Burbic Contracting Co., Inc. v. Cement Asbestos Products Co.

Decision Date08 January 1982
Citation409 So.2d 1
Parties32 UCC Rep.Serv. 1406 BURBIC CONTRACTING CO., INC. v. CEMENT ASBESTOS PRODUCTS COMPANY, a corp., Hartford Accident and IndemnityCompany, a corp., and Robintech Incorporated, a corp. HARTFORD ACCIDENT AND INDEMNITY COMPANY, a corp. v. CEMENT ASBESTOS PRODUCTS COMPANY, a corp. 80-218, 80-218A.
CourtAlabama Supreme Court

James W. May of Odom & May, Birmingham, for appellant Burbic Contr. Co.

Charles E. Sharp, Mac B. Greaves & Catherine E. Crudup of Sadler, Sadler, Sullivan, Sharp & Stutts, Birmingham, for appellant Hartford Acc. & Indemn. Co.

L. Vastine Stabler, Jr. and Lee E. Bains, Jr. of Cabaniss, Johnston, Gardner, Dumas & O'Neal, Birmingham, for appellee Cement Asbestos Products.

Stephen D. Heninger of Hare, Wynn, Newell & Newton, Birmingham, for appellee Robintech, Inc.

FAULKNER, Justice.

Cement Asbestos Products Company (CAPCO), a manufacturer and supplier of pipe, brought suit against Burbic Contracting Company for the price of materials sold to it under an oral agreement. Burbic, in its answer, asserted that the pipes were defective and developed leaks and counterclaimed against CAPCO. CAPCO claimed that the pipe in question was not defective and that the leaks were caused by the improper installation of the pipes by Burbic's employees. As Burbic's surety for a portion of CAPCO's claim against Burbic, Hartford Accident and Indemnity Company was also named as a defendant. Robintech, the manufacturer of the pipe, was joined as a third party defendant.

CAPCO and Burbic made an oral agreement for the sale and purchase of a specified amount of polyvinyl chloride pipe. CAPCO shipped the pipe in several installments. Prior to the initial shipment of the pipe, CAPCO sent a printed acknowledgment form to Burbic. Each shipment also included an invoice on CAPCO's form. The acknowledgment form contained the following contractual limitation of remedies on the reverse side of the form:

4. WARRANTY: Seller makes no warranties either expressed, implied, or statutory in regard to products or materials sold hereunder by Seller, except, however, if within 90 days from the date of delivery any place is judged by Seller to be defective in material or workmanship, Seller may repair or replace it, but the full measure of Seller's liability shall be the purchase price paid to Seller for said piece. In no event shall Seller be liable for labor or consequential damages.

The front of the form stated: "ALL SALES SUBJECT TO CONDITIONS OUTLINED ON REVERSE SIDE OF THIS ORDER FORM."

The trial court found that the limitation of remedies was not a material addition to the contract within the meaning of Code 1975, § 7-2-207. The trial court also found that under the circumstances, Burbic accepted the limitation of remedies. Furthermore, the trial court stated that the leaks in the pipe were caused not by defects in the pipe, but by the improper installation of the pipe by Burbic's employees. The trial court awarded $78,858.25 to CAPCO, which represents the unpaid amount owed by Burbic for the pipe. Robintech was found not to be liable. The trial court also found in favor of CAPCO against Hartford, and in favor of Hartford against Burbic. Burbic and Hartford appeal from the judgment entered against them in favor of CAPCO. We affirm the judgment of the trial court.

Burbic and Hartford assert that the trial court erred in applying the limitations of remedies clause in the present case. The appellants attack the clause on several grounds. First, the appellants contend that the clause is a material alteration of the contract under Code 1975, § 7-2-207, and therefore is not part of the terms of the contract. Second, the limitation of remedies is attacked on the grounds that the limitation is not effective under Code 1975, § 7-2-719. Furthermore, the appellants argue that under the circumstances of this case, the limitation of remedies is unconscionable. Code 1975, § 7-2-302. Finally, the appellants urge this Court to set aside the finding of the trial court that the leaks in the pipes were attributable to the improper installation of the pipes by Burbic's employees.

Burbic and Hartford also assert that the trial court erred in failing to admit evidence of subsequent modification of the pipe and evidence of similar claims against CAPCO or Robintech.

Burbic and Hartford attempted to introduce the testimony of another buyer of Robintech's pipe concerning the buyer's complaints and troubles with the pipe. In Meadows v. Coca-Cola Bottling, Inc., 392 So.2d 825 (Ala.1981), this Court held that while under certain circumstances evidence of similar defects may be admissible, the party must lay a proper predicate for the testimony. No predicate was laid showing that the witness had sufficient expertise and knowledge to testify as to his opinion. Burbic also failed to establish that the pipe used by the other buyer was the same type pipe sold to Burbic. The trial court's decision will not be overturned on appeal unless there is a showing of palpable abuse. Id. The trial judge committed no error in refusing to permit the testimony.

The appellants also contend that the trial court erred in refusing to permit testimony concerning the subsequent modification of the pipe to establish CAPCO's and Robintech's breach of warranty. As the appellants admit, the general rule in Alabama and other states is that evidence of repairs or modifications made by a defendant after the alleged injury occurs is not admissible to show the defendant's antecedent negligence. Montgomery v. Quinn, 246 Ala. 156, 19 So.2d 529 (Ala.1944); Bedgood v. T. R. Miller Mill Co., 202 Ala. 299, 80 So. 364 (Ala.1918). The rationale is that admission of such evidence would discourage persons from improving the condition which caused the injury. Id. Burbic and Hartford note that several courts have held that this rationale is not applicable to subsequent modifications in strict liability cases. The appellants urge this Court to extend the exception for strict liability cases to actions for breach of warranty. 1

"Questions as to the relevancy of testimony is a matter ordinarily within the discretion of the trial court, and unless such discretion has been grossly abused, it will not be considered error on appeal." Costarides v. Miller, 374 So.2d 1335, 1337 (Ala.1979). Burbic sought to admit evidence that Robintech began producing an improved, more expensive pipe which had special provisions against the problems Burbic's employees allegedly confronted with the pipe Burbic purchased. The record shows that Robintech still produces the same pipe that CAPCO sold to Burbic. This evidence coupled with the fact that the pipe which Burbic sought to admit was a more expensive, improved pipe, shows that the trial court did not err in refusing to introduce the new pipe into evidence because it was irrelevant.

Section 7-2-201 of Alabama's version of the Uniform Commercial Code permits a written confirmatory memorandum to satisfy the requirement of the statute of frauds. Thus, the order acknowledgment sent by CAPCO to Burbic is a writing sufficient to satisfy the statute of frauds. Likewise, the fact that the form states additional terms does not affect the enforceability of the contract, given the subsequent dealings of the parties. See Code 1975, § 7-2-207(2). Thus, the preliminary issue is not whether the parties entered into a valid contract, but the issue is what terms are a part of the agreement. Section 7-2-207(2) provides:

(2) The additional terms are to be construed as proposals for addition to the contract. Between merchants such terms become part of the contract unless:

(a) The offer expressly limits acceptance to the terms of the offer;

(b) They materially alter it; or

(c) Notification of objection to them has already been given or is given within a reasonable time after notice of them is received.

As noted by several courts, Section 2-207 of the Uniform Commercial Code was not drafted with great clarity and courts often have great difficulty determining its meaning. See Dorton v. Collins & Aikman Corp., 453 F.2d 1161 (6th Cir. 1972); Roto-Lith, Ltd. v. F. P. Bartlett & Co., 297 F.2d 497 (1st Cir. 1962); Valmont Industries, Inc. v. Mitsui & Co., 419 F.Supp. 1238 (D.Neb.1976); Southwest Engineering Co. v. Martin Tractor Co., 205 Kan. 684, 473 P.2d 18 (1970). The purpose of Section 2-207 was to alter the "mirror" rule of common law, requiring the terms of the offer and acceptance to be identical, or to mirror each other. I. W. Hawkland, A Transactional Guide to the Uniform Commercial Code § 1.090303, at 16 (1964); R. Nordsstrom, Handbook of the Law of Sales, § 37 (1970). An acceptance which contained terms additional to or different from the offer acted as a rejection and a counter-offer. Section 2-207 recognizes that in a commercial setting, the terms of the offer and acceptance will seldom mirror each other. Under Section 2-207 of the Uniform Commercial Code (Code 1975, § 7-2-207), between merchants, proposed terms become part of the contract unless they "materially alter" the contract.

The question before this Court is whether a contractual limitation of remedies is a material alteration of the contract between CAPCO and Burbic. The courts are split on this issue. Compare Roto-Lith, Ltd. v. F. P. Bartlett & Co., 297 F.2d 497 (1st Cir. 1962) and Boese-Hilburn Co. v. Dean Machinery Co., 616 S.W.2d 520 (Mo.Ct.App.1981); with Dorton v. Collins & Aikman Corp., 453 F.2d 1161 (6th Cir. 1972), and Ebasco Services, Inc. v. Pennsylvania Power and Light Co., 402 F.Supp. 421 (E.D.Pa.1975). We hold that the question of whether a limitation of remedies clause materially alters a contract is a question of fact. Dorton v. Collins & Aikman Corp., 453 F.2d 1161 (6th Cir. 1972). Ebasco Services, Inc. v. Pennsylvania Power and Light Co., 402 F.Supp. 421 (E.D.Pa.1975).

In Roto-Lith, Ltd. v. F. P. Bartlett & Co. and Boese-Hilburn Co. v. Dean Machinery Co., the...

To continue reading

Request your trial
16 cases
  • Alabama Power Co. v. Marine Builders, Inc.
    • United States
    • Alabama Supreme Court
    • August 2, 1985
    ...unless that discretion has been grossly abused. Costarides v. Miller, 374 So.2d 1335 (Ala.1979). See also Burbic Contracting Co. v. Cement Asbestos Products Co., 409 So.2d 1 (Ala.1982) (exclusion of post-manufacture improvement in product line is not abuse of trial court's discretion). In t......
  • Shutter Shop, Inc. v. Amersham Corp., CIV. A. 99-D-1279-N.
    • United States
    • U.S. District Court — Middle District of Alabama
    • September 11, 2000
    ...have become part of the sales contract between The Shutter Shop and THH. See Kennedy, 437 So.2d at 81; Burbic Contracting Co. v. Cement Asbestos Prods. Co., 409 So.2d 1, 4 (Ala.1982). Plaintiff cites two cases from other jurisdictions for the proposition that THH's limitation of remedies fa......
  • Mercedes-Benz U.S. Intern., Inc. v. Cobasys, LLC
    • United States
    • U.S. District Court — Northern District of Alabama
    • March 31, 2009
    ...common law, requiring the terms of the offer and acceptance to be identical, or to mirror each other." Burbic Contr. Co., Inc. v. Cement Asbestos Products Co., 409 So.2d 1, 4 (Ala.1982). This section recognizes that in commercial settings, the terms of the offer and acceptance will rarely b......
  • Micor Indus., Inc. v. Mazak Corp.
    • United States
    • U.S. District Court — Northern District of Alabama
    • February 9, 2018
    ...[which] require[es] the terms of the offer and acceptance to be identical, or to mirror each other." Burbic Contracting Co. v. Cement Asbestos Prod. Co., 409 So. 2d 1, 4 (Ala. 1982). Section 7-2-207(1) thus states that:[a] definite and seasonable expression of acceptance or a written confir......