Chris Nelsen & Son, Inc. v. City of Monroe, 33
Decision Date | 05 October 1953 |
Docket Number | No. 33,33 |
Citation | 60 N.W.2d 182,337 Mich. 438 |
Parties | CHRIS NELSEN & SON, Inc. v. CITY OF MONROE. |
Court | Michigan Supreme Court |
Dell and Heber, Royal Oak, for appellant.
Victor H. Weipert, City Atty., William J. Weipert, Monroe, of counsel, for appellee.
Before the Entire Bench, except BOYLES, J.
Plaintiff sued defendant for cost of removal of 1,876 cubic yards of rock excavation over and above the amount claimed by plaintiff to be indicated by drawings and evidence furnished by defendant to plaintiff to procure plaintiff's bid for construction of water main. On trial before the court without a jury, the court found for the defendant and rendered judgment accordingly. Plaintiff appeals.
The contract in the obtaining of which bids were publicly requested by the city, covered the installation of a water main approximately 8 miles long, from Stony Point to the city of Monroe, much of the course being alongside of the Pointe Aux Peaux road. The city furnished plaintiff company all the data known and available to the city except that the plaintiff claims the indication of total rock excavation necessary was misinformative and faulty evidence.
Neither the pleadings nor the testimony of any witness for the plaintiff alleges any bad faith on the part of the city or its agents. The action is in assumpsit and is based solely upon the furnishing of faulty and incorrect information. The plaintiff, in the instant case, seeks only to recover that which will compensate it for the damages suffered as a direct result of the breach of the city's implied warranty of the accuracy of the data furnished.
The city made no computation of the total rock yardage to be removed, and was under no obligation to furnish any such computation; it was simply under obligation to make no false statement to plaintiff, and the claimed inaccuracy and falsity of the soundings made by the city hereinafter mentioned is the sole basis for plaintiff's claim. Plaintiff offered no proof that any one or more of the soundings shown on the diagram relied on by plaintiff in making its bid and entering into the contract, was false or incorrect, as a sounding at the very point or points indicated on the diagram.
Plaintiff's witness Korneffel (who as subcontractor did the explosive work on the job in question) testified:
'If you insist on 3, 4, and 5 feet from that particular spot as the actual sounding I have nothing in the way of evidence to show that the sounding as taken by the engineers employed by the city of Monroe where taken were incorrect.'
Mr. Goodwin, engineer employed by the city on the contract in question, was present at most of the soundings and testified as to the manner of making the topography survey and the test soundings in question, as follows:
In all 103 soundings were thus taken, all in general proximity to the proposed water main, but few if any, on the precise line of the water main, all of which was indicated on the plan and drawings seen and relied on by plaintiff's engineer before bidding.
Mr. Goodwin further testified:
Mr. Goodwin further testified on cross-examination as follows:
Mr. Goodwin further testified that the depth of rock below the surface varied in the 8 mile course of the water main, in one location 2 1/2 feet in 50 feet; in another locality, the variation was 2.8 feet in 180 feet; that in one 3,000 foot stretch there would be approximately a variance of 7 feet; in one locality a variance of 3 feet in 65 feet; that at Sandy Creek there is a variance of 3 1/2 feet over a space of 85 or 90 feet; that the soundings are indicated on the chart or map by a small blue or black dot; telephone or telegraph poles (from which distances and directions to the sounding are shown) are indicated by a circle with a line projecting out on each side; that the symbols are not drawn to a scale, you would not be able to see them on a scale of one inch to 100 feet, and that the soundings were made in January and February, 1947.
Plaintiff's engineer (in at least practical effect) for this job, Robert Nielsen, who is also plaintiff's vice president and secretary, had seen the advertisement for the letting of the contract in question about one month before the letting, August 23, 1948; but plaintiff did nothing during that month to obtain more detailed information as to rock depths along the line of the water main instead of near it. Nielsen testified it would have taken him and two men two weeks to make the same number of soundings indicated on the city's drawings. He said:
'We didn't make any test borings because we assumed the blue-prints to be correct, the cost was prohibitive, and there wasn't sufficient time before the bidding.'
The plans and specifications were sent plaintiff...
To continue reading
Request your trial-
Warner Constr. Corp. v. City of Los Angeles
...in the data. (See Wunderlich v. State of California (1967) 65 Cal.2d 777, 784--785, 56 Cal.Rptr. 473; Chris Nelsen & Son, Inc. v. City of Monroe (1953) 337 Mich. 438, 446, 60 N.W.2d 182, 423 P.2d Whether the misrepresentation of 'clay binder' for 'minute binder' was a material misrepresenta......
-
Wunderlich v. State ex rel. Department of Public Works
...to warrant to conclusion that the pit would average the median of that range, as claimed by plaintiffs. (See Chris Nelsen & Son v. City of Monroe (1953) 337 Mich. 438, 60 N.W.2d 182.) Had plaintiffs consulted the records they would have found precisely what the memorandum reported. And even......