges under applicable schedules are due and payable in all events (except as provided above with respect to strike, damage or destruction) even though such Customer takes no service or takes less than the amount on which the minimum charge is based.

Customer is aware that auxiliary and standby service from Company must be specifically contracted. Unless such service is designated at the top of this contract, Company's obligation to supply electric service shall be conditioned on such service being Customer's exclusive source of electric power for the term of this contract.

The contract was dated April 13, 1981, 3 but was not signed by GSU or Monochem until November 11, 1981.

Rider A recognized the corporate and physical interrelationships among Borden, Uniroyal, and Monochem and classified these corporations as a single customer for the purposes of supplying electricity under the 1981 agreement. 4 Rider B set forth the estimated monthly facilities charge. 5 The facilities charge was designed to reimburse GSU for the equipment installed to deliver power to the Monochem substation. Rider C permitted Monochem to reduce by 15% the amount of kilowatt demand or contract power on three specified dates. 6 Under the terms of the 1981 agreement, the amount of contract power was 85,000 kilowatt hours.

Also made part of the 1981 agreement was a transmittal letter, dated May 27, 1981, to Borden from Michael A. Ketterer, Industrial Services Engineer of GSU. The letter provided, in part, as follows:

Attached please find two (2) copies of the proposed Agreement for Electric Service between Gulf States Utilities and Monochem, Inc.

Please have a contracting official with Monochem sign both copies. Keep one copy for your files, and return the other to my attention.

The purpose of the contract language in Article V, last paragraph concerning auxiliary or standby service, is not to restrict the customer from installing and operating alternate energy sources. The stipulation outlined in this paragraph simply requires the customer to notify GSU if any auxiliary or standby service is used within the plant and operated in parallel with our system, and specifically contract for this service in a rider to the Electric Service Agreement.

If the customer does not choose to contract for auxiliary or standby service in the original agreement, this contract can be amended at the customer's request during the term of the contract to include this type of service.

In 1984, Borden began to gradually install cogeneration facilities. When all of its cogeneration facilities were operational, Borden determined that it no longer required the standard electric service, which was the object of the 1981 agreement between GSU and Monochem. Borden then requested that GSU amend the 1981 agreement to reduce and/or eliminate the minimum charges for firm power. GSU refused.

On December 4, 1986, Borden filed suit for declaratory judgment, specific performance, and injunctive relief, alleging that GSU's failure and refusal to amend the 1981 agreement to permit cogeneration, to supply plaintiff with adequate standby power, to eliminate the minimum demand charges allegedly due under the 1981 agreement, and to purchase excess electric energy cogenerated by Borden constituted a breach of contract. Pursuant to exceptions filed by GSU, Monochem and Uniroyal joined Borden as parties-plaintiffs.

After trial, the trial court determined that Borden, Monochem, and Uniroyal were one customer of GSU under the 1981 agreement for electric service. The trial court further determined that, because Borden had received certificates from the Federal Energy Regulatory Commission qualifying its three cogeneration facilities, GSU was obligated to provide standby power to each of Borden's existing cogeneration facilities at rates approved by the Louisiana Public Service Commission and to purchase excess electricity generated by Borden's cogeneration units under terms and conditions established by the Commission. Judgment was otherwise rendered in favor of GSU rejecting Borden's demand for a declaratory judgment, specific performance, and a permanent injunction and dismissing Borden's suit. The trial court also recognized Borden's contractual obligation to pay the minimum demand charges to GSU. Monochem, Borden, and Uniroyal appealed that portion of the judgment, assigning the following specifications of error:

1. The trial court erred in determining that the contract was clear and unambiguous after receiving substantial evidence of the parties' intent and the facts and circumstances surrounding contract negotiation.

2. The trial court erred in its application of the rules of contract construction, in that the trial court failed to interpret the contract in accordance with the intent of the parties, failed to interpret doubtful contractual provisions against GSU, and failed to interpret the contract in accordance with principles of equity.

GSU neither appealed nor answered the appeal, and consequently that portion of the judgment rendered against GSU is now definitive and not at issue.

CONTRACT INTERPRETATION

Borden, Monochem, and Uniroyal contend that the trial court erred in finding that the 1981 agreement was clear and unambiguous. Borden, Monochem, and Uniroyal reason that, because the trial court held a full evidentiary hearing and accepted evidence surrounding the negotiations of the 1981 agreement, the contract was ambiguous.

The contract between parties is the law between them, and the courts are obligated to give legal effect to such contracts according to the true intent of the parties. Bailey v. Franks Petroleum, Inc., 479 So.2d 563 (La.App. 1st Cir.1985); G/O Enterprises, Inc. v. Mid Louisiana Gas Company, 444 So.2d 1279 (La.App. 4th Cir.1984), writ denied, 446 So.2d 318 (La.1984); Rebstock v. Birthright Oil & Gas Co., 406 So.2d 636 (La.App. 1st Cir.1981), writ denied, 407 So.2d 742 (La.1981). This intent is to be determined by the words of the contract when they are clear, explicit, and lead to no absurd consequences. LSA-C.C. art. 2046; Thomas v. Knight, 457 So.2d 1207 (La.App. 1st Cir.1984); Campesi v. Margaret Plantation, 417 So.2d 1265 (La.App. 1st Cir.1982), writ denied, 422 So.2d 163 (La.1982).

When the words of a contract are clear and explicit and lead to no absurd consequences, no further interpretation may be made in search of the parties' intent. LSA-C.C. art. 2046; Investors Associates Ltd. v. B.F. Trappey's Sons, Inc., 500 So.2d 909 (La.App. 3rd Cir.1987), writ denied, 502 So.2d 116 (La.1987); Kalmn, Inc. v. Walker Louisiana Properties, 488 So.2d 340 (La.App. 3rd Cir.1986). Further, the rules of interpretation establish that when a clause in a contract is clear and unambiguous, the letter of that clause should not be disregarded under the pretext of pursuing its spirit. LSA-C.C. art. 2046, comment (b); Cashio v. Shoriak, 481 So.2d 1013 (La.1986).

The meaning and intent of the parties to the written contract in such cases must be sought within the four corners of the instrument and cannot be explained or contradicted by parol evidence. LSA-C.C. art. 1848; Tauzin v. Claitor, 417 So.2d 1304 (La.App. 1st Cir.1982), writs denied, 422 So.2d 423 (La.1982). Contracts, subject to interpretation from the instrument's four corners without the necessity of extrinsic evidence, are to be interpreted as a matter of law, and the use of extrinsic evidence is proper only where a contract is ambiguous after an examination of the four corners of the agreement. Investors Associates Ltd. v. B.F. Trappey's Sons, Inc., supra....

To continue reading

Request your trial
65 cases
  • 92 1544 La.App. 1 Cir. 3/11/94, Belle Pass Terminal, Inc. v. Jolin, Inc.
    • United States
    • Court of Appeal of Louisiana — District of US
    • 11 Marzo 1994
    ... ... Camcraft, Inc., 580 So.2d 1073, 1077 (La.App. 4th Cir.1991); Borden, Inc. v. [92 1544 La.App. 1 Cir. 17] Gulf States Utilities Company, 543 ... ...
  • Mobil Exploration v. Certain Underwriters, 2001 CA 2219.
    • United States
    • Court of Appeal of Louisiana — District of US
    • 20 Noviembre 2002
    ... 837 So.2d 11 ... MOBIL EXPLORATION & PRODUCING U.S. INC., Mobil Producing Texas & New Mexico Inc., Mobil Oil ... Casualty and Surety Company, 574 So.2d at 369; Borden, Inc. v. Gulf States Utilities Company, 543 So.2d 924, 928 ... ...
  • Usner v. Strobach
    • United States
    • Court of Appeal of Louisiana — District of US
    • 22 Noviembre 1991
    ... ...         There is no United States or Louisiana constitutional right to a trial by jury in a ... Cf. Dawson v. Mazda Motors of America, Inc., 517 So.2d 283 (La.App. 1st Cir.1987); Seals v. Pittman, ... Borden, Inc. v. Gulf State Utilities Company, 543 So.2d 924 ... ...
  • 96 0863 La.App. 1 Cir. 2/14/97, Osborne v. Ladner
    • United States
    • Court of Appeal of Louisiana — District of US
    • 14 Febrero 1997
    ... ... Orleans, for Defendant Allied-Bruce Terminix Companies, Inc ...         Before CARTER, LeBLANC and PARRO, ... art. [96 0863 La.App. 1 Cir. 11] 2045, which states that the interpretation of a contract is the determination ... Carter v. BRMAP, 591 So.2d at 1188; Borden, Inc. v. Gulf States Utilities Company, 543 So.2d 924, 928 ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT