Chaco Energy Co. v. Thercol Energy Co.

Decision Date01 December 1981
Docket NumberNo. 13489,13489
Citation637 P.2d 558,97 N.M. 127,1981 NMSC 127
PartiesCHACO ENERGY COMPANY, Applicant-Appellant, v. THERCOL ENERGY CO., Respondent-Appellee.
CourtNew Mexico Supreme Court
OPINION

FRANK H. ALLEN, Jr., District Judge.

An application was filed in the Bernalillo County District Court by the appellant, Chaco Energy Company (Chaco), to confirm an arbitration decision and to vacate an amendment to the decision. By cross-application the appellee, Thercol Energy Company (Thercol), sought to confirm both the arbitration decision and its amendment. The trial court entered a judgment confirming the decision and the amendment. Chaco appeals. We reverse.

Chaco and Thercol entered into a Joint Development and Operating Agreement dated January 26, 1977, wherein Chaco was to receive a one-third interest in certain state and federal coal leases covering property in McKinley County, New Mexico, for mining the coal properties. The agreement specified that Chaco would commence mining the coal properties by January 1, 1980, absent of a force majeure event or events. The agreement also provided that Chaco must begin making minimum distribution payments of $200,000 per month to Thercol starting January 1, 1980, unless Chaco was prevented from taking the coal by a force majeure event or events.

On October 16, 1979, and again on December 31, 1979, Chaco gave notice to Thercol that it would not begin mining on January 1, 1980, nor make the minimum distribution payments to Thercol because of the following five force majeure events:

1. Lease Assignment. The assignment of one-third of Thercol's interest in the coal properties to Chaco had not been approved by the United States Bureau of Land Management. Chaco had paid $31,000,000 for this ownership interest and Chaco claimed that it could not mine coal when it was not an approved owner of the property.

2. Water Rights. Chaco lacked sufficient water rights for a mining operation.

3. Permitting. The United States Department of Interior and the State of New Mexico had not issued the required surface mining permit to Chaco.

4. Surface Rights. The Navajo Tribe owned portions of the surface over the coal and had not consented to Chaco's proposed surface mining operations.

5. Transportation. The only feasible method of transporting coal from the proposed mine was by railroad and the Santa Fe Railroad Company had not completed its line to the mine site.

Thercol denied that the claimed events satisfied the force majeure section of the agreement and demanded arbitration. Each party appointed an arbitrator and a neutral arbitrator was appointed by the United States District Court for the District of New Mexico. The arbitration clause of the agreement provided that the written decision of the arbitrators was to be delivered to the parties thirty days after selection of the last arbitrator, this date being June 12, 1980. The written decision provided that Permitting and Surface Rights were events which satisfies the force majeure clause, and Lease Agreement and Water Rights did not. The final event, Transportation, was not decided since it was premature. On June 10, the arbitrators telephoned the respective counsel and orally reported the decision. The arbitrators, after signing the decision, dispersed. Copies of the written decision were mailed to counsel for the parties by express mail on the afternoon of June 10, 1980. Chaco's lawyers received a signed copy of the June 10 decision on June 11. Thercol's lawyers received an unsigned copy on June 11, and a signed copy on June 12.

The day after the June 10 decision, the neutral arbitrator felt he had erred with respect to a portion of his earlier decision, and placed a conference call to the arbitrators to discuss the matter. Without re-opening the proceedings for additional evidence or argument, the neutral arbitrator and Thercol's arbitrator prepared an amended decision which held that the events of force majeure for Permitting and Surface Rights would expire March 1, 1981. Chaco's arbitrator refused to participate in the decision. Copies of the amended decision, dated June 11, 1980, were hand-delivered to the parties on June 12, 1980.

After a hearing on the merits the trial court confirmed both the June 10 decision and the June 11 amended decision. The district court concluded that the June 10 decision was incomplete because the arbitrators failed to decide an issue specifically submitted to them, to-wit: the duration of the force majeure events of Permitting and Surface Rights. Since the arbitrators had not completed their task on June 10, the June 10 decision did not render the arbitrators functus officio when they made their June 11 amended decision. The district court further concluded that since the arbitrators had until June 12 to complete their work, the arbitrators retained authority to change the decision until that date. And, finally, the district court concluded that even if the June 10 decision was complete, it could be amended at any time before delivery because delivery is a necessary prerequisite to making a final award. Such delivery did not occur until June 12 when signed copies of the June 10 decision and the June 11 amended decision were delivered to both parties pursuant to Section 44-7-8(A), N.M.S.A.1978.

The Joint Development and Operating Agreement entered into by the parties provides that arbitration proceedings shall be carried out in accordance with the provisions of the New Mexico Uniform Arbitration Act. In New Mexico, arbitration proceedings and awards are governed both by common law and by the New Mexico Uniform Arbitration Act, N.M.S.A. §§ 44-7-1 through 44-7-22, N.M.S.A.1978. Robinson v. Navajo Freight Lines, Inc., 70 N.M. 215, 372 P.2d 801 (1962). The provisions of the Act govern where the Act conflicts with common law. Andrews v. Stearns-Roger, Inc., 93 N.M. 527, 602 P.2d 624 (1979).

Although the trial court found that the June 10 decision was incomplete because the arbitrators failed to decide an issue submitted to them, the June 10 decision was considered by the arbitrators as a final arbitration decision. The neutral arbitrator testified that the June 10 decision was not a draft or temporary decision, it was complete in all aspects, and no further deliberations were to take place.

The June 11 decision is referred to as an "amended" decision and the last sentence provides "(e)xcept as herein modified my decision of June 10, 1980, remains in effect." (emphasis added.) The June 10 decision addressed the questions of setting a termination date for the force majeure events when the neutral arbitrator recited: "(N)ot having any control over the Federal Government, I feel fixing a definite date cannot be justified." The June 11 decision changed this finding...

To continue reading

Request your trial
2 cases
  • Hollister Inc. v. Abbott Laboratories
    • United States
    • United States Appellate Court of Illinois
    • 18 Mayo 1988
    ...cites as authority the cases of Lewis v. County of Suffolk (1979), 70 A.D.2d 107, 419 N.Y.S.2d 680 and Chaco Energy Co. v. Thercol Energy Co. (1981), 97 N.M. 127, 637 P.2d 558. In Lewis, the dispute involved certain increases of salary to be paid by the County of Suffolk to its employees. T......
  • Applehans v. Farmers Ins. Exchange
    • United States
    • Colorado Court of Appeals
    • 13 Marzo 2003
    ...power to modify the award except where the controlling statute or the parties authorize modification); Chaco Energy Co. v. Thercol Energy Co., 97 N.M. 127, 637 P.2d 558 (1981)(an arbitration award that is amended for purposes other than those enumerated by the statute is void and of no Here......
2 books & journal articles
  • CHAPTER 10 PITFALLS AND PRATFALLS—DIAGNOSING CONTRACT CLAUSES WHICH ARE LITIGATION TRAPS
    • United States
    • FNREL - Special Institute Resolution and Avoidance of Disputes (FNREL)
    • Invalid date
    ...arbitration clause clearly worded? Second, is the proposed arbitration procedure workable? See Chaco Energy Company v. Thercol Energy Co., 97 N.M. 127; 637 P.2d 558 (N.M., 1981) for a case involving an attempt by arbitrators to amend an arbitration decision after the final decision was issu......
  • A Three-year Survey of Colorado Appellate Decisions on Arbitration-part Ii
    • United States
    • Colorado Bar Association Colorado Lawyer No. 34-3, March 2005
    • Invalid date
    ...598, citing Conn. Valley Sanitary Waste Disposal, Inc. v. Zielinski, 763 NE.2d 1080 (Mass. 2002); Chaco Energy Co. v. Thercol Energy Co., 637 P.2d 558 (N.M. 39. Applehans, supra, note 25 at 598. 40. Id. at 599. The court addressed other issues mainly unique to UM/UIM arbitrations, see id, b......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT