Bradford Novelty Co. v. Technomatic, Inc.

Decision Date01 March 1955
Citation112 A.2d 214,142 Conn. 166
CourtConnecticut Supreme Court
PartiesBRADFORD NOVELTY COMPANY, Inc. v. TECHNOMATIC, Inc. Supreme Court of Errors of Connecticut

Milton L. Cohn, Bridgeport, with whom was Israel J. Cohn, Bridgeport, for appellant (plaintiff).

Herbert L. Cohen, Bridgeport, for appellee (defendant).

Before BALDWIN, O'SULLIVAN, WYNNE and DALY, JJ., and ALCORN, Superior Court Judge.

BALDWIN, Associate Justice.

The plaintiff brought this action to recover the sum of $2,100, paid pursuant to a contract to construct a machine. It alleged that the defendant had failed to perform the contract within the time agreed. The defendant denied any breach of the contract and by counterclaim sought damages for the refusal of the plaintiff to accept the machine and pay the balance of the purchase price. The trial court rendered judgment for the defendant on the complaint and the counterclaim, and the plaintiff has appealed.

The finding of facts, which is not subject to correction, may be summarized as follows: The plaintiff was engaged in the business of manufacturing plastic novelty items. Its process of manufacture required the use of both automobile and hand spraying machines for lacquering. The defendant designed and manufactured special machinery for particular manufacturing requirements. On July 24, 1950, it submitted a proposal to the plaintiff for the construction of an automatic spraying machine. The proposal contained a clause stating that the defendant would not be responsible for delays in performance 'due to strikes, accidents, shortages of labor or materials, delays by carriers or other causes beyond [its] control.' After a series of modifications of the proposal, the parties entered into a contract on August 17, 1950, calling for the construction and delivery of an automatic machine within three to five months, subject to the clause regarding delays. The defendant encountered various problems, but it completed the designs for the machine by the end of October. Prior to November 7, the defendant brought to the plaintiff's attention an automatic spraying device which utilized a centrifugal system of paint dispersal and which could be adapted to the plaintiff's requirements. Although employment of this device would be a departure from the original proposal, the plaintiff, after a demonstration, agreed to the modification, and the parties, by an exchange of letters on November 7 and 8, changed their original agreement to provide for the use of this type of sprayer. On November 8, the plaintiff paid the defendant $2,100 on the purchase price of $5100, as agreed in their contract. Because of difficulties beyond its control, the defendant failed to complete the machine by January 17, 1951, the date originally agreed upon.

In the early spring of 1951, the plaintiff advised the defendant that because of the inferior quality of plastic materials available for use it would be necessary to employ a machine with a rotary spindle instead of the type first contemplated. The defendant agreed to this change on March 28. The alteration presented new technical problems to the defendant and further delayed the project. Since neither party could obtain priorities for the purchase of necessary materials, which were in short supply owing to the Korean War, further delay ensued. Delay also resulted because the defendant could not promptly obtain, for experiementation in developing the machine, the kind of lacquer used by the plaintiff. During the spring of 1951, the plaintiff made inquiries concerning the progress of the work. It was advised by the defendant on May 2, that, barring unforeseen developments, the machine should be completed by the end of the month. An appointment to see the completed machine in operation was made for July 7. On that date, the finished machine was ready for delivery. It conformed to all the specifications of the contract between the parties. The defendant requested that the demonstration fixed for July 7, which fell on Saturday, be postponed until Monday, July 9. The plaintiff expressed its displeasure at the postponement but agreed to come to the defendant's plant on Tuesday, July 10. Instead, on July 9, it posted a registered letter to the defendant rescinding the contract and demanding the immediate return of the $2,100 it had paid. The defendant was ready and able to deliver the machine on July 7 and on July 10, and for a reasonable time thereafter. It did not try to sell the machine or determine its market value because it was constructed especially for the plaintiff's needs, and efforts to sell it would have been futile. It had no pecuniary value to the defendant. On these facts the trial court concluded that the defendant had fulfilled its contract, as modified in November, 1950, and March, 1951, and ordered judgment for the defendant to recover $3,000, the unpaid balance of the purchase price.

The time fixed by the parties for performance is, at law, deemed of the essence of the contract. Janulewycz v. Quagliano, 88 Conn. 60, 63, 89 A. 897. The plaintiff claims that this rule applies especially to mercantile contracts like the present one and that the defendant's failure to perform within the time stated relieved the plaintiff from performance on its part. 3 Corbin, Contracts, § 718; 2 Williston, Sales (Rev.Ed.) §§ 452a, 453. While the rule is generally accepted, it is not decisive of the case at bar. Where the contract calls for the manufacture and sale of an article as yet nonexistent, the time specifided for delivery is less likely to be considered of the essence. The reason is that in such a situation there is a probability of delay, and the loss to the manufacturer is likely to be great if the buyer refuses to accept and pay because of noncompliance with strict performance. 3 Corbin, Contracts, § 719. This holds true on the facts here. The parties modified their original agreement on two occasions--in November, 1950, when the use of a centrifugal sprayer was agreed upon, and in March, 1951, at the instance of the plaintiff, when a rotary spindle was adopted because the plaintiff could get nothing but inferior plastics for use in...

To continue reading

Request your trial
13 cases
  • Export Development Canada v. T. Keefe & Son, LLC
    • United States
    • Connecticut Superior Court
    • November 9, 2016
    ... ... the plaintiff's assignor, Metal Perreault, Inc. (Metal ... Perreault), sold and delivered goods to the defendant, ... stated, in a precode case, Bradford Novelty Co. v ... Technomatic , 142 Conn. 166, 170, 112 A.2d 214 ... ...
  • R. A. Weaver and Associates, Inc. v. Haas and Haynie Corp.
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • December 4, 1980
    ...(1900) (same).58 See, e. g., American Concrete Steel Co. v. Hart, 285 F. 322, 327-328 (2d Cir. 1922); Bradford Novelty Co. v. Technomatic, Inc., 142 Conn. 166, 112 A.2d 214, 217 (1955); Hardin v. Eska Co., 256 Iowa 371, 127 N.W.2d 595, 597 (1964). The question whether the elapsed time was r......
  • DP Technology Corp. v. Sherwood Tool, Inc., Civ. No. H-90-355(AHN).
    • United States
    • U.S. District Court — District of Connecticut
    • November 29, 1990
    ...of the delivery schedule, and that the defendant waived the 10-12 week delivery requirement. In Bradford Novelty Co. v. Technomatic, 142 Conn. 166, 170, 112 A.2d 214, 216 (1955) (pre-Code), where the buyer acquiesced to a delay in delivery, the court found that the buyer "by its conduct, wa......
  • RBC Nice Bearings, Inc. v. SKF USA, Inc.
    • United States
    • Connecticut Supreme Court
    • September 22, 2015
    ...internal quotation marks omitted.) Dallas Aerospace, Inc. v. CIS Air Corp., supra, at 783; see, e.g., Bradford Novelty Co. v. Technomatic, Inc., 142 Conn. 166, 170–71, 112 A.2d 214 (1955) (by repeatedly acquiescing in previous delays, obligee waived its right to insist on strict compliance ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT