Chick v. Hills, 75--1274

Decision Date22 January 1976
Docket NumberNo. 75--1274,75--1274
Citation528 F.2d 445
PartiesJames J. CHICK et al., Plaintiffs-Appellants, v. Carla A. HILLS et al., Defendants-Appellees.
CourtU.S. Court of Appeals — First Circuit

Michael D. Padnos, Boston, Mass., for appellants.

David L. Whitney, Boston, Mass., for Boston Redevelopment Authority, appellee.

Jeffrey Swope, Boston, Mass., with whom Palmer & Dodge, Boston, Mass., was on brief, for E.T.C. Development Inc., and others, appellees.

Albert F. Cullen, Jr., Boston, Mass., with whom John G. Carberry, Boston, Mass., and Nessen & Csaplar, Boston, Mass., were on brief, for Massachusetts Housing Finance Agency, appellee.

Michael A. McCord, Atty., Dept. of Justice, with whom Walter Kiechel, Jr., Acting Atty. Gen., Edmund B. Clark, and Carl Strass, Attys., Dept. of Justice, Washington, D.C., were on brief, for Carla A. Hills, etc., appellee.

Before COFFIN, Chief Judge, and McENTEE and CAMPBELL, Circuit Judges.

PER CURIAM.

This is an appeal by a group of residents of the South End of Boston from the dismissal of their suit to enjoin the financing and construction of a federally subsidized housing project in their neighborhood. They alleged that the Department of Housing and Urban Development (HUD) had failed to comply with § 102 of the National Environmental Policy Act (NEPA), 42 U.S.C. § 4332, in connection with the project. 1 In particular, the residents charged that HUD had unlawfully segmented the project from the overall development plan for the area, that the Special Environmental Clearance prepared by HUD was inadequate under HUD regulations, and that an Environmental Impact Statement (EIS) should have been prepared for the total planned development in the area. The district court found that NEPA had been satisfactorily complied with, denied the requested injunction, and dismissed the suit.

The housing project, Viviendas La Victoria I (La Victoria I) is sited in Parcel 19, a development area designated by the Boston Redevelopment Authority (BRA). In 1969, BRA tentatively designated ETC as the developer of the Parcel. ETC's overall plan calls for a high rise residence for the elderly, two rehabilitation projects (Phase I and Phase II or Casa Borinquen), and two housing projects for low and middle income families (Viviendas La Victoria I and II). As of the date of suit, two portions of the plan had been completed, Phase I rehabilitation and the high rise for the elderly. Both had been financed through federal programs.

In evaluating ETC's application for financial assistance for La Victoria I under § 236 of the National Housing Act. 12 U.S.C. § 1715z--1, HUD prepared a Special Environmental Clearance (SEC), the appropriate document under HUD regulations, HUD Handbook 1390.1, 38 Fed.Reg. 19182 (July 18, 1973), as amended, 39 Fed.Reg. 38922 (Nov. 4, 1974), for a housing project containing 100--500 units. As the SEC did not suggest that the project would create an adverse environmental impact, an EIS was not prepared.

Plaintiffs claim that the SEC evaluating La Victoria I was not the appropriate form of environmental review for this project. Invoking the principles articulated in Jones v. Lynn, 477 F.2d 885 (1st Cir. 1973), they contend that HUD should have prepared an environmental review for all of Parcel 19. Since the plans for the Parcel call for more than 500 dwelling units, an EIS should have been prepared according to the applicable regulations. Id. 2 Distinguishing Jones, the district court found that HUD had not recognized Parcel 19 as a redevelopment unit and that there was no expectation of additional HUD financing for the remaining construction on the Parcel. Accordingly, it held that HUD had not unlawfully segmented the Parcel in limiting its environmental review to La Victoria I. The issue on appeal is whether the district court's finding that La Victoria I was the relevant federal action for NEPA purposes was clearly erroneous.

Before proceeding to the merits, there is a preliminary issue of mootness. This suit was filed on April 25, 1975, but a preliminary injunction was not requested. On May 9, 1975, ETC, BRA, MHFA, and HUD closed on the financing of La Victoria I. Construction was begun. On May 29, plaintiffs moved for a preliminary injunction to restrain the defendant government agencies from dispersing any funds to ETC. By the time of argument on this appeal, approximately one million dollars had been spent on the construction of the housing project. 3

Appellees claim that this appeal should be dismissed as moot because the work on the project has progressed so far as to be irreversible. See Kelaghan v. Industrial Trust Co., 211 F.2d 134 (1st Cir. 1954). The federal action, executing contracts with the developers and the state and local government agencies, had been completed. See San Francisco Tomorro v. Romney, 472 F.2d 1021, 1025 (9th Cir. 1973). HUD retains no discretionary power to alter the plans for the project. Compare Wilson v. Lynn, 372 F.Supp. 934, 936 (D.Mass.1974). Further, relying on the contract with HUD, the other defendants have proceeded with the financing and construction of the project. An injunction would severly prejudice their interests. We note, however, that inequity barring blanket injunctive relief does not necessarily render a suit challenging the federal government's compliance with NEPA moot. See Conservation Society of Southern Vermont v. Secretary of Transportation,508 F.2d 927, 935 (2d Cir. 1974); Environmental Defense Fund, Inc. v. Froehlke, 477 F.2d 1033 (8th Cir. 1973). Since we affirm the decision of the district court on the merits, we do not decide whether we could have properly dismissed this case as moot.

The sole question on appeal is whether the district court properly found that La Victoria I was the relevant federal project for environmental review. As La Victoria I was the project for which HUD was granting financial assistance, the plaintiffs had the burden to...

To continue reading

Request your trial
8 cases
  • Sierra Club v. Babbitt, CV F 99-5219 AWI DLB.
    • United States
    • U.S. District Court — Eastern District of California
    • July 12, 1999
    ...when HUD signed the R-5 contract in 1971 and that the Coalition failed to press its claim until September 24, 1979. See Chick v. Hills, 528 F.2d 445 (1st Cir.1976); Sworob v. Harris, 451 F.Supp. 96 (E.D.Pa. 1978), aff'd. without opinion, Sworob v. Harris, 578 F.2d 1376 (3d Cir.1978), cert. ......
  • Aertsen v. Landrieu
    • United States
    • U.S. Court of Appeals — First Circuit
    • December 11, 1980
    ...was no reasonable expectation of further federal financing "as the subsidized housing program had been discontinued." Chick v. Hills, 528 F.2d 445, 448 (1st Cir. 1976). It was only after funds again became available in 1977 that the developer applied for and received funding for La Victoria......
  • Sadler v. 218 Housing Corp., Civ. A. No. 75-32A.
    • United States
    • U.S. District Court — Northern District of Georgia
    • July 26, 1976
    ...section is too narrow in scope." Citizens Against the Destruction of NAPA v. Lynn, 391 F.Supp. 1188, 1194 (N.D.Cal. 1975); Chick v. Hills, 528 F.2d 445 (1st Cir. 1976); San Francisco Tomorrow v. Romney, 472 F.2d 1021 (9th Cir. Moreover, the analogy to highway construction segmentation decis......
  • Preservation Coalition, Inc. v. Pierce
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • February 12, 1982
    ...when HUD signed the R-5 contract in 1971 and that the Coalition failed to press its claim until September 24, 1979. See Chick v. Hills, 528 F.2d 445 (1st Cir. 1976); Sworob v. Harris, 451 F.Supp. 96 (E.D.Pa.1978), aff'd without opinion, Sworob v. Harris, 578 F.2d 1376 (3d Cir. 1978), cert. ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT