Chicopee Concrete Service, Inc. v. Hart Engineering Co.

Decision Date09 October 1986
PartiesCHICOPEE CONCRETE SERVICE, INC. v. HART ENGINEERING CO.
CourtUnited States State Supreme Judicial Court of Massachusetts Supreme Court

Peter J. Gagne, Boston, for plaintiff.

Francis M. Lynch, Boston, for defendant.

Robert J. Sherer, Boston and James F. Grosso, Wellesley, for Associated Gen. Contractors of Massachusetts, Inc., amicus curiae, submitted a brief.

Before HENNESSEY, C.J., and WILKINS, NOLAN, LYNCH and O'CONNOR, JJ.

WILKINS, Justice.

The Appeals Court held that the defendant, Hart Engineering Co. (Hart), the general contractor on a public works project in Holyoke, and the plaintiff, Chicopee Concrete Service, Inc. (Chicopee), had entered into a contract concerning the supplying of concrete for the project and that Hart was liable for breach of contract when it terminated the contract after the engineering firm representing the city, as was its right, disapproved of Chicopee as a supplier of concrete. Chicopee Concrete Serv., Inc. v. Hart Eng'g Co., 20 Mass.App.Ct. 315, 479 N.E.2d 748 (1985). The Appeals Court thus reversed the summary judgment for Hart entered in the Superior Court, ordered entry of summary judgment for Chicopee on liability, and remanded the case for the determination of damages. Id. at 321, 479 N.E.2d 748.

We granted Hart's application for further appellate review, concerned principally with Hart's arguments that (1) the Appeals Court opinion declared that the terms of a general contract could not become part of a subcontract unless those terms were unambiguously restated in the subcontract and (2) the Appeals Court should not have ordered summary judgment for Chicopee on the question of liability. We agree with the Appeals Court's conclusions and shall comment only on the points that attracted our attention in the application for further appellate review.

Hart argued, successfully in the Superior Court but unsuccessfully in the Appeals Court, that its contract with Chicopee incorporated by reference the provisions of the prime contract that subcontractors had to be approved by the city's representative and that, because the city's representative disapproved of Chicopee as a supplier of concrete, the subcontract was unenforceable. The problem with Hart's argument is that the terms of the prime contract were not fully incorporated in the subcontract by the language Hart included in the purchase order it gave to Chicopee, but rather only terms relating to the work to be done were incorporated by general reference. The Appeals Court was most careful to note that the terms of a general contract could be incorporated fully in the subcontract by appropriate reference. Chicopee Concrete Serv., Inc. v. Hart Eng'g Co., supra at 320, 479 N.E.2d 748. We do not read the Appeals Court opinion as announcing a rule, as the amicus curiae argues, that a provision of a general contract will be included in a subcontract only if it is specifically referred to as a condition of the subcontract. Unless incorporation by general reference is explicitly rejected by some statute or regulation, incorporation by a clearly stated general reference will suffice. 1

The subcontract could have incorporated the general terms and conditions of the general contract by cross-reference to the relevant documents. In this case, however, the incorporation was only of those terms of the general contract that were relevant to the work to be performed by Chicopee.

Hart complains that the Appeals Court should not have ordered summary judgment for Chicopee on the issue of liability. If the Superior Court judge should have entered that judgment on the basis of the material properly before him on the parties' cross-motions for summary judgment, the Appeals Court dealing with the same record is fully warranted in directing that it be done. See 6 Moore's Federal Practice par. 56.27 (2d ed. 1985).

We see no genuine issue as to any material fact which would bar the award of summary judgment on...

To continue reading

Request your trial
16 cases
  • Greene v. Ablon
    • United States
    • U.S. Court of Appeals — First Circuit
    • July 16, 2015
    ...by some statute or regulation, incorporation by a clearly stated general reference will suffice.” Chicopee Concrete Serv., Inc. v. Hart Eng'g Co., 398 Mass. 476, 498 N.E.2d 121, 122 (1986). Accordingly, a Massachusetts employer's policies may be incorporated by reference into its employment......
  • Bulwer v. Mount Auburn Hosp.
    • United States
    • Appeals Court of Massachusetts
    • September 24, 2014
    ...standards would incorporate by reference the ACGME requirements into the residency contract. See Chicopee Concrete Serv., Inc. v. Hart Engr. Co., 398 Mass. 476, 478, 498 N.E.2d 121 (1986) (“incorporation by a clearly stated general reference will suffice”).16 Bulwer's claim in this regard r......
  • Partylite Gifts, Inc. v. MacMillan
    • United States
    • U.S. District Court — Middle District of Florida
    • September 11, 2012
    ...Microsoft Corp. v. Big Boy Distribution LLC, 589 F.Supp.2d 1308, 1319 (S.D.Fla.2008); see also Chicopee Concrete Service, Inc. v. Hart Engineering Co., 398 Mass. 476, 498 N.E.2d 121, 122 (1986) (incorporation of subcontract into contract must be clearly stated). The requirement that the con......
  • Bulwer v. Mount Auburn Hosp.
    • United States
    • United States State Supreme Judicial Court of Massachusetts Supreme Court
    • February 29, 2016
    ...national origin. This policy was incorporated by reference in the medical resident agreement. See Chicopee Concrete Serv., Inc. v. Hart Eng'g Co., 398 Mass. 476, 478, 498 N.E.2d 121 (1986) (“incorporation by a clearly stated general reference will suffice”). Whether the defendants violated ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT