Central Maine Power Co., In re

Decision Date03 April 1956
Citation122 A.2d 541,152 Me. 32
Parties, 14 P.U.R.3d 418 In re CENTRAL MAINE POWER CO. In re MAINE CONSOLIDATED POWER COMPANY.
CourtMaine Supreme Court

Everett H. Maxcy, Augusta, for plaintiff.

Locke, Campbell, Reid & Hebert, Augusta, for defendant.

Before FELLOWS, C. J., and WILLIAMSON, WEBBER, BELIVEAU, TAPLEY and MURRAY, JJ.

WILLIAMSON, Justice.

This case is before us on exceptions by the respondent Maine Consolidated Power Company to a decree of the Public Utilities Commission establishing an increase in the rate for electric energy supplied by the petitioner Central Maine Power Company. R.S. c. 44, § 67. On complaint of the petitioner, the Commission found the rate then in effect under a contract between the petitioner and the respondent, both public utilities, was 'unjust, unreasonable and unjustly discriminatory', and granted a proposed increase. R.S. c. 44, §§ 55, 62.

The three grounds of the exceptions are: (1) that the decree is not supported by substantial evidence; (2) that the Commission did not make specific findings of fact on which to base its decision, although so requested by the respondent; (3) that the Commission erred in finding that the so-called 1948 amendment to the contract between the utilities was valid.

We turn to the second exception relating to findings by the Commission. Under Section 67 'Questions of law may be raised by alleging exceptions to the ruling of the commission on an agreed statement of facts or on facts found by the commission * * *.' Our Court has said that, 'it is clearly the duty of the Commission under the statute, at least if requested by any of the interested parties, to set forth in its orders and decrees the facts on which its order is based, otherwise the remedy provided by the statute for any erroneous rulings of the law may be rendered futile.' Hamilton v. Caribou Water, Light & Power Co., 121 Me. 422, 425, 117 A. 582, 583; Application of Casco Castle Co., 141 Me. 222, 42 A.2d 43.

The analogy with the statutory requirement in equity is close. 'Upon request of either party, the justice hearing the cause shall give separate findings of law and fact.' R.S. c. 107, § 26. Sacre v. Sacre, 143 Me. 80, 55 A.2d 592, 173 A.L.R. 1261; Woodsum v. Portland R. Co., 144 Me. 74, 89, 65 A.2d 17. See also Rule 52(a), Federal Rules of Procedure, 28 U.S.C.A.; Kweskin v. Finkelstein, 7 Cir., 1955, 223 F.2d 677.

The test is whether there has been a fair compliance with the statute. See Public Service Comm. of Wisconsin v. Wisconsin Tel. Co., 289 U.S. 67, 53 S.Ct. 514, 77 L.Ed. 1036. The Commission in its decree stated the basic facts briefly to be sure, but nevertheless adequately within the spirit of the rule. The pertinent facts agreed upon by the parties and found by the Commission are: The contract between the utilities with amendments and 'decrees of the Commission in F.C. No. 1410, infra, under which the petitioner was authorized to increase its rates, tolls and charges for electric energy by an aggregate amount of $2,520,000' were introduced in evidence. No question about such facts, apart from the validity of the so-called 1948 amendment, is raised by the respondent. We quote the following findings from the decree:

'The additional revenue provided by Supplemental Decree No. 4 in F.C. No. 1410 falls short of the additional revenue of $1,100,000 allowed and provided by the facts approved in Supplemental Decree No. 3, by $18,208, the amount of additional revenue designed to be produced by the said Class V-2 Rate. (the rate under discussion)

* * *

* * *

'It is acknowledged that recently the petitioner was granted a general rate increase of about 10% by decree of this Commission. Central Maine Power Co. v. Public Utilities Commission, F.C. No. 1410, Supplemental Decrees No. 3 and No. 4. See also same case in 150 Me. 257, 109 A.2d 512. The record herein, including the records and decrees in F.C. No. 1410, show that the petitioner is entitled to an overall increased return which must be paid for by its consumers. The portion of that increase which will affect this customer is about $18,000. If that amount is not allowed the petitioner at all, its rates will be insufficient to give it a fair and reasonable total return and will adversely affect the general public if the petitioner is thereby unable to render proper service. On the other hand, if this amount is allowed the petitioner and yet absorbed by other customers, they in turn will be paying unjust, unreasonable and discriminatory rates. The Commission finds it to be in the public interest that the general rate increase by divided among all customers of the petitioner, including the respondent, approximately equally.'

In substance the present controversy is part of the Central Maine Power Company general rate case known as F.C. No. 1410. There is no reason for us to blind ourselves to the understanding by all concerned that the issues about the V-2 rate should be separated from the general rate case for later disposition.

Neither party requested or expected the Commission to value again the properties of the Central Maine Power Company or to determine again the need for additional income or the amount thereof, or to review again in any manner the conclusions reached in F.C. No. 1410. This is not a rehearing of a general rate case involving the petitioner's entire system.

The point of the second exception lies not in the sufficiency of the evidence, but in the sufficiency of the findings in the decree to form an adequate basis for review on exceptions. No precise limitations on the rule of 'fair compliance' can be stated. Much depends upon the issues and the accepted background of each case. A statement of the facts on which the petitioner's general rate increase was based in F.C. No. 1410 would have served no useful purpose. The increase was a fact accepted and unquestioned by the respondent. From the decree we know what the Commission found and the factual basis for its decision. There is no necessity in our view that the decree be vacated and the cause remanded for findings of fact and entry of a new decree.

The first exception directly raises the issue of whether the present rate is unjust, unreasonable, insufficient or unjustly discriminatory. The facts may be briefly restated: At the close of F.C. No. 1410 with an increase of about 10% in rates the petitioner lacked $18,000 of authorized income. This amount is obtainable by a like increase in the rate to be paid by the respondent.

It is clearly the law that utility rates established by contract as here may be set aside by the Commission when the rates are no longer fair. Such rates are presumed to be reasonable and just until otherwise determined. In re Guilford Water Co., 118 Me. 367, 108 A. 446; In re Searsport Water Co. (In re Lincoln Water Co.), 118 Me. 382, 108 A. 452. The burden is upon the petitioner to establish before the Commission the need for revision of the rates. On review, however, we do not reach the question of burden of proof. The findings of fact by the Commission must stand if supported by any...

To continue reading

Request your trial
6 cases
  • Casco Bay Lines v. Public Utilities Commission
    • United States
    • Maine Supreme Court
    • August 8, 1978
    ...§ 307; Central Maine Power Co. v. Public Utilities Commission, 156 Me. 295, 299, 163 A.2d 762, 765 (1960); In re Central Maine Power Co. 152 Me. 32, 36, 122 A.2d 541, 543 (1956); Central Maine Power Co. v. Public Utilities Commission, 150 Me. 257, 266-67, 109 A.2d 512, 516 (1954). We emphas......
  • City of Bangor v. Public Utilities Commission
    • United States
    • Maine Supreme Court
    • November 22, 1960
    ...service has been a most perplexing one. Obviously, a correct mathematical result cannot be attained. In Central Maine Power Company (Re Contract Rate), 152 Me. 32, 37, 122 A.2d 541, 544, the Court 'When there is a general rate increase, and from such an increase the parties cannot here esca......
  • Central Maine Power Co. v. Public Utilities Commission
    • United States
    • Maine Supreme Court
    • May 30, 1980
    ...New England Telephone & Telegraph Company v. Public Utilities Commission, Me., 390 A.2d 8, 57 (1978); In re Central Maine Power Company, 152 Me. 32, 36, 122 A.2d 541, 543 (1956); Everett T. Chapman, Re : Petition to Amend, 151 Me. 68, 70, 116 A.2d 130, 131-132 Second, insofar as the Commiss......
  • Richer, Application of
    • United States
    • Maine Supreme Court
    • June 22, 1960
    ...Company, 121 Me. 422, 425, 117 A. 582, 583. See also Casco Castle Co., Petitioner, 141 Me. 222, 42 A.2d 43; In re Central Maine Power Co. (Re Contract Rate), 152 Me. 32, 122 A.2d 541. The remaining five items are the findings required by statute as the basis for granting a permit. The quest......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT