Certified Mechanical Contractors, Inc. v. Wight & Co., Inc.

Decision Date30 October 1987
Docket NumberNo. 2-87-0032,2-87-0032
Citation162 Ill.App.3d 391,113 Ill.Dec. 888,515 N.E.2d 1047
Parties, 113 Ill.Dec. 888 CERTIFIED MECHANICAL CONTRACTORS, INC., Plaintiff-Appellant, v. WIGHT & COMPANY, INC., Defendant-Appellee.
CourtUnited States Appellate Court of Illinois

Burton A. Brown, and Wayne G. Nelson (argued), Law Offices of Burton A. Brown, P.C., Chicago, for Certified Mechanical Contractors, Inc.

Jay H. Tressler, and Francis A. Spina (argued), Tressler, Soderstrom, Maloney & Priess, Wheaton, for Wight & Co., Inc.

Justice UNVERZAGT delivered the opinion of the court:

Plaintiff, Certified Mechanical Contractors, Inc. (CMC), appeals from the judgment of the circuit court of Du Page County granting summary judgment to defendant, Wight & Co. (Wight), on count II of CMC's three-count complaint. Count I for libel arising from the preparation of an architectural report by Wight was dismissed, and Wight's motion for summary judgment on count III for libel arising out of the publication of a newspaper article was granted subsequent to the judgment entered here. CMC and Wight were engaged as general contractor and architect, respectively, by the Roman Catholic Diocese of Joliet (Diocese) for construction of a new parish center at St. Michael's Church in Wheaton, Illinois.

The essence of CMC's complaint in count II against Wight for intentional interference with contractual relations is that Wight, knowing of CMC's contract with the Diocese, wrongfully, maliciously and in bad faith interfered with that contract by causing the Diocese to order CMC to cease its operations on the project in order to allow tests to be conducted by Wight on the work performed by CMC. The results of the tests were reduced to a written report which outlined perceived construction problems in eight separate areas relating to the poured-in-place concrete work and was inherently critical of CMC's job performance. The initial cessation of work on November 9, 1983, was to last 10 days; CMC's work on the project did not resume until April 1984. CMC claimed damages as a result of Wight's alleged wrongful conduct.

Wight's first motion for summary judgment on count II was denied. Its renewed motion for summary judgment was granted, the court's opinion being that there had been no breach of the contract (i.e., CMC resumed its work on the project) and, therefore, one of the necessary elements of CMC's case was missing. Later, denying CMC's motion for reconsideration, the court opined that although CMC's contention that the delay of the construction contract may well have constituted a breach of the contract, it was the court's further opinion that Wight had a conditional privilege to advise the Diocese concerning the quality of the construction. The court stated it found no evidence, only speculation, which would support CMC's claim of malicious intent on Wight's part. The court subsequently also denied CMC's motions to make its judgment immediately appealable (107 Ill.2d R. 304(a)) or for leave to amend count II. CMC brought the instant appeal after summary judgment was granted in Wight's favor on the remaining count III.

CMC contends the court erred in granting summary judgment on its intentional interference with contractual relations count because the record before the court raised the reasonable inference that Wight desired to injure it for reasons unrelated to and independent of its desire to properly advise the Diocese. CMC further contends it should have been allowed to amend count II. We affirm.

Initially, we address two motions filed by Wight and ordered to be taken with the case. In the first, Wight asks we dismiss CMC's appeal from the January 29, 1985, and December 16, 1986, orders of the trial court which, respectively, dismissed count I and granted summary judgment on count III. CMC filed neither an objection nor a reply to this motion and, in fact, concedes in its brief that the court's judgments as to counts I and III "are not being appealed." Accordingly, CMC's appeal from the court's judgments noted above is dismissed.

In its second motion, Wight asks we strike certain portions of CMC's "Statement of Facts" as violative of Supreme Court Rule 341(e)(6). (107 Ill.2d R. 342(e)(6).) Insofar as that rule provides the facts necessary to an understanding of the case are to be "stated accurately and fairly without argument or comment," Wight finds CMC's "facts" are inaccurate recitations of the facts or are set forth in an improper editorial form containing conclusions or argument. The four statements of "facts" Wight objects to are statements of opinion of CMC's president, Timothy Carlin. The statements were included in excerpts of his deposition attached to CMC's response to Wight's renewed motion for summary judgment, to wit: that it was apparent the project was going to be delayed due to Wight's "errors and omissions"; that the architect would be liable for additional costs if the project was delayed; that, therefore, Wight tried to convince the Diocese to remove CMC as general contractor; and that the report issued by Wight "contained gross misrepresentations and inaccuracies making [CMC] appear incompetent." Wight also objects to CMC's reference to the pleadings in a separate suit filed by the Diocese against Wight and CMC.

CMC filed no objections to Wight's motion, but argues in its reply brief that Wight "[i]n essence * * * again is seeking to exclude evidence "which it had objected to in the trial court, but on which objection the trial court had not ruled." CMC contends Wight's failure to secure a ruling on its objection waives it, citing Feldscher v. E & B, Inc. (1983), 95 Ill.2d 360, 69 Ill.Dec. 644, 447 N.E.2d 1331. CMC further contends this court should disregard Wight's attack on the credibility of Carlin's affidavit by reference to certain deposition testimony of Carlin which was presented to the court in connection with the court's subsequent consideration of count III, but which was not available to the court during consideration of count II which is at issue here. In those deposition excerpts noted by Wight, Carlin admits, in essence, the factual accuracy of Wight's report as to the condition of the work on the project, i.e., that there was remedial work required on the concrete; that there were bowed forms and a crooked wall; that a keyway was omitted in a foundation wall; that reinforcing steel in many areas of the building was not in the proper place after concrete was poured; that there was more than one cold joint, one of which caused a weakening of the wall.

We agree with Wight that the complained-of excerpts from CMC's "Statement of Facts" must be stricken. The excerpts clearly are improperly set forth as facts, and, since they comprise a significant portion of CMC's 1 1/2 page "Statement of Facts," this court's ability to review the case has been hindered. (Cf. James v. Yasunaga (1987), 157 Ill.App.3d 450, 109 Ill.Dec. 663, 510 N.E.2d 531 (court denied appellee's motion to strike appellant's statement of facts where the brief included proper record references, set forth other fairly innocuous representations of fact and violations were not so flagrant as to hinder or preclude review).) CMC clearly made no effort to provide this court with a fair statement of the facts, and we will not abide such blatantly derisive treatment. Cf. Midland Hotel Corp. v. Reuben H. Donnelley Corp. (1986), 149 Ill.App.3d 53, 57-58, 103 Ill.Dec. 742, 501 N.E.2d 1280, appeal allowed (1987), 113 Ill.2d 576, 106 Ill.Dec. 49, 505 N.E.2d 355 (where, despite "a more argumentative statement of facts" than could be imagined, the court declined to grant the appellee's motion to strike appellant's statement of facts although it recognized that "at some point" sanctions would have to be imposed to prevent Supreme Court Rule 341(e)(6) from becoming a "pretend-rule").

CMC's contention Wight waived its objection to the statement is without merit. CMC does not provide record references for the "certain evidence" to which Wight allegedly objected at trial, nor does it state what that "certain evidence" was. As far as we can determine from the record, there is no identity between the deposition excerpts sought to be stricken here and the evidence Wight sought to have stricken in the trial court. Wight filed a written motion in the trial court on January 3, 1986, to strike as conclusions of law paragraphs 7 through 10 of Carlin's affidavit, which was filed in support of CMC's motion for reconsideration. In those paragraphs, Carlin averred the work stoppage violated various provisions of the contract between itself and the Diocese and caused damages. On January 21, 1986, Wight filed a second written motion to strike those same paragraphs 7 through 10 and paragraph 11, as well as exhibits I through Q, all purporting to support CMC's averrment as to the damages it sustained by reason of Wight's conduct. Accordingly, the trial court could not have ruled on the matter sought to be stricken here, since it has just now been presented to this court.

As to the credibility of Carlin's affidavit in light of matters subsequently presented to the trial court in connection with count III, the scope of this court's consideration of the trial court's judgment is limited to the matters considered by the trial court in determining the motion for summary judgment. (See In re Johnson (1985), 134 Ill.App.3d 365, 376, 89 Ill.Dec. 335, 480 N.E.2d 520 (what might have subsequently occurred, following hearing resulting in order from which appeal was taken, was not before the court on review).) Further, CMC's reference to the complaint filed by the Diocese against CMC is stricken. The complaint filed by the Diocese was appended to CMC's motion to reconsider and was alleged therein to be "new and significant evidence corroborating [its] allegations that the Diocese breached its contract with [CMC] although the contract was not terminated." The unproven allegations set...

To continue reading

Request your trial
41 cases
  • Christianson v. Colt Industries
    • United States
    • U.S. District Court — Central District of Illinois
    • March 28, 1991
    ...Torts sec. 767 91979); W. Prosser, Torts sec. 129, at 936-37 (4th ed. 1971). Certified Mechanical Contractors v. Wight & Co., 113 Ill.Dec. 888, 894, 515 N.E.2d 1047, 1053, 162 Ill.App.3d 391 (2nd Dist.Ill.1987). This Court has no doubt that the law recognizes that the protection of a defend......
  • Vickers v. Abbott Laboratories
    • United States
    • United States Appellate Court of Illinois
    • September 30, 1999
    ...Supply Co., 227 Ill.App.3d 414, 421, 169 Ill.Dec. 521, 592 N.E.2d 8 (1991), citing Certified Mechanical Contractors, Inc. v. Wight & Co., 162 Ill.App.3d 391, 113 Ill.Dec. 888, 515 N.E.2d 1047 (1987). While a plaintiff need not prove its entire case at the summary judgment stage of proceedin......
  • Langer v. Becker
    • United States
    • United States Appellate Court of Illinois
    • November 2, 1988
    ...admissions and affidavits on file, summary judgment for the defendant is proper. (Certified Mechanical Contractors, Inc. v. Wight & Co. (1987), 162 Ill.App.3d 391, 399, 113 Ill.Dec. 888, 515 N.E.2d 1047; Lindenmier v. City of Rockford (1987), 156 Ill.App.3d 76, 85, 108 Ill.Dec. 624, 508 N.E......
  • Cress v. Recreation Services, Inc.
    • United States
    • United States Appellate Court of Illinois
    • July 7, 2003
    ...court case. See HPI, 131 Ill.2d at 159,137 Ill.Dec. 19,545 N.E.2d 672, citing Certified Mechanical Contractors, Inc. v. Wight & Co., 162 Ill.App.3d 391, 401, 113 Ill.Dec. 888, 515 N.E.2d 1047 (1987) ("If an architect induces a breach of contract, not to further its principal's best interest......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT