Calderwood v. Bender

Decision Date29 March 1983
Citation189 Conn. 580,457 A.2d 313
CourtConnecticut Supreme Court
PartiesDaniel P. CALDERWOOD v. Jack BENDER.

M. Hatcher Norris, Glastonbury, for appellant (defendant).

Mary E. Holzworth, Norwich, with whom was Jackson T. King, Jr., Norwich, for appellee (plaintiff).

Before PETERS, HEALEY, PARSKEY, SHEA and GRILLO, JJ.

PARSKEY, Associate Justice.

This case involves a claim for damages caused by the installation of inadequate and defective septic tank systems. Judgment was rendered for the plaintiff and the defendant has appealed. The defendant assigns error in the trial court's finding that the failure of the septic tank systems was proximately caused by the defendant's negligence. The defendant also claims that the amount of damages awarded was erroneous because it was based on an improper standard. We find no error.

The court found the following facts: On or about April 1, 1978, the plaintiff entered into two building contracts, one with Michael Pankiw and the other with Carmelo Franco, to build for each of them a dwelling on the property each owned. The lots of the owners were adjoining and located on Village Hill in the town of Lebanon. Each agreement obligated the plaintiff to install a septic system in connection with the construction of the residences.

Sometime in May, 1978, the plaintiff contacted the defendant, a licensed septic installer, and asked him if he could put in a septic system at the rear of each house and how much it would cost. The defendant replied that he could but that he had to consult the town sanitarian. About a week later the defendant stated he would put the systems in for $2400. The plaintiff then told the defendant to put them in and when they were completed the contract price was paid. At that time, the plaintiff had very little knowledge about installation of septic systems and relied on the defendant to put in a reliable system in accordance with the state public health code.

The septic system on the Franco lot began to overflow and cause offensive odors in the early fall of 1978 and the septic system on the Pankiw lot began to overflow and cause offensive odors in February, 1979. The plaintiff complained to the defendant in each instance. On May 9 and May 21, 1979, the plaintiff sent the defendant letters demanding that the septic systems be corrected. The defendant ignored each letter. Thereafter, the plaintiff hired James Burns to remedy the situation at a cost of $5412. The old systems had to be ripped out and new systems installed. Burns used thirty-seven loads of fill and nine loads of loam for one lot and twenty-nine yards of fill for the other lot in installing the septic systems.

When the defendant contracted to do the jobs in May, 1978, he relied on the opinion of the town sanitarian as to the size and layout of the systems. There was a brook to the rear of the two lots in question. After consultation with the sanitarian, the defendant, on the Franco lot, instead of laying out the system according to the state code, "squeezed" the lines so that the three lines running from the distribution box were closer to each other than the state code permitted. After consultation with the town sanitarian, he also installed one tank nearer to the dwelling than the code permitted. While digging the trench on the Franco lot, ground water appeared in the trench but he continued with the installation of the systems.

In the fall of 1979, the defendant did examine the Franco system but no corrective measures were taken. When the defendant was notified of the failure of the Pankiw septic system he requested a Mr. Schur of the state health services to investigate. Schur's opinion, based on percolation tests made on each lot, was that a plan by an engineer would be necessary as the properties in their present condition were unsuitable for sewage disposal. An engineer engaged by the defendant testified to the same effect. The accuracy of their opinion was, however, put into doubt because of the location of the holes for the percolation tests upon which they relied; the plaintiff's witnesses testified that it was inappropriate to dig test holes between...

To continue reading

Request your trial
27 cases
  • Martins v. Connecticut Light and Power Co.
    • United States
    • Connecticut Court of Appeals
    • September 14, 1994
    ...a plaintiff to maintain a cause of action in negligence, the plaintiff must show the existence of a duty of care. Calderwood v. Bender, 189 Conn. 580, 584, 457 A.2d 313 (1983); O & G Industries, Inc. v. New Milford, 29 Conn.App. 783, 790, 617 A.2d 938 (1992), aff'd, 229 Conn. 303, 640 A.2d ......
  • Willow Springs Condominium Ass'n, Inc. v. Seventh BRT Development Corp.
    • United States
    • Connecticut Supreme Court
    • June 2, 1998
    ...mean, however, that current cost of repair estimates cannot be evidence of the extent of earlier damage. 56 In Calderwood v. Bender, 189 Conn. 580, 583, 457 A.2d 313 (1983), for example, we stated that the actual cost of repairing a faulty septic system was the proper measure of damages. It......
  • Catz v. Rubenstein
    • United States
    • Connecticut Supreme Court
    • August 12, 1986
    ...are essential elements of a cause of action in negligence. Prosser & Keeton, Torts, (5th Ed.) § 30, pp. 164-65; Calderwood v. Bender, 189 Conn. 580, 584, 457 A.2d 313 (1983); Coburn v. Lenox Homes, Inc., 186 Conn. 370, 375, 441 A.2d 620 (1982); Busko v. DeFilippo, 162 Conn. 462, 466, 294 A.......
  • Rivera v. Fairbank Management Properties, Inc.
    • United States
    • Connecticut Superior Court
    • August 7, 1997
    ...are essential elements of a cause of action.... [W.] Prosser & [W.] Keeton, Torts, (5th Ed.) § 30, pp. 164-65; Calderwood v. Bender, 189 Conn. 580, 584, 457 A.2d 313 (1983); Coburn v. Lenox Homes, Inc., 186 Conn. 370, 375, 441 A.2d 620 (1982); Busko v. DeFilippo, 162 Conn. 462, 466, 294 A.2......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT