A.C. Hoyle Co. v. Sperry Rand Corp.
Decision Date | 16 November 1983 |
Docket Number | Docket No. 64037 |
Parties | A.C. HOYLE COMPANY, a Michigan corporation, Plaintiff-Appellant, v. SPERRY RAND CORPORATION, Defendant-Appellee. |
Court | Court of Appeal of Michigan — District of US |
Petrucelli & Petrucelli by Vincent R. Petrucelli, Iron River, for plaintiff-appellant.
Bodman, Longley & Dahling by Walter O. Koch and Thomas Van Dusen, Troy, for defendant-appellee.
Before CYNAR, P.J., and J.H. GILLIS and WAHLS, JJ.
Plaintiff, A.C. Hoyle Company, appeals as of right from an April 13, 1982, order of partial summary judgment against it pursuant to GCR 1963, 117.2(1), failure to state a claim upon which relief can be granted.
In its complaint plaintiff alleged that it had entered into a contract with Bethlehem Steel Corporation to supply deck machinery for four ocean-faring oil tankers which Bethlehem was building. The machinery to be supplied by plaintiff was designed to be hydraulically powered.
Plaintiff contracted with Vickers, a division of the defendant corporation, for the design, manufacture, and delivery of 60 hydraulic motors to be incorporated into the system powering the deck machinery. Defendant, however, failed to deliver the motors according to the contracted delivery schedule, and the motors, when delivered and installed, failed to conform to the agreed-upon specifications. Defendant admitted both these allegations.
Plaintiff alleged that it was not able to cancel the contract with defendant because the deck machinery was designed solely for the application of the defendant's motors and the urgencies of Bethlehem Steel's sailing dates did not allow for the substitution of other hydraulic motors.
Plaintiff further alleged:
"[I]n an effort to remedy SPERRY-VICKERS' breach of contract and honor its contract with Bethlehem Steel Corporation, HOYLE was required to expend considerable time and expense in correcting the defective SPERRY-VICKERS split-rise motors; was required to make substantial engineering revisions; was required to incur additional costs from subcontractors; was required to secure substitute subcontractors at a greater expense and cost to complete portions of the contract and that these damages amounted to a sum of money in the excess of One Hundred Ninety Thousand ($190,000.00) Dollars and were a direct proximate cause of SPERRY-VICKERS' breach of contract."
Plaintiff did not allege that the motors were themselves damaged by virtue of their defect, nor did plaintiff allege that the motors caused physical injury to persons or other property.
In its complaint plaintiff sought damages under three theories: breach of contract (Count I), breach of express and implied warranties (Count II) and negligence (Count III). Defendant moved for partial summary judgment as to the negligence count. In that count, plaintiff alleged:
The trial court, in reliance on McGhee v. General Motors Corp., 98 Mich.App. 495; 296 N.W.2d 286 (1980), granted defendant's motion and dismissed the negligence count.
In McGhee, plaintiff purchased a used truck tractor from defendant. While plaintiff was working on the tractor's transmission, the cab fell from the frame to the ground and sustained substantial damage. Plaintiff brought an action for damages against defendant, claiming breach of express and implied warranties, fraud, and negligence. This Court affirmed the trial court's entry of summary judgment dismissing all counts.
Regarding dismissal of the negligence count, the Court held that "no cause of action is stated in the complaint, where the foundation of the relationship between the parties is contractual and no personal injury or damage to property other than the subject goods themselves is alleged". In so holding, the Court adopted the position expressed in S.M. Wilson & Co. v. Smith International, Inc., 587 F.2d 1363, 1376 (CA9, 1978):
" " ...
To continue reading
Request your trial-
Neibarger v. Universal Cooperatives, Inc.
...applying Michigan law to the issue of economic loss stemming from a commercial sale of goods. In A.C. Hoyle Co. v. Sperry Rand Corp., 128 Mich.App. 557, 561-562, 340 N.W.2d 326 (1983), the court affirmed the dismissal of the plaintiff's claim of negligence in the design, manufacture, and de......
-
Hart Engineering Co. v. FMC Corp., Civ. A. No. 83-0219 S.
...Argo Welded Products, Inc. v. J.T. Ryerson Steel & Sons, Inc., 528 F.Supp. 583, 586 (E.D.Pa.1981); A.C. Hoyle Co. v. Sperry Rand Corp., 128 Mich.App. 557, 340 N.W.2d 326, 327-29 (1983); National Crane Corporation v. Ohio Steel Tube Company, 213 Neb. 782, 786-90, 332 N.W.2d 39, 44 (1983); Ka......
-
Liberty Ins. Corp. v. LSP Prods. Grp., Inc.
...purpose. Accordingly, the economic-loss doctrine bars Cincinnati's four tort claims. See A.C. Hoyle Co. v. Sperry Rand Corp. , 128 Mich.App. 557, 340 N.W.2d 326, 329 (1983) (per curiam) (holding that trial court properly dismissed buyer's cause of action for negligence, because both buyer a......
-
Ritter v. Custom Chemicides, Inc.
...Prairie Production, Inc. v. Agchem Div.-Pennwalt Corp., 514 N.E.2d 1299, 1304-06 (Ind.Ct.App.1987); A.C. Hoyle Co. v. Sperry Rand Corp., 128 Mich.App. 557, 340 N.W.2d 326, 327-29 (1983); National Crane Corp. v. Ohio Steel Tube Co., 213 Neb. 782, 332 N.W.2d 39, 44 (1983); Local Joint Executi......