Buder v. Martin, 44160

Citation657 S.W.2d 667
Decision Date26 July 1983
Docket NumberNo. 44160,44160
PartiesG.A. BUDER, III, Respondent, v. Robert E. MARTIN, d/b/a R.E.M. Construction, Appellant.
CourtCourt of Appeal of Missouri (US)

Joseph Howlett, Shaw, Howlett & Schwartz, Ronald J. Kaden, St. Louis, for appellant.

Samuel T. Vandover, St. Louis, for respondent.

STEPHAN, Judge.

Defendant Robert E. Martin, d/b/a R.E.M. Construction, appeals from a judgment based on a breach of contract claim in which a jury awarded plaintiff G.A. Buder, III, $16,000 in damages. We affirm.

Plaintiff, an owner of farm land in Pacific, Missouri, entered into two written contractual agreements with defendant on December 2, 1974. By the terms of the contracts, plaintiff engaged defendant to build a five to eight acre lake and a 1/3 to 1/2 acre pond on plaintiff's property for $12,000 and $1,250, respectively. The excavation began in December, 1974, and the project was completed in May, 1975.

In the process of building the lake, defendant constructed a dam, which sloped in the center, forming a large "U" shape. Because the center of the dam was not sufficiently higher than the spillway on the side, excess water caused by heavy rains on March 27 and 28, 1977, flowed over the top of the dam, instead of being channeled off to the side. As a result, a large portion of the dam washed out, knocking down plaintiff's fence and destroying part of the adjoining road. When defendant constructed the small pond, all the dirt was removed down to porous bedrock; consequently, the pond did not hold water.

The defendant argues on appeal that the trial court erroneously submitted instruction number 5 (MAI 26.02), which directed the jury to find for plaintiff if it believed:

First, Defendant did not build the lake and pond in a workmanlike manner, and

Second, because of such failure, Defendant's contract obligations were not substantially performed, and

Third, Plaintiff was thereby damaged.

Defendant claims it was error to give this instruction because it assumes the existence of a contract that has uncontested terms. Defendant maintains that the terms of the contracts to "build" a lake and a pond are in dispute and render the contract ambiguous for purposes of this point on appeal. Instead, defendant would have the trial court submit MAI 26.06, used when the contractual terms and breach are in issue. We conclude that the trial court properly submitted MAI 26.02.

In both the contract for building the lake and the pond, defendant was required to complete all work "in a workmanlike manner according to standard practices." The defendant argues that he entered into a contract for labor, not materials, and the "workmanlike manner" clause does not expand the agreement into a "multi-year guaranty of engineering construction and planning." We do not believe that the terms of the contracts render the agreement unclear.

Ambiguity does not arise from a contract merely because the parties disagree as to how the contract should be construed. J.E. Hathman, Inc. v. Sigma Alpha Epsilon Club, 491 S.W.2d 261, 264 (Mo. banc 1973); Von Seggern v. 310 West 49th Street, Inc., 631 S.W.2d 877, 882 (Mo.App.1982). When there is no ambiguity in the document, it is the responsibility of the court, not the jury, to state its clear meaning. J.E. Hathman, Inc., supra. This the trial court properly did. The clause of the contract requiring the lake and pond to be completed in a workmanlike manner "was an express specification of the contract and one that would have been implied had it not been expressly stated." Hotchner v. Liebowits, 341 S.W.2d 319, 326 (Mo.App.1961).

Defendant misplaces his reliance on Braun v. Lorenz, 585 S.W.2d 102 (Mo.App.1979), in arguing that MAI 26.02 was improperly submitted to the jury. The court in Braun held that MAI 26.06, not 26.02, was the appropriate instruction where issue was joined as to what the basic agreement was. One party argued that the contract was for payment in settlement of respondent's claims, and the other argued that the contract was to purchase respondent's stock. The dispute existed as to the very essence of the parties' obligations, absent express contractual terms. MAI 26.02 is intended to be used in situations "where the existence and terms of the contract are undisputed and the jury is to decide only the issues of breach and resultant damages." Reed Stenhouse, Inc. v. Portnoy, 642 S.W.2d 947, 951 (Mo.App.1982). So it is here.

There was ample evidence that the basic requirement for "building a lake" in the topographical setting of plaintiff's farm was the construction of a dam with a spillway on the side so that excess water could escape without topping the dam, thereby causing it to erode. With respect to the pond, it was clear that its purpose was to hold water, and the jury could find that removal of all soil down to porous rock defeated that purpose. In short, completion of the construction "in a workmanlike manner" would have required proper location of the spillway and avoidance of the leakage problem in the pond. We have no doubt that defendant understood what he agreed to construct and that the workmanlike standards of the industry were the terms of performance. We conclude, therefore, that MAI 26.02 was properly submitted to the jury. Defendant's point is denied.

The defendant contends in his second point on appeal that the trial court erroneously disallowed certain testimony by defendant. After several attempts by defense counsel to ask defendant what his understanding of the agreement with plaintiff was, the trial court sustained plaintiff's objections that "the instrument speaks for itself." The defendant argues that excluding such testimony was erroneous, because it was admissible to explain the meaning of a "patently ambiguous contract."

In failing to make an offer of proof, defendant failed to preserve this point for review. Elliott v. Richter, 496 S.W.2d 860, 864 (Mo.1973); United States Fire Insurance Co. v. Madesco Investment Corp., 573 S.W.2d 442, 443 (Mo.App.1978).

Defendant tells us in his brief what Mr. Martin would have said, had he been allowed to testify. The brief was, of course, not before the trial court; but taking the representations at face value, we conclude that the testimony was inadmissible. According to his brief, defendant was merely an excavator who was "hired ... to provide labor only to build a dam under the instructions of the landowner." The trial court did not accept this approach to the relationship between plaintiff and defendant, and we are of the opinion that such an approach would be at odds with the clear wording of the contracts relating to the construction of the lake and the pond respectively. In each instrument, defendant promised to construct the improvement "in accordance with above specifications." The specifications of the...

To continue reading

Request your trial
10 cases
  • Jake C. Byers, Inc. v. J.B.C. Investments
    • United States
    • Missouri Court of Appeals
    • July 14, 1992
    ...v. Szombathy, 365 Mo. 845, 289 S.W.2d 116, 118 (1956); Pitzer v. Hercher, 318 S.W.2d 397, 399 (Mo.App.1958); see, e.g., Buder v. Martin, 657 S.W.2d 667, 669 (Mo.App.1983). Moreover, in an action for breach of such a contract, the plaintiff has the burden of proving it fulfilled this implied......
  • State v. Welty
    • United States
    • Missouri Court of Appeals
    • April 10, 1987
    ...goes far to dispel the hearsay argument. Mash v. Missouri Pacific Railroad Co., 341 S.W.2d 822 (Mo.1960); Buder v. Martin, 657 S.W.2d 667 (Mo.App.1983). It is difficult to see how the recordings themselves were anymore subject to objection on the ground raised than was Howell's live testimo......
  • Barklage v. Metropolitan Life Ins. Co., 84-1028-CV-W-1.
    • United States
    • U.S. District Court — Western District of Missouri
    • January 17, 1985
    ...because the parties disagree as to how the contract should be construed. J.E. Hathman, supra, 491 S.W.2d at 264; Buder v. Martin, 657 S.W.2d 667, 669 (Mo. App.1983). We find that the provisions of the policy in question are clear and unambiguous. The language has been stipulated to by the p......
  • Millican v. State, 14870
    • United States
    • Missouri Court of Appeals
    • July 20, 1987
    ...of Shirley James. The affidavit of Shirley James was, of course, hearsay, and vulnerable to objection on that basis. Buder v. Martin, 657 S.W.2d 667, 671 (Mo.App.1983). The affidavit, however, was never formally offered in evidence by either side, so the occasion for a hearsay objection nev......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT