Charles A. Burton, Inc. v. Durkee
| Court | Ohio Supreme Court |
| Writing for the Court | MATTHIAS; WEYGANDT |
| Citation | Charles A. Burton, Inc. v. Durkee, 158 Ohio St. 313, 109 N.E.2d 265, 49 O.O. 174 (Ohio 1952) |
| Decision Date | 03 December 1952 |
| Docket Number | No. 32972,32972 |
| Parties | , 49 O.O. 174 CHARLES A. BURTON, Inc. v. DURKEE et al. |
Syllabus by the Court.
1. The parol evidence rule is a rule of substantive law which, when applicable, defines the limits of a contract.
2. Where parties, following negotiations, make mutual promises which thereafter are integrated into an unambiguous written contract, duly signed by them, the parol evidence rule excludes from consideration evidence as to other oral promises resulting from such negotiations.
This cause originated in the Court of Common Pleas of Cuyahoga County as an action for the foreclosure of a mechanic's lien.
The plaintiff, Charles A. Burton, Inc., is a corporation organized under the laws of Ohio with its principal place of business in Cleveland.
The defendants are husband and wife and owners of the premises subject to the lien.
The case was tried on the petition, amended answer and cross-petition, and reply.
The petition alleges that on or about September 23, 1948, the plaintiff and the defendant Harvey B. Durkee entered into a contract, partly oral and partly written, under the terms of which plaintiff, a general contractor, agreed to furnish all labor, materials and services requisite to construct, according to plans prepared by another, a residence with garage on premises of the defendants located in Lyndhurst, Ohio. However, it is alleged that the furnishing and installing of heating, wiring and kitchen equipment specifically were excepted from the contract, and the plans were to be modified by omitting the finishing of the second floor, the plastering of the garage, the laying of a stone floor on the back porch and the stone veneering of the front of the garage.
Plaintiff alleges that under the contract the cost of said construction was to include the cost of all materials, labor, permits, taxes and insurance furnished, supplied or incurred in connection therewith and all other costs and expenses directly incident to said work, together with a fixed fee of $2,700 to the plaintiff and compensation at a rate of $2.625 per hour for the time of Charles A. Burton, president of the plaintiff corporation, 'spent on matters pertaining to said job, either in the office or in the field.'
Plaintiff alleges that it promptly entered into performance of the contract, ordering on its own account and credit and causing to be delivered to the premises above referred to all necessary materials for the construction of the building; that it assigned laborers, carpenters and other building mechanics carried on its own payroll to fabricate such building; that it sublet on its own account and credit such portions of the work as could not be done directly by the plaintiff as general contractor; that it placed one of its foremen in immediate charge of the job; that the company's president devoted such of his own time thereto as was necessary; and that the plaintiff paid the weekly payroll of its laborers, mechanics and foremen and for labor and materials furnished by subcontractors, and also all other costs and expenses necessary or incidental to the construction of said building, including permits, public liability and state industrial compensation insurance premiums, contributions to the state Bureau of Unemployment Compensation, social security, federal income taxes and its own office overhead, for which overhead, however, no charge was made to the defendants.
Plaintiff alleges that the defendants made frequent changes in materials, including substitutions for materials previously installed by the plaintiff, thereby adding greatly to the time consumed in the construction of the building; that in the course of the work changes in the plan and style of construction were made, which were necessitated by reason of deficiencies and defects in the drawings; and that such changes caused substantial additional cost for labor, materials and supervision.
Plaintiff avers that on December 31, 1948, it submitted to the defendants a bill for expenditures and charges for labor, materials and services in the sum of $14,802.16, which sum the defendants shortly thereafter paid; that on March 31, 1949, a second invoice was submitted for $12,899.85 on which the defendants paid the sum of $10,000, out of which payment $18 was applicable to work done on defendants' other residence; that the next invoice submitted to the defendants was under date of May 31, 1949, and was in the sum of $9,900.91; and that the last invoice was submitted July 15, 1949, in the sum of $2,053.15, no part of which has been paid, and defendants still refuse to pay the same.
Plaintiff alleges that notwithstanding the defaults in payment it continued work until June 14, 1949, at which time the residence was substantially completed, but the defendants directed the plaintiff to desist from further work, with which direction it complied; and that it performed the contract in a proper, efficient and workmanlike manner except as it was prevented therefrom by the conduct of the defendants.
Plaintiff alleges that it has expended of its own funds, or become liable for, $36,597.25 in the performance of this contract and that there is now due the plaintiff from the defendants the sum of $14,871.91; and that said last sum is not in excess of the fair and reasonable cost and value of the labor and materials furnished and services performed by the plaintiff for the benefit of the defendants, measured by the existing market and prevailing rates under the circumstances then and there appertaining.
The plaintiff prays that it may be adjudged to have a valid and subsisting mechanic's lien on the premises for the sum of $14,871.91, with interest at the rate of six per cent from June 14, 1949; that its lien be foreclosed; and that all liens on the premises be marshaled, the priorities thereof determined and the premises ordered sold as upon execution.
The defendants in their answer admit that the plaintiff and defendants entered into a contract under which plaintiff was to construct a dwelling house with garage, in accordance with the plans and specifications as modified in certain specified particulars; and that by the terms of the contract plaintiff was to furnish all labor, materials and services required to construct such residence except those required for the installation of heating, electric wiring and the kitchen equipment, all of which latter items were to be furnished by the defendants at their own expense. The defendants deny that under the contract the plaintiff was to omit the plastering of the garage, the laying of the stone floor on the back porch or the stone veneering of the front of the garage.
Paragraphs five and six of the answer are as follows:
'5. Defendants further say that it was agreed between the parties at the time said contract was entered into, as a part of said contract, that the entire cost to said defendants for the labor and materials to be furnished by plaintiff would be approximately $27,000 plus the sum of $2,700 as plaintiff's fixed fee for its overhead and profit; that such fee was computed as ten per cent of the approximate price for which the plaintiff agreed to furnish such labor and materials.
'6. Defendants further say that plaintiff represented and warranted that said construction would be done in a good and workmanlike manner, and that the cost thereof would not exceed the fair and reasonable value of the labor and materials used plus the fixed fee of $2,700, nor the fair and reasonable value of the improvements thereby made to defendant's land.'
Defendants admit further that the plaintiff proceeded with the construction of the residence, and that it furnished certain materials and labor therefor, but deny that the defendant Harvey B. Durkee interfered with the construction of the premises as alleged. Defendants admit the submission of bills, as alleged, and that payments were made thereon as claimed by the plaintiff, but deny that they directed the plaintiff to discontinue work.
The answer continues as follows:
'Defendants deny that plaintiff has done and performed all things in an efficient and workmanlike manner; deny that plaintiff has expended $36,597.25 in the performance of said contract, and deny that there is now due and owing to plaintiff from them the sum of $14,871.91, or any other sum whatsoever.'
Defendants then plead that they paid $11,570.36 for labor and materials in the completion of the house and garage; that the reasonable value of the work done by the plaintiff in finishing the second floor which was in addition to the original contract had a reasonable value of $1,800; that in giving full credit to the plaintiff, in accordance with the contract as alleged in paragraph five of the answer, the agreed price with additions was $29,888.80; and that if plaintiff's claim...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial
-
Bender v. Logan
...(1996) (citation omitted), quoting 3 Corbin, Corbin on Contracts 357, Section 573 (1960), and citing Charles A. Burton, Inc. v. Durkee, 158 Ohio St. 313, 49 O.O. 174, 109 N.E.2d 265 (1952). Thus, " ‘absent fraud, mistake or other invalidating cause, the parties' final written integration of......
-
Mark-It Place Foods, Inc. v. New Plan Excel Realty Trust, Inc., 2004 Ohio 411 (Ohio App. 1/26/2004)
...and cannot be shown by parole evidence. See TRINOVA Corp., supra at 275; Aultman Hosp. Assn., supra at 53; Charles A. Burton, Inc. V. Durkee (1952), 158 Ohio St. 313, 109 N.E.2d 265, at paragraph two of the syllabus. Thus, extrinsic evidence is admissible to ascertain intent only when the c......
-
Columbia Gas Transmission Corp. v. Ogle, C2-96-839.
...with a written contract which attempt to vary or contradict terms of the written contract. See Charles A. Burton, Inc. v. Durkee, 158 Ohio St. 313, 109 N.E.2d 265 (1952). In the December 11, 1996 Order, the Court pointed out that, as a general matter, the construction to be given a written ......
-
Expeditors Intern. of Wash. v. Crowley Amer. Tran.
...evidence rule] defines the limits of a contract. It fixes the subject matter for interpretation ...." Charles A. Burton. Inc. v. Durkee, 158 Ohio St. 313, 324, 109 N.E.2d 265 (1952) (quoting 3 WILLISTON ON CONTRACTS The parol evidence rule "prohibits a party who has entered into a written c......
-
The Bullet Point: Ohio Commercial Law Bulletin: Is my Agreement Ambiguous? Volume 4, Issue 20
...of parol evidence. Rice v. Rice, 7th Dist. Columbiana No. 2001-CO-28, 2002-Ohio- 3459, ¶ 38, citing Charles A. Burton, Inc. v. Durkee, 158 Ohio St. 313, 324, 109 N.E.2d 265 (1952). The trial court determined that a reading of paragraph 6 and rider A together created an ambiguity since multi......