Bruce Construction Corp. v. United States, 16374.

Decision Date12 April 1957
Docket NumberNo. 16374.,16374.
Citation242 F.2d 873
PartiesBRUCE CONSTRUCTION CORPORATION et al., Appellants, v. UNITED STATES of America for use of WESTINGHOUSE ELECTRIC SUPPLY COMPANY, Appellee.
CourtU.S. Court of Appeals — Fifth Circuit

Charles R. Scott, Jacksonville, Fla., H. Reid DeJarnette, Miami, Fla., John S. Cox, Marvin L. Thacker, Jacksonville, Fla., Scott & Cox, of counsel, Jacksonville, Fla., for appellants.

Eugene T. Branch, Atlanta, Ga., Ray W. Richardson, Jacksonville, Fla., Bird & Howell, Atlanta, Ga., Patterson, Freeman, Richardson & Watson, Jacksonville, Fla., of counsel, for appellee.

Before TUTTLE and BROWN, Circuit Judges.

JOHN R. BROWN, Circuit Judge.

The question is whether summary judgment ought to have been granted against a general contractor and its surety1 in an action under the Miller Act, 40 U.S.C.A. §§ 270a-270d, for materials furnished to or for a subcontractor2 for construction of a Veterans Hospital.

We have long recognized that no matter how enticing, in an era of congested dockets, is a device to dispose of cases without the delay and expense of traditional trials with their sometime cumbersome and time-consuming characteristics, summary judgment was not devised for, must not be used as, a substitute for trial.Its wholesome utility is, in advance of trial, to test, not as formerly on bare contentions found in the legal jargon of pleadings, but on the intrinsic merits, whether there is in actuality a real basis for relief or defense.Consequently, where the proceedings have indicated that a genuine issue existed, we have consistently rejected3 appealing shortcuts and not the less so even though it was likely that on a trial, the trier would resolve the disputed issues as one of fact in the same manner as when thought to have been one of law alone.

But, equally vigorous in giving full range to this mechanism, we have just as consistently rejected any notions that pretense, or apparent formal controversy can thwart application of this rule or hamstring the court in determining whether it is a proper case for it.Consequently, when a movant makes out a convincing showing that genuine issues of fact are lacking, we require4 that the adversary adequately demonstrate by receivable facts that a real, not formal, controversy exists, and, of course, he does not do that by mere denial or holding back evidence.

And yet, reflecting in spots a picayunishness out of step with the spirit of the Federal Rules, that is just what the General Contractor did and which the District Court found, as do we, inadequate.

It asserts, for example, that an issue of fact was revealed because the complaint alleged that the last material was supplied to the Subcontractor on January 14, 1955, while one affidavit said it was January 15, and two others fixed it at January 17.But this was just such trivia as the Federal Rules were designed to weed out.For the date was important only in fixing the time within which the 90-day written notice must be given, 40 U.S.C.A. § 270b, where services or supplies are furnished to a subcontractor.And, except for a like quibbling, there was really no question about this.By categorical affidavit, an authenticated copy of the letter dated January 24, 1955, from the Supplier to the General Contractor (with indicated copies to the Subcontractor and surety) giving plain notice that the unpaid balance of the Subcontractor's account was $112,997.78 was shown to have been sent Registered-Return Receipt Requested that day and receipted for by a specified representative of the General Contractor on January 26, 1955.Because another somewhat similar letter was sent on May 23, 1955, beyond the 90-day period, and the copy of the one of January 24 was not somehow itself sworn or certified to, Fed.Rules Civ.Proc. rule 56(e),28 U. S.C.A. (although the affidavit of the credit manager incorporated and attached it as an exhibit) and these minor discrepancies appeared, it is claimed that a court, with or without a jury, had to hear evidence on this matter even though it was conceded on argument, as it had to be that a notice specifying the balance as $112,997.78 was a statement "with substantial accuracy" for a claim asserted and allowed finally in the sum of $114,770.52, Coffee v. United States, 5 Cir., 157 F.2d 968;Houston Fire & Casualty Insurance Co. v. United States, 5 Cir., 217 F.2d 727.

Equally hypercritical is the struggle to contrive a dispute over the filing of the suit within one year after the date of final settlement between the Government and the contractor, 40 U. S.C.A. § 270b(b).As it was undisputed, we hold above, that the last material was supplied about January 15-17, 1955, the contract obviously was not then closed, and the suit, filed August 26, 1955, while theoretically capable of being too early, could not possibly have been too late.Moreover, no one would have better knowledge of the exact time final settlement was made with the Government, or more ready means for obtaining the conclusive certificate of the Comptroller General, 40 U.S.C.A. 270c, than the General Contractor.It could not, in the good faith the Rules command, FRCP 8(b), 11, 56(g), construct a disputed issue by allegations in its answer that it was "without knowledge as to those * * * allegations of * * * said complaint."And when this matter, after a year's pretrial discovery, reached a hearing on the motion for summary judgment in which the Judge, FRCP 56(d), by examination of the papers and "interrogating counsel," would have to determine to what extent genuine issues were lacking, it was for the General Contractor then to demonstrate under oath what it did not attempt to do, because it could not.So the complaint again is that trial was denied of an issue in fact utterly out of the case, and on which no dispute could or did exist and which, of all people, the General Contractor so well knew.

The matter stands no differently when it comes to the accuracy and recoverability of the amount ($114,770.52) sued for and allowed.This was not, as has sometimes been the case, of court and some counsel rushing headlong into timesavers that turn out to be time wasters.Here, starting with a complaint which attached a detailed list showing the date, number and amount of every invoice, charge and credit, discovery machinery was used by the General Contractor as fully as desired.Detailed, sworn, factual answers by the Supplier to interrogatories showed the exact totals of all of the deliveries made and charged to the Subcontractor with credits, and those delivered to the General Contractor for use by the Subcontractor, and credits for payments made by it.These corresponded to the penny to the amount sued for and allowed.Subsequently, upon motion and order under FRCP 34, months before the submission of the motion for summary judgment, the General Contractor sought and the Supplier furnished for unlimited examination and use all purchase orders made to Westinghouse Electric Supply Company for materials used or to be used, all quotations made to the Subcontractor for materials used or to be used, and all invoices for materials furnished to be used or used in this construction project.And, months later, with no suggestion from the General Contractor that it did not have adequate information or time within which to procure it, the Supplier's motion for summary judgment was filed with affidavits of three persons having personal knowledge of the matters, FRCP 56(e), categorically showing the delivery of all of the materials at the times, quantities and prices indicated in the identified invoices.Not until the eve of the hearing, September 14, 1956, did the General Contractor dispute or deny or claim doubt about knowledge when it filed the affidavit of one of the individual general contractors, Jack S. Mintzer.

From this, it is claimed, disputed issues arose for two reasons: first, while the complaint alleged the supply of "materials for the prosecution of the work * * * to the Subcontractor of a price or value of $114,770.52 * *," the affidavits and interrogatories showed without dispute that of this sum, $2,601.16 actually represented the net balance yet due and owing by the General Contractor not Subcontractor, for the materials supplied direct to it.Second, the counter-affidavit of Mintzer denied the correctness of the claimed amount and asserted that it was excessive to the extent that the invoice prices charged exceeded the quotation which the Supplier gave the Subcontractor.

The first ignores both the limited function of the complaint under rules which test relief by the evidence received, Millet v. Godchaux Sugars, Inc., 5 Cir., 241 F.2d 264, FRCP 15(b), and the substantive fact that the General Contractor and its surety are liable under the Miller Act for materials supplied...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
108 cases
  • McCormick v. Ross
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • November 25, 1974
    ...demonstrate by receivable facts that a real, not a formal, controversy exists in order to defeat the motion for summary judgment. Fed.R.Civ.P. 56(e); DeBardeleben v. Cummins, 453 F.2d 320 (5th Cir. 1972); Bruce Construction Corp. v. United States, 242 F.2d 873 (5th Cir. 1957); 6 Moore's Fed.Prac. A study of plaintiff's complaint, supporting affidavit, and briefs reveals that plaintiff specifically pleads and avers that he has a copy of an information charging him with murder...
  • Riley-Stabler Const. Co. v. Westinghouse Electric Corp.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • June 07, 1968
    ...sham claims and defences which stand in the way of a direct approach to the truth of a case, was not intended to, it cannot deprive a litigant of, or at all encroach upon, his right to a jury trial." Again in Bruce Construction Corporation v. United States of America, 5th Cir., 242 F.2d 873, 874, this Court said in cautioning against the use of summary "We have long recognized that no matter how enticing, in an era of congested dockets, is a device to dispose of cases without the delay...
  • In re Wright
    • United States
    • U.S. Bankruptcy Court — District of Massachusetts
    • March 29, 1982
    ...Hinkel & Co., Inc. v. Manhattan Co., 506 F.2d 201, 205 (D.C.Cir.1974). The wholesome utility of summary judgment is, in advance of trial, to test on the intrinsic merits whether there is in actuality a real basis for relief or defense. Bruce Construction Corp. v. United States, 242 F.2d 873, 874 (5th Cir. 1957). Here the defendant has admitted executing two notes in favor of the plaintiff, and has admitted liability thereon, but simply denies the amount which the plaintiff says iswhich it can adduce and which will change the result. Radio City Music Hall Corp. v. United States, 135 F.2d 715, 718 (2nd Cir. 1943); Tilden Financial Corp. v. Palo Tire Service, Inc., 596 F.2d 604, 607 (3rd Cir. 1979); Bruce Construction Corp. v. United States, supra. More than mere allegations are necessary to defeat a properly supported motion for summary judgment. Tilden Financial Corp. v. Palo Tire Service, Inc., supra at Given the opportunity to respond...
  • Curl v. International Business Machines Corp.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • August 08, 1975
    ...movant makes out a convincing showing that genuine issues of fact are lacking, we require that the adversary adequately demonstrate by receivable facts that a real, not formal controversy exists . . .." Bruce Construction Corp. v. United States, 242 F.2d 873, 875 (5th Cir. 1957). In her response to IBM's motion for summary judgment, Mrs. Curl has done nothing more than to stand on the original allegations in her complaint, albeit in a verbose manner, and attempt to create a factual...
  • Get Started for Free