Chirichella v. Erwin

Decision Date01 November 1973
Docket NumberNo. 47,47
Citation310 A.2d 555,270 Md. 178
PartiesJohn J. CHIRICHELLA et ux. v. Howard Lawson ERWIN et ux.
CourtMaryland Court of Appeals

Richard F. Rothenburg, Oxon Hill (Joseph C. V. Ferrusi, Oxon Hill, on the brief), for appellants.

George W. Shaffer, Rockville (Carr, Bonner, O'Connell, Kaplan, Thompson & Diuguid, Rockville, on the brief), for appellees.

Argued before MURPHY, C. J., and BARNES, McWILLIAMS, SINGLEY, SMITH, DIGGES and LEVINE, JJ.

LEVINE, Judge.

This appeal is from a decree for specific performance of a contract for the sale of real estate. Appellants (the Chirichellas) had contracted in June 1971 to sell their home in Silver Spring to appellees (the Erwins) for the sum of $39,200. Due to the refusal of the Chirichellas to settle, the Erwins finally sued them on August 31, 1972 for specific performance. At the conclusion of the trial, the Circuit Court for Montgomery County (Miller, J.) entered the decree from which this appeal is taken.

The contract entered into by the parties was the 'standard' form used by the Montgomery County Board of Realtors. Paragraph Six of the form contract, entitled 'Settlement,' reads as follows:

'Within _ _ days from date of acceptance hereof by the Seller, or as soon thereafter as a report of the title can be secured if promptly ordered, and/or survey, if required, and/or Government-insured loan, if used, can be processed, if promptly applied for, the Seller and Purchaser are required and agree to make full settlement in accordance with the terms hereof. . . .'

Apparently when the real estate salesman initially submitted the contract to the Chirichellas, the words, 'by Oct. 1, 1971 or sooner,' had been inserted in the blank space. By mutual agreement, this language was amended to read, 'Coincide with settlement of New Home in Kettering Approx. Oct. '71.' No other reference to the 'New Home in Kettering' appears in the contract.

The Chirichellas had contracted to purchase the 'New Home' in April 1971. Their agreement provided that they were to settle 'within fifteen (15) days from the date of completion.' Although construction of the new house had not yet commenced when the Erwin contract was executed in April, the Chirichellas were confident that it would be completed by October unless unforeseen developments intervened. Their confidence proved to be unwarranted as the first settlement of the 'New Home' was scheduled for June 15, 1972. The record does not indicate when construction actually commenced.

The June settlement on the 'New Home' never materialized because the Chirichellas claimed it was not completed 'in a workmanlike manner.' In July, their attorney wrote to the realtor handling that transaction and itemized 84 alleged defects in the house. The testimony at trial reflects a clear-cut difference of opinion in that regard between the Chirichellas and a representative of the builder. The latter maintained that the house had been satisfactorily completed and implied that the Chirichellas were being unreasonable. In any event, settlement was rescheduled for two separate dates in August, but the Chirichellas persisted in their claim that the house was not yet ready for occupancy. Settlement has never occurred on the 'New Home' and it appears that it has been resold to another purchaser.

The first settlement of the contract on the house sold by the Chirichellas to the Erwins was also scheduled for June 15, 1972. Sometime prior to that date, but after October 1971, Mr. Erwin asked Mr. Chirichella to settle, but the latter refused because the 'New Home' was not ready. The Chirichellas did not appear at the June 15 settlement, and it was rescheduled for August 9. When that proved to be futile, the Erwins filed their suit on August 31, 1972.

Although he was of the view that the Chirichellas' complaints concerning the 'New Home' were justified, the chancellor concluded that the provision for settlement inserted in the Erwin contract was not a condition precedent to performance, but merely a requirement that settlement take place during the month of October 1971, or within a reasonable time thereafter. And, since more than a reasonable time had elapsed, the Erwins were entitled to a decree for specific performance. We agree, and therefore affirm.

Before this Court, the Chirichellas attack the chancellor's ruling on the same grounds raised below: That the contested provision was a condition precedent to performance on their part, and since that condition failed, the contract failed with it. They rely almost entirely on Griffith v. Scheungrab, 219 Md. 27, 146 A.2d 864 (1958) for this contention. This reliance is completely misplaced, as there we merely held that:

'. . . Where a contractual duty is subject to a condition precedent, . . . there is no duty of performance and . . . 'a decree for specific performance will not be granted unless conditions precedent, express, implied, or constructive, have all occurred or been performed.' (citations omitted).' 219 Md. at 34-35, 146 A.2d at 868 (emphasis added).

This argument begs the question. The issue is not whether there was a failure of a condition precedent, but whether the disputed clause indeed constitutes a condition precedent. We have already indicated our agreement with the chancellor that it does...

To continue reading

Request your trial
72 cases
  • Holzman v. Fiola Blum, Inc.
    • United States
    • Court of Special Appeals of Maryland
    • April 2, 1999
    ...that settlement was a condition precedent to the Broker's contractual right to a commission. See generally Chirichella v. Erwin, 270 Md. 178, 182, 310 A.2d 555 (1973) (recognizing that the determination of what constitutes a condition precedent if a question of "construction dependent on th......
  • Canaras v. Lift Truck Services, Inc.
    • United States
    • Maryland Court of Appeals
    • August 1, 1974
    ...since it could not, under any circumstances be complied with.' 7 Judge Levine, for the Court in the recent case of Chirichella v. Erwin, 270 Md. 178, 310 A.2d 555 (1973), after defining a 'condition precedent,' stated: 'The question whether a stipulation in a contract constitutes a conditio......
  • B & P ENTERPRISES v. Overland Equipment Co.
    • United States
    • Court of Special Appeals of Maryland
    • September 5, 2000
    ...as "if" and "provided that," are commonly used to indicate that performance has expressly been made conditional. Chirichella v. Erwin, 270 Md. 178, 182, 310 A.2d 555 (1973) (citations omitted); accord Hartford Fire Ins. Co. v. Himelfarb, 355 Md. 671, 680, 736 A.2d 295 (1999); New York Bronz......
  • Adam v. Wells Fargo Bank, N.A.
    • United States
    • U.S. District Court — District of Maryland
    • August 26, 2011
    ...where contract stated that "[t]his agreement is effective and binding . . . when both parties sign it"); see also Chiricella v. Erwin, 270 Md. 178, 182, 310 A.2d 555 (1973) (describing words and phrases indicating express condition precedent). Nevertheless, HSBC maintains that the condition......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT