CECO Corp. v. Concrete Specialists, Inc.

Decision Date11 April 1989
Docket NumberNo. 19769,19769
Parties53 Ed. Law Rep. 705 CECO Corporation, Plaintiff and Appellant, v. CONCRETE SPECIALISTS, INC., a Utah corporation, et al., Defendants and Appellees. BLUMENTHAL BROTHERS, INC., a Utah corporation, and Industrial Indemnity Company, a California corporation, Cross-Claimants and Third-Party Plaintiffs, v. STANSBURY MINING CORPORATION, a Utah corporation, Victor Borcherds, and John Does and Jane Roes, numbers 1 through 15, Cross-Defendants and Third-Party Defendants.
CourtUtah Supreme Court

George M. Haley, Robert H. Rees, Salt Lake City, for plaintiff and appellant.

William T. Thurman, David W. Slaughter, John G. Marshall, Kenton W. Willis, David E. Leta, Salt Lake City, for defendants and appellees.

ZIMMERMAN, Justice:

Plaintiff CECO Corporation appeals from a trial court's grant of summary judgment dismissing its action against third-party plaintiff Blumenthal Brothers, Inc. CECO claims that the trial court erred in holding that CECO was estopped from asserting its claim against Blumenthal. Blumenthal cross-appeals from the trial court's dismissal of its third-party action for indemnification against Stansbury Mining Corporation, Victor Borcherds, and others. In the event that this Court reverses the trial court's grant of summary judgment, Blumenthal seeks reinstatement of its third-party claim. We reverse the trial court's dismissal of CECO's claim against Blumenthal and of Blumenthal's indemnification action against the third-party defendants.

This case was presented to the trial court on stipulated facts, which are summarized below. In November of 1980, Blumenthal signed a contract with the Board of Education of the Murray School District. Blumenthal was to act as general contractor for the construction of an addition to the Murray High School gymnasium. Blumenthal posted a 100 percent labor and materials payment bond with the School District, as required by sections 53-11-1 and 63-56-38 of the Utah Code. 1 In December of 1980, Blumenthal subcontracted the concrete work on the project to Concrete Specialists, Inc. ("CSI"), which did not post a bond. In January of 1981, CSI sub-subcontracted a portion of its work to CECO. CECO fully performed its work under the CSI/CECO contract between May and August of 1981.

Blumenthal made periodic payments to CSI as construction progressed. By August of 1981, CSI had received approximately $180,000 from Blumenthal, but had not paid CECO anything. Therefore, during the first week of August of 1981, James Trenam, CECO's district manager, telephoned William H. Blumenthal, Vice-President of Blumenthal. Trenam asked Blumenthal if any payments had been made to CSI, notified him that CSI had not yet paid CECO for the work it had performed, and asked Blumenthal if he could put some pressure on CSI to pay CECO. Blumenthal responded that he had made regular payments to CSI and that he would attempt to help CECO. He offered to make checks for CSI's next payments payable jointly to CSI and CECO. Trenam replied that CSI had agreed to pay CECO on August 14, 1981, and asked Blumenthal to refrain from making a payment to CSI until after that date. Blumenthal complied with this request.

On August 19, 1981, Trenam called William Blumenthal again. Trenam notified Blumenthal that CECO had received payment from CSI on its first invoice and that, although CSI still owed CECO approximately $21,500 on subsequent invoices, CSI had represented that it would pay this amount to CECO. Trenam stated that it appeared it would not be necessary for Blumenthal to pay CSI by checks jointly payable to CSI and CECO in order to ensure CECO's being paid, that Blumenthal should go ahead and pay CSI in the ordinary way as it had in the past, as is the custom in the industry, and that CECO would continue to seek payment directly from CSI. Blumenthal subsequently paid CSI $16,020 on August 20, 1981, and $9,630 on September 25, 1981, without making the checks jointly payable to CSI and CECO. Sometime in September, CSI failed to perform further on its contract with Blumenthal. CSI also failed to make any more payments to CECO and eventually filed a petition in bankruptcy. On November 4, 1981, CECO notified Blumenthal in writing of CSI's payment default, as required by Blumenthal's payment bond and informed Blumenthal that it was making a claim for $25,399.70 as amounts due but unpaid from CSI. Trenam also telephoned William Blumenthal on December 16, 1981, and personally informed him that CSI had made no payments after August 19, 1981. Blumenthal replied that Blumenthal did not owe any further sums to CSI and therefore could not help CECO with checks made jointly payable to CSI and CECO.

CECO instituted this action against Blumenthal and its indemnity bond carrier. The trial court granted Blumenthal summary judgment. It held that because Trenam refused Blumenthal's offer to issue checks to CSI made jointly payable to CSI and CECO, permitted Blumenthal to pay CSI directly, and represented that it would look to CSI for payment, CECO was estopped from later asserting a claim against Blumenthal for sums that would be otherwise due under the bond. On appeal, CECO argues that the trial court erred in holding that it was estopped. CECO contends that the facts essential to create an estoppel defense are missing.

The standard of review when considering a challenge to a summary judgment is settled. A grant of summary judgment is appropriate only when no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law. Utah R.Civ.P. 56(c); see, e.g., Geneva Pipe Co. v. S & H Ins. Co., 714 P.2d 648, 649 (Utah 1986). And in deciding whether the trial court properly granted judgment as a matter of law to the prevailing party, we give no deference to the trial court's view of the law; we review it for correctness. See Mountain Fuel Supply Co. v. Salt Lake City Corp., 752 P.2d 884, 887 (Utah 1988); Atlas Corp. v. Clovis Nat'l Bank, 737 P.2d 225, 229 (Utah 1987); Scharf v. BMG Corp., 700 P.2d 1068, 1070 (Utah 1985). Here, because there is no dispute as to the facts, we are faced with a purely legal question: Do the facts show estoppel?

Estoppel is an equitable defense that requires proof of three elements: (i) a statement, admission, act, or failure to act by one party inconsistent with a claim later asserted; (ii) reasonable action or inaction by the other party taken or not taken on the basis of the first party's statement admission, act, or failure to act; and (iii) injury to the second party that would result from allowing the first party to contradict or repudiate such statement, admission, act, or failure to act. Celebrity Club, Inc. v. Utah Liquor Control Comm'n, 602 P.2d 689, 694 (Utah 1979); see also Blackhurst v. Transamerica Ins. Co., 699 P.2d 688, 691 (Utah 1985); United American Life Ins. Co. v. Zions First Nat'l Bank, 641 P.2d 158, 161 (Utah 1982); J.P. Koch, Inc. v. J.C. Penney Co., 534 P.2d 903, 905 (Utah 1975).

CECO first contends that the facts essential to show the first element of an estoppel defense are not present, to wit: CECO has not been shown to have said or done anything that is inconsistent with its assertion that it is entitled to collect the unpaid amounts from Blumenthal on the bond. Trenam, in his August 19, 1981 conversation with Blumenthal, declined Blumenthal's offer to make CSI's payments by checks made jointly payable to CSI and CECO, stating that such act was not necessary since CSI had just made a partial payment and had assured CECO that it would pay the remaining amounts due. Trenam also said that CECO would seek payment directly from CSI for the remaining amounts owed and that Blumenthal should pay CSI directly, as was the normal...

To continue reading

Request your trial
45 cases
  • State v. Hamilton
    • United States
    • Utah Supreme Court
    • May 9, 2003
    ...the other "party to contradict or repudiate" its earlier "statement, admission, act, or failure to act." CECO Corp. v. Concrete Specialists, Inc., 772 P.2d 967, 969-70 (Utah 1989). ¶ 35 Here, Hamilton contends that the trial court erred in allowing the State to proceed forward with its crim......
  • Sfr, Inc. v. Comtrol, Inc.
    • United States
    • Utah Court of Appeals
    • January 25, 2008
    ...S.E.2d 128, 131 (1956)), vacated on other grounds, 163 Ariz. 340, 788 P.2d 73 (1990). 8. SFR's citation to CECO Corp. v. Concrete Specialists, Inc., 772 P.2d 967, 968-71 (Utah 1989), is similarly inapplicable. CECO involved a subcontractor's refusal of the general contractor's offer to issu......
  • Breuer-Harrison, Inc. v. Combe
    • United States
    • Utah Court of Appeals
    • September 24, 1990
    ...when no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law." Ceco v. Concrete Specialists, Inc., 772 P.2d 967, 969 (Utah 1989); see also Utah R.Civ.P. 56(c). We construe the facts and view the evidence in the light most favorable to the los......
  • Bahr v. Imus
    • United States
    • Utah Supreme Court
    • April 1, 2011
    ...v. Utah Liquor Control Comm'n, 602 P.2d 689, 694 (Utah 1979) (internal quotation marks omitted); see also CECO Corp. v. Concrete Specialists, Inc., 772 P.2d 967, 969–70 (Utah 1989). We now extend these elements—with some modification—to the specific context of a boundary dispute. ¶ 24 First......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT