Byington v. Clover Club Potato & Produce Co.

Decision Date21 September 1966
Docket NumberNo. 9536,9536
Citation91 Idaho 165,418 P.2d 206
PartiesDonald BYINGTON and Eugene Byington, Plaintiffs-Respondents, v. CLOVER CLUB POTATO & PRODUCE COMPANY, an Idaho corporation, Defendant-Appellant.
CourtIdaho Supreme Court

Hansen & Hansen, Idaho Falls, for appellant.

Petersen, Moss & Olsen, Idaho Falls, for respondents.

SMITH, Justice.

Appellant appeals from a $6,579.40 judgment entered against it in respondents' favor as damages for breach of a contract for the sale and purchase of a crop of potatoes; it also appeals from orders denying its motions for judgment notwithstanding the verdict and for a new trial.

March 4, 1961, appellant, through its agent Ray DeRoche, manager of its warehouse at Cotton Siding, Idaho, entered into a written contract whereby respondents agreed to grow approximately 50 acres of Kennebec potatoes and appellant agreed to buy 'all lots of potatoes from this acreage graded not less than 85% U.S. #1, with the balance of 15% graded U.S. #2 or better, two inch minimum,' appellant to pay for the potatoes in accordance with the following schedule:

'$1.40 per CWT out of field at harvest time.

'1.50 per CWT Out of Growers Storage up to November 15, 1961.

1.55 per CWT From November 15, 1961 to January 1, 1962.

1.60 per CWT From January 1, 1962 to February 1, 1962.

1.65 per CWT From February 1, 1962 to March 1, 1962.

1.70 per CWT From March 1, 1962 until April 1, 1962--

All spuds to be run by 4/1/62.'

Respondents agreed to purchase the seed potatoes to be approved by the parties; also to store the potatoes until April 1, 1962. The contract then provided: 'Potatoes will be graded and run by Clover Club Potato & Produce Company. If Grower (respondents) has his own crew, an allowance of $.20 per cwt. will be paid him for sorting.'

During a meeting subsequent to the signing of the contract, Mr. DeRoche promised respondents that appellant would begin grading and sorting the potatoes immediately if, while in storage, they showed any indication of deterioration. The evidence is in sharp conflict as to whether Mr. DeRoche further promised that appellant would take all potatoes which met the federal standard for U.S. No. 2 or better.

Thereafter, respondents acquired from appellant 997 cwt. (hundred weight) of Kennebec seed at $3.50 per cwt. if paid for within 30 days after purchase; or at $4.00 per cwt. if not so paid for.

Respondents planted the crop during the growing season of 1961. Because this was their first experience with Kennebec potatoes, respondents maintained a close contact with appellant throughout the summer to see that the proper care was taken of the crop; i. e., irrigation, cutting and rolling the vines, and digging the crop. During the first part of October, 1961, the potatoes were harvested and placed into respondents' potato cellar. At that time the potatoes appeared to be in good condition.

Sometime during the middle part of November 1961 respondents measured the pile of potatoes and cut into a few of them. They determined that the pile consisted of 10,200 cwt.; 75% of which were U.S. No. 2's or better.

November 25, 1961, respondent Donald Byington observed a wet spot developing at the top of the pile about 20 to 25 feet from the back of the cellar. He immediately telephoned Mr. DeRoche who came to the cellar and inspected the potatoes. He advised said respondent 'that there was nothing to be concerned about at that time,' but to continue to check the pile and notify him if the spot started enlarging. Some five days later respondent Eugene Byington telephoned Mr. DeRoche and he again came to the cellar. After examining the potatoes, he concluded that they should be immediately removed from the cellar. He further advised respondent that the cellar temperature, which had been kept at about 35 , should be raised to above 40 and kept there in order to increase the starch content of the potatoes before they were moved. Respondents thereupon placed a 'salamander' (heating stove) in the cellar and raised the temperature to 42 or 43 and kept it at this level until February, 1962, when appellant advised them that no further attempts to grade and run the potatoes would be made.

On or about December 4, 1961, appellant moved its crew (consisting of 5 to 7 men) into respondents' cellar and began 'running' the potatoes. At the end of three days, some 800 sacks, composite pack-U.S. No. 1's and 2's packed together in the same sack, were run before operations ceased because of lack of room to continue work. Appellant's workers departed, leaving the sacked potatoes and did not return until sometime after Christmas during the latter part of December. During that period respondent Eugene Byington called appellant on several occasions urging it to resume operations. Subsequently the sacked potatoes were inspected during the last part of December 1961 or forepart of January 1962 and rejected because of 'external defects.' As a result of the rejection Mr. DeRoche contacted respondents and told them that the potatoes were rejected because they were 'too dirty' and sought permission to 'wet run' the potatoes. The same potatoes were again run and sacked during a 5 to 7 days period during the forepart of January. The work crew was again removed and the potatoes remained for some two weeks before they were inspected on January 27, 1962. All but 116 sacks were rejected because of 'external defects.' On that occasion several of the potatoes cut into showed no notable internal discoloration.

During the forepart of February, the rejected potatoes and several truck loads from the pile were taken to appellant's warehouse at Cotton Siding. By that time sunken spots in the top of the pile were noticeable; water was oozing out of the pile to the extent that a pump had to be placed in the cellar, and spoilage odor was prevalent. Mr. DeRoche testified that appellant had found 'it was impossible to run any portion of these potatoes'; that if respondents could 'run them' and 'could get then into grade,' appellant would buy them, but that appellant was 'going to give up on them.' Respondents' several attempts to sell the potatoes to other sources were unsuccessful. One man trucked some potatoes for 'feed' and promised to pay anything over trucking expenses; respondents received nothing from him. On April 4, 1962, respondents had the remaining potatoes inspected when it was determined that 31% of them were U.S. No. 1's, 31% were No. 2's and the remainder were 'culls.' Eventually some of the potatoes were sold for 'culls' for which respondents received $200.

Respondents filed their complaint alleging breach of contract on the part of appellant for its failure to 'run and grade' the potatoes pursuant to the contract. Appellant admitted the contract but denied the breach thereof, and counterclaimed for the price of the Kennebec potato seed.

At the trial by jury, although not pleading modification of the contract, respondents introduced evidence to show that the written agreement had been modified to the extent that appellant would take all of respondents' potatoes which graded U.S. No. 2 or better and that the potatoes would be 'run' at the first sign of deterioration.

At the close of all of the evidence, appellant moved for a directed verdict which the court denied. The jury returned a verdict in the amount of $6,579.40 for respondents, followed by entry of judgment thereon. Appellant then moved for judgment notwithstanding the verdict and for a new trial, contending that the evidence was insufficient to support the verdict, which motions the court denied. Appellant has appealed from the judgment and from the orders denying the motion for judgment notwithstanding the verdict and for a new trial.

Appellant, in its argument, states that it denies respondents' allegations that the contract was modified by subsequent oral agreement. The jury resolved that issue in favor of respondents. Appellant's brief does not 'contain a distinct enumeration' of any assignment of alleged error so committed, nor citation of authority or argument thereon, thus...

To continue reading

Request your trial
7 cases
  • Deshazer v. Tompkins
    • United States
    • Idaho Supreme Court
    • October 20, 1969
    ...the jury's verdict. Skaggs Drug Centers, Inc. v. City of Idaho Falls,90 Idaho 1, 407 P.2d 695 (1965); Byington v. Clover Club Potato & Product Co., 91 Idaho 165, 418 P.2d 206 (1966); Dawson v. Eldredge, 84 Idaho 331, 372 P.2d 414 (1962). This same rule does not apply, however, to a trial co......
  • Industrial Indem. Co. v. Columbia Basin Steel & Iron Inc., 10260
    • United States
    • Idaho Supreme Court
    • June 16, 1970
    ...not be set aside. I.C. § 13-219; Big Butte Ranch, Inc. v. Grasmick, 91 Idaho 6, 415 P.2d 48 (1966); Byington v. Clover Club Potato & Produce Company, 91 Idaho 165, 418 P.2d 206 (1966); Commercial Credit Equipment Corp. v. Knowlton, 86 Idaho 314, 386 P.2d 370 (1963); Anderson v. Smith Frozen......
  • Bean v. Diamond Alkali Co., 10203
    • United States
    • Idaho Supreme Court
    • May 12, 1969
    ...disturb the verdict. Skaggs Drug Centers Inc., v. City of Idaho Falls, 90 Idaho 1, 407 P.2d 695 (1965); Byington v. Clover Club Potato & Produce Co., 91 Idaho 165, 418 P.2d 206 (1966). The focal point of this appeal, therefore, is whether the opinion testimony of the respondent's witnesses ......
  • Paullus v. Liedkie
    • United States
    • Idaho Supreme Court
    • July 9, 1968
    ...considered is not applicable here. See McLean v. City of Spirit Lake, 91 Idaho 779, 430 P.2d 670 (1967); Byington v. Clover Club Potato & Produce Co., 91 Idaho 165, 418 P.2d 206 (1966); Jordan v. Jordan, 87 Idaho 432, 394 P.2d 163 We shall first deal with appellant's pro se motion for new t......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT