Catamount Const., Inc. v. Town of Milford

Decision Date16 September 1981
Docket NumberNo. 80-349,80-349
Citation435 A.2d 123,121 N.H. 781
PartiesCATAMOUNT CONSTRUCTION, INC. v. TOWN OF MILFORD.
CourtNew Hampshire Supreme Court

Wiggin & Nourie, Manchester and Snyder, Tepper & Berlin, Boston, Mass. (Gary Ellis Hicks, & a., Manchester, on the brief and Mr. Hicks orally), for plaintiff.

Patrick J. Enright, Milford, by brief and orally for defendant.

BROCK, Justice.

In this petition for declaratory judgment (RSA 491:22) the plaintiff, Catamount Construction, Inc., seeks a judicial determination of its obligations under a construction contract with the defendant, Town of Milford. Specifically, the issue is which party must reimburse the Boston & Maine Railroad for the cost of a railroad crossing associated with the construction of a wastewater treatment plant being built by the plaintiff. The Superior Court (Goode, J.) ruled that the plaintiff was obligated to pay the costs of the railroad crossing, and the plaintiff then filed its notice of appeal in this court. For the reasons which follow, we reverse.

On July 19, 1979, the parties entered into a construction contract which called for the construction of a wastewater treatment facility and pumping station in Milford. Because of the location of the proposed plant, the construction of a railroad crossing was contemplated, and the contract, therefore, required the plaintiff to "furnish all materials, labor, tools and equipment necessary to install the sewer pipe under the railroad tracks and construct the rubber track" railroad crossing. The trial court found that both parties were aware that the Boston & Maine Railroad would require that itspersonnel perform the required track work. Moreover, the contract called for the plaintiff to cooperate with the railroad and perform the crossing work "in a manner fully satisfactory" to the railroad.

The plaintiff requested the railroad to install the crossing, and the railroad agreed on the condition that it be paid a $25,000 deposit toward actual construction costs. That amount exceeded the contract allowance of $3,200 for the crossing. The plaintiff therefore requested that the defendant town assume all costs for the crossing in excess of that amount. The town took the position that the stated allowance of $3,200 was the total it was required to pay under the contract for the crossing, and it denied the plaintiff's request. Following that decision, the plaintiff filed its petition for a declaratory judgment in the superior court.

The proper interpretation of contracts is a question of law. Murphy v. Doll-Mar, Inc., 120 N.H. 610, 611, 419 A.2d 1106, 1108 (1980). "In reaching the proper interpretation we require that the words and phrases used by the parties be given their common meaning ... and this court will determine the meaning of the contract based upon the meaning that would be attached to it by a reasonable person." Id. at 611-12, 419 A.2d at 1108. (Citation omitted). Applying that rule to the facts of this case can result in only one conclusion; the defendant town must bear the entire cost of the railroad crossing.

The pertinent portion of the "Stated Allowances" section of the contract provides:

                "PART 1.01 GENERAL
                 -----------------
                1.01    Stated allowances shall be as follows
                          ITEM                                                ALLOWANCE DOLLARS
                          ----                                                -----------------
                . . 
                    H.    Railroad Personnel Expenses                                 $3,200.00
                    1.   Stated allowance for railroad work shall be for
                         personnel, inspection and other items of expense
                         billed to the Contractor by the railroads in the
                         normal course of constructing the work on or
                         under railroad property, but will not be used to
                         reimburse the Contractor for expenses incurred
                         by his own carelessness or by unauthorized work
                1.02    Stated allowances shall be paid as described in
                        the PROPOSAL and as in SECTION 34 of the
                        GENERAL CONDITIONS, also Railroad Work
                        shall be paid as outlined in SECTION 02850 and
                        Electrical Work shall be paid as outlined in
                        SECTION 16010.
                1.03    The dollar amount stated is only approximate.  If
                        the Contractor's actual cost as billed is greater or
                        less than the quoted allowances in 1.01 above,
                        appropriate adjustments will be made and the
                        Contractor shall be reimbursed if necessary.
                                   END OF SECTION 01020"
                (Emphasis added.)
                

The town contends that the "Stated Allowances" section only contemplated the expenses associated with railroad inspectors and railroad flagmen, who were needed to control traffic. We cannot accept such an interpretation because paragraph "H.1" clearly states that the allowance is for "personnel, inspection and other items of expense ..." for work performed by the railroad in the normal course of construction. In addition, section 1.03 clearly provides that the plaintiff shall be reimbursed if actual costs are greater than the stated allowance.

We can find no portion of the contract that can reasonably be interpreted as supporting the town's position. Indeed, the town's position is made even more untenable when the following contract provision is considered:

"4.02 Charges to the Contractor by the railroad for review, inspection, flagmen or any other required activity by the railroad for the proposed construction will be paid to the Contractor as a stated allowance in Section 01020. Allowances are approximate and the actual amount to be paid may be more or less but shall match the actual amount paid to the railroad provided that the Contractor shall record the actual amounts paid to the railroad, and at the end of each month submit the total of charges paid for that month, in 5 copies to the Engineer."

(Emphasis added.) The phrase "any other required activity" is used without limitation; it encompasses all costs associated with work that the railroad determines it must perform.

The contract provisions are clear. All costs billed to the plaintiff by the Boston & Maine Railroad for construction of the crossing in question must be paid by the defendant.

So ordered; judgment below vacated.

DOUGLAS and BATCHELDER, JJ., did not sit.

BOIS, J., dissents.

The others concurred.

BOIS, Justice, dissenting:

I disagree with the majority's conclusion that "no portion of the contract ... can reasonably be interpreted as supporting the town's position," and, therefore, would reach a different result.

Section 02850 of the contract, entitled "Work on Railroad Property" reads in pertinent part:

"PART 1 SCOPE

1.01 The Contractor shall furnish all materials, labor, tools and equipment necessary to install the sewer pipe under the railway tracks and construct the rubber track crossing at the location shown on the Drawings."

As noted by the majority, there is no doubt that "the contract, therefore, required the plaintiff to 'furnish all materials, labor, tools and equipment necessary to install the sewer pipe under the railroad tracks and construct the rubber track' railroad crossing." (Emphasis supplied.)

"1.03 All requirements of the Railroad shall be strictly adhered to and if...

To continue reading

Request your trial
5 cases
  • In re Ames Dept. Stores, Inc.
    • United States
    • U.S. Bankruptcy Court — Southern District of New York
    • 14 Octubre 2004
    ...that such a distinction is relevant. 71 Baker v. McCarthy, 122 N.H. 171, 443 A.2d 138, 140 (1982); Catamount Constr., Inc. v. Town of Milford, 121 N.H. 781, 435 A.2d 123, 124 (1981). 72 See supra, notes 56-61, 63 and accompanying text. 73 Murphy v. Doll-Mar, Inc., 120 N.H. 610, 419 A.2d 110......
  • Baker v. McCarthy, 81-122
    • United States
    • New Hampshire Supreme Court
    • 5 Marzo 1982
    ...that the proper interpretation of a contract, such as a deed, is a question of law for this court. Catamount Const. Inc. v. Town of Milford, 121 N.H. 781, 782-83, 435 A.2d 123, 124 (1981); Clark v. Neergaard, 121 N.H. 632, 635, 434 A.2d 599, 600 (1981). In reaching the proper interpretation......
  • Exeter Banking Co. v. New Hampshire Ins. Co.
    • United States
    • New Hampshire Supreme Court
    • 8 Diciembre 1981
    ...meaning of the contract based upon the meaning that would be attached to it by a reasonable person." Catamount Construction, Inc. v. Town of Milford, 121 N.H. ---, 435 A.2d 123 (1981) (quoting Murphy v. Doll-Mar, Inc., 120 N.H. 610, 611-12, 419 A.2d 1106, 1108 An insurance contract, moreove......
  • Ocor Products Corp. v. Walt Disney Productions
    • United States
    • U.S. District Court — District of New Hampshire
    • 8 Febrero 1988
    ...of Ocor, but of Decomatic, S.A. The proper interpretation of a contract is a question of law. Catamount Const., Inc. v. Town of Milford, 121 N.H. 781, 782, 435 A.2d 123, 124 (1981). The Court must give the words and phrases used by the parties their common meaning—the meaning a reasonable p......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT