Caldwell & Drake v. Schmulbach
Decision Date | 23 December 1909 |
Citation | 175 F. 429 |
Parties | CALDWELL & DRAKE v. SCHMULBACH. |
Court | U.S. Court of Appeals — Fourth Circuit |
substantial performance of the contract precluding the owner from resisting payment of a balance of over $20,000 of the contract price under a provision requiring the work to be completed to the satisfaction of the architects and the owner before final payment.
This bill is filed to enforce a mechanic's lien. On February 9, 1905, the plaintiffs contracted to perform certain specified work toward the erection of a 12-story office building in Wheeling with the defendant for $231,698, payable upon estimates made every 30 days, with 10 per cent. reserved until 20 days 'after contract is completed and satisfactory to architects and owner,' when final payment was to be made. Further provisions of the contract relating to matters in controversy here were: That the work was to be done 'under direction and to the satisfaction of M. F Gierey and F. F. Faris, architects, acting for the purpose of the contract as agents of the owner. ' That That ' That '
On August 17, 1907, plaintiffs filed their notice, account, and declaration of mechanic's lien in which they claim a balance due on the contract of $24,009.58 and for a large number of specified extras, $26,122.97, less $406.80 for work omitted netting $49,725.75, and to enforce this lien this bill was filed at September rules following. The defendant has filed answer, not denying the contract nor assailing the regularity of the proceedings taken to secure and enforce the mechanic's lien, but denying the accuracy and verity of the account and demands upon which it is based. By this answer it is claimed that the true amount due upon the contract is $21,309.58; that the utmost amount the plaintiffs can justly claim for extras is $6,155.40, as against which sums defendant is entitled to set off $6,329.06 for omitted and defective work and $29,150 liquidated damages at the rate of $50 per day as fixed by the contract, for 583 days' delay in finishing the work, thereby extinguishing plaintiffs' just demands and leaving them, in fact, indebted to plaintiffs in the sum of $8,014.08.
To this answer replication has been made and proofs taken and the cause submitted.
James W. Ewing, John A. Howard, and John J. Coniff, for plaintiffs.
Samuel M. Noyes, Caldwell & Caldwell, and Nelson C. Hubbard, for defendant.
DAYTON, District Judge (after stating the facts as above).
Records like this, weighing over 100 pounds, consisting of over 3,200 typewritten pages of evidence (which counsel with commendable industry have sought to abstract within a limit of 800 pages), books of accounts, plans, specifications, drawings, correspondence, contracts, stipulations, and agreements, all of which must receive careful study and consideration, may possibly throw some light upon the vexed question of the law's delays and failure of the courts to expedite business. It seems clear to me, after having read this record, that a reference to a master will be absolutely necessary, no matter how much the delay is to be regretted, unless I take the time to state an account between these parties involving more than 200 items, on the one hand, ranging from 20 cents to over $6,000 for extras, and, on the other hand, for similar items of omitted and defective work. It does seem to me, however, that I should, in order to expedite this work before a master, indicate that sufficient evidence in my judgment has already been taken to fully enable him to state such account, and that, unless special reasons be shown to the contrary, he should be limited to the record as it now stands. Further, it seems to me that I may very well pass upon matters of principal dispute herein involving legal propositions, leaving him thus unembarrassed, to make the necessary calculations as to such items.
It becomes necessary, therefore, to consider first the claim of defendant for $29,150 damages for delay in the completion of the contract. It is claimed by defendant that this contract was a West Virginia one, and that the Supreme Court of Appeals of West Virginia in the recent case of the Charleston Lumber Co. v. Friedman, 64 W.Va. 151, 61 S.E. 815, has determined that a provision similar to the one here fixing a specific sum to be paid per day for delay in the execution of the contract is enforceable, not as a penalty, but as liquidated damages. And the cases of Wheeling Mold & Foundry Company v. Wheeling Steel & Iron Co., 58 W.Va. 62, 51 S.E. 129, and Sun Printing & Publishing Association v. Moore, 183 U.S. 642, 22 Sup.Ct. 240, 46 L.Ed. 366, are cited in support of this contention. There can be no question of the soundness of this position where delays in execution of such a contract are wholly occasioned by the default of the contractor, but this I perceive to be the full extent to which these decisions go. In the Lumber Co. v. Friedman Case the contractor undertook to erect complete a store building by a fixed date, and to pay $10 per day for each day thereafter that the building remained incomplete and unfinished. The enforcement of this clause was resisted on the ground that it was a penalty, and equity would not enforce it. Reversing the court below so holding, the Supreme Court of Appeals...
To continue reading
Request your trial-
Gillioz v. State Highway Com'n
... ... 867; Vitler Mfg. Co ... v. Tygart Valley Brewing Co., 168 F. 1002; Caldwell ... v. Schmulbach, 175 F. 429; Standard Steel Car Co. v ... United States, 67 Court of ... ...
- In re Harper
-
Redlinger & Hanson Co., a Corp. v. Parker
... ... L.R.A.(N.S.) 363, 93 N.E. 81; Murphy v. Kassis, 59 ... N.D. 35, 228 N.W. 449; Caldwell v. Schmulbach, 175 ... F. 429; King Iron Bridge Mfg. Co. v. St. Louis, 10 L.R.A ... ...
-
Hart v. American Concrete Steel Co.
... ... Gearty v. Mayor, etc., of New ... York, 171 N.Y. 61, 63 N.E. 804; Caldwell & Drake v ... Schmulbach (C.C.) 175 F. 429; Wilson v. Curran, ... 190 A.D. 581, 180 N.Y.Supp ... ...