Center for Biological Div. V. Marina Point Dev.

Citation566 F.3d 794
Decision Date06 August 2008
Docket NumberNo. 07-55243.,No. 07056574.,No. 06-56193.,06-56193.,07-55243.,07056574.
PartiesCENTER FOR BIOLOGICAL DIVERSITY; Friends of Fawnskin, Plaintiffs-Appellees, v. MARINA POINT DEVELOPMENT CO.; Okon Development Co.; Oko Investments, Inc.; Northshore Development Associates, L.P., e/s/a North Shore Development Associates, L.P.; Site Design Associates, Inc.; Ken Discenza; VDLP Marina Point; Venwest Marina Point, Inc., e/s/a Venture West Inc.; Irving Okovita, Defendants-Appellants. Center for Biological Diversity; Friends of Fawnskin, Plaintiffs-Appellees, v. Marina Point Development Co.; Okon Development Co.; Oko Investments, Inc.; Northshore Development Associates, L.P., e/s/A North Shore Development Associates, L.P.; Site Design Associates, Inc.; Ken Discenza; VDLP Marina Point; Venwest Marina Point, Inc., e/s/a Venture West Inc.; Irving Okovita, Defendants-Appellants. Center for Biological Diversity; Friends of Fawnskin, Plaintiffs-Appellees, Marina Point Development Co.; Okon Development Co.; Oko Investments, Inc.; Northshore Development Associates, L.P., e/s/a North Shore Development Associates, L.P.; Site Design Associates, Inc.; Ken Discenza; VDLP Marina Point; Venwest Marina Point, Inc., e/s/a Venture West Inc.; Irving Okovita, Defendants-Appellants.
CourtUnited States Courts of Appeals. United States Court of Appeals (9th Circuit)

Robert D. Crockett, Latham & Watkins LLP, Los Angeles, CA, for the defendants-appellants.

Bernice Conn, Robins, Kaplan, Miller & Ciresi L.L.P., Los Angeles, CA, for the plaintiffs-appellees.

Appeal from the United States District Court for the Central District of California, Manuel L. Real, District Judge, Presiding. D.C. No. CV-04-07036-R-RZ.

Before: FERDINAND F. FERNANDEZ, PAMELA ANN RYMER, and ANDREW J. KLEINFELD, Circuit Judges.

Opinion by Judge FERNANDEZ; Concurrence by Judge RYMER: Partial Concurrence and Partial Dissent by Judge KLEINFELD.

ORDER AMENDING OPINION AND DENYING APPELLEES' PETITION FOR REHEARING EN BANC AND AMENDED OPINION
ORDER

We amend our opinion originally filed on August 6, 2008, and commencing at slip op. 9919,1 as amended on March 27, 2009, and commencing at slip op. 36972 as follows:

(1) We revoke the first sentence of the first full paragraph at slip op. 3717(913) and substitute the following in its place:

Moreover, long before any action was filed and, in fact, before 60 days had gone by, the Corps issued its cease and desist order on July 23, 2003, and all activity by Marina Point regarding the lake stopped as it had to.

(2) We revoke the first paragraph at slip op. 3719(913) and substitute the following in its place:

In fine, the notices were insufficient at their inception regarding wetlands and possible § 402 violations, and to the extent that they were sufficient, if barely so, as to possible § 404 violations, their efficacy was limited by prompt Corps and Marina Point action. The district court did not have jurisdiction to hear the CWA action, and it should have dismissed the action at the outset. Thus, in this respect the district court's judgment must fall for lack of jurisdiction, and must be vacated.

Appellees' petition for rehearing en banc filed April 10, 2009, which relates to appeal No. 06-56193 and appeal No. 07-56574, was circulated to the judges of the court, and no judge requested a vote for en banc consideration.

Appellees' petition for rehearing en banc is DENIED. No subsequent petition for rehearing or rehearing en banc may be filed.

Appellants' petition for rehearing and for rehearing en banc filed April 10, 2009, which relates to appeal number 07-55243, remains under consideration and will be ruled upon in a subsequent order of this court.

OPINION

FERNANDEZ, Circuit Judge:

Marina Point Development Associates, Okon Development Co., Oko Investments, Inc., Northshore Development Associates, L.P., Irving Okovita, Site Design Associates, Inc., Ken Discenza, VDLP Marina Point L.P. and Venwest Marina Point, Inc. (collectively "Marina Point") appeal the district court's judgment on the merits in favor of Center for Biological Diversity and Friends of Fawnskin (collectively "the Center") on their claims under the Clean Water Act (CWA),1 and under the Endangered Species Act (ESA).2 Marina Point also appeals the district court's order awarding attorney fees to the Center and the district court's contempt order. We vacate the district court's judgment on the merits and instruct it to dismiss for lack of jurisdiction. We reverse the contempt order and vacate the order awarding attorney fees.

BACKGROUND

Marina Point's 12.51 acre development project site is located on the north shore of Big Bear Lake and the east shore of Grout Bay in the San Bernardino Mountains. The property extends from the edge of the trees to the lake. The land area, known as "Cluster Pines," had functioned as a tavern, recreational vehicle park, campground, and licensed commercial marina from the early 1950's until 2001. Marina Point acquired the property in 1989 in order to develop a residential condominium project upon it.

After acquiring the property, Marina Point began securing permits. The United States Army Corps of Engineers (Corps) solicited public comment, and ultimately concluded that the planned development could go forward. The Corps stated that the United States Fish and Wildlife Service (FWS) had ultimately determined that the upland portion of the site was not a suitable bald eagle habitat, and that a consultation pursuant to 16 U.S.C. § 1536 was not required. On September 10, 1991, the Corps granted a permit to Marina Point which authorized it to strengthen the existing shoreline. See 33 U.S.C. § 1344.

The permit authorized Marina Point to dredge the adjacent shoreline and the interior of the existing marina, and to use the dredged material as fill for building pads on the land.

Marina Point was forbidden, however, from placing rip-rap3 at elevations below lake bottom contours, from depositing sand below the ordinary high water mark, and from transferring fill or structures to neighboring wetlands. In order to protect bald eagles' seasonal behavioral habits, it was also barred from working during the winter months. Besides the permit from the Corps, Marina Point secured permits from the County of San Bernardino, the California Department of Fish and Game, and Big Bear Municipal Water District. In addition, the California Regional Water Quality Control Board issued a water discharge requirements order.

Work began in May 2002, but Marina Point's permit from the Corps expired on September 10, 2002, after several extensions. Marina Point graded the land area before the permit expired. On October 7, 2002, Marina Point's contractor also used a grader to remove trees on the land. Moreover, the Corps allowed Marina Point to proceed with dredging without a permit as long as that did not result in more than "incidental fallback" of soil within the Corps' jurisdiction, but the Corps disallowed any pushing or pulling of materials along the lake bed.

Work resumed at the site in June of 2003 and went on until about July 23, 2003, when the Corps issued a Cease and Desist Order to Marina Point. The Corps' stated reasons for the order were that Marina Point's use of a dragline bucket, rather than a clamshell dredge, caused more than incidental fallback of soil, and that the contractor had been temporarily stockpiling material below the ordinary high water mark.

In September 2003, Marina Point requested interim approval to resume work. The Corps then issued an Initial Corrective Measure Order (ICMO) on October 16, 2003, which required Marina Point to complete specific remedial actions by December 1, 2003. That deadline was extended to December 24, 2003, because of unforeseen difficulties, such as a forest fire in the area.

In the meantime, the Center had sent a number of notices of intent to commence a citizen's action against Marina Point.4 The Center then filed this action on April 7, 2004.

The district court denied Marina Point's motion to dismiss for lack of subject matter jurisdiction. The case then proceeded to trial, and on June 12, 2006, the district court issued an opinion5 in which it determined that Marina Point had violated the CWA and the ESA. Its ensuing judgment on August 21, 2006, permanently enjoined Marina Point from any development on the site without the court's prior authorization, directed Marina Point to follow any remedial orders from the Corps, and imposed a statutory penalty upon it. Marina Point appealed on August 22, 2006.

Thereafter, the district court awarded attorney fees to the Center as the prevailing party under the CWA and the ESA. Marina Point appealed that ruling on February 15, 2007.

Still later, on November 7, 2007, the district court determined that Marina Point was in contempt and issued various orders as a result. Marina Point appealed that decision on November 19, 2007.

STANDARD OF REVIEW

We review issues of the district court's subject matter jurisdiction de novo. See Satey v. JPMorgan Chase & Co., 521 F.3d 1087, 1090 (9th Cir.2008). We also review de novo the question of whether the Center's notice under the CWA was adequate. See Natural Res. Def. Council v. Sw. Marine, Inc., 236 F.3d 985, 995-96 (9th Cir.2000).

JURISDICTION

At the outset, we must consider whether there was federal jurisdiction over this dispute when the complaint was filed, and whether jurisdiction still remains. For the reasons discussed below, the answer is no.

I. Clean Water Act.

In general, actions can be brought by private persons and entities for the purpose of enforcing many of the provisions of the CWA. See 33 U.S.C. § 1365(a). That is usually referred to as the citizen suit provision. However, before an action is commenced, the citizen must give a 60-day notice of intent to sue. Id. § 1365(b)(1)(A). In fact, absent that notice, the action is prohibited. Id.

The...

To continue reading

Request your trial
82 cases
  • Sierra Club v. Portland General Elec. Co.
    • United States
    • U.S. District Court — District of Oregon
    • September 30, 2009
    ..."The giving of a sixty-day notice is not simply a desideratum; it is a jurisdictional requirement." Ctr. for Biological Diversity v. Marina Point Dev. Co., 566 F.3d 794, 800 (9th Cir.2009) (citations omitted). The purpose of the CAA's notice requirement "is not to prove violations, it is to......
  • Missud v. Oakland Coliseum Joint Venture
    • United States
    • U.S. District Court — Northern District of California
    • March 5, 2013
    ...33 U.S.C. § 1365(b)). Compliance with the notice requirement is a jurisdictional necessity. Center for Biological Diversity v. Marina Point Dev. Co., 566 F.3d 794, 800 (9th Cir. 2008) (citing Waterkeepers N. Cal. v. AG Indus. Mfg., Inc., 375 F.3d 913, 916 (9th Cir. 2004)). ii. Article III S......
  • Missud v. Oakland Coliseum Joint Venture
    • United States
    • U.S. District Court — Northern District of California
    • June 27, 2013
    ...33 U.S.C. § 1365(b)). Compliance with the notice requirement is a jurisdictional necessity. Center for Biological Diversity v. Marina Point Dev. Co., 566 F.3d 794, 800 (9th Cir. 2008) (citing Waterkeepers N. Cal. v. AG Indus. Mfg., Inc., 375 F.3d 913, 916 (9th Cir. 2004)).b. Application to ......
  • Puget Soundkeeper Alliance v. Cruise Terminals of Am., LLC, CASE NO. C14-0476 JCC
    • United States
    • U.S. District Court — Western District of Washington
    • November 20, 2015
    ...a "guessing game" as to what they allegedly did wrong, which the Ninth Circuit has frowned upon. Ctr. For Biological Diversity v. Marina Point Dev. Co. , 566 F.3d 794, 801 (9th Cir.2009). But Defendants needed to do no such thing. They were informed of the allegedly violating activities: eq......
  • Request a trial to view additional results
2 books & journal articles
  • Delineating deference to agency science: doctrine or political ideology?
    • United States
    • Environmental Law Vol. 40 No. 3, June 2010
    • June 22, 2010
    ...(holding that EPA's regulations were ultra vires under APA [section] 706(2)(C)); Ctr. for Biological Diversity v. Marina Point Dev. Co., 566 F.3d 794 (9th Cir. 2009) (notice of intent to sue under CWA); El Comite Para El Bienestar de Earlimart v. Warmerdam, 539 F.3d 1062 (9th Cir. 2008) (la......
  • Case summaries.
    • United States
    • Environmental Law Vol. 44 No. 3, June 2014
    • June 22, 2014
    ...Baykeeper, Inc. v. Tosco Corp., 309 F.3d 1153, 1155 (9th Cir. 2002). (24) See Ctr. for Biological Diversity v. Marina Point Dev. Co., 566 F.3d 794, 800-01 (9th Cir. 2009) (describing the important role that a plaintiffs citizen suit notice letter (25) Miller v. Yokohama Tire Corp., 358 F.3d......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT