Christensen v. Idaho Land Developers, Inc.

Decision Date08 March 1983
Docket NumberNo. 14012,14012
Citation104 Idaho 458,660 P.2d 70
PartiesHarold CHRISTENSEN d/b/a Loc Electric, Plaintiff-Respondent, v. IDAHO LAND DEVELOPERS, INC., an Idaho corporation, Defendant-Appellant, and Kelly Enterprises, Inc., an Idaho corporation, and William P. Kelly and Douglas Hanson and DeWayne Woolf, d/b/a Woolf and Hanson Concrete Contractors, Defendants.
CourtIdaho Court of Appeals

E. Don Copple, Davison, Copple, Copple & Copple, Boise, for defendant-appellant.

Charles A. Homer, Holden, Kidwell, Hahn & Crapo, Idaho Falls, for plaintiff-respondent.

BURNETT, Judge.

We are asked to decide whether a contractor who makes repairs and improvements to real property, under agreement with a tenant, is entitled to impose a laborer's and materialman's lien against the landlord's interest in the property. Upon the facts presented in this case, the district court entered summary judgment holding that the contractor was entitled to such a lien. We affirm.

The facts essential to our opinion are undisputed. The landlord, Idaho Land Developers, Inc., leased a tavern and restaurant to the tenants, William P. Kelly and Kelly Enterprises, Inc., for a period of fifteen years. The lease instrument required the tenants to "maintain the plumbing, heating, air conditioning equipment, and electrical outlets ... and all other maintenance." The lease further provided that the tenants "shall not do or permit to be done in said premises anything that would be dangerous, illegal or unlawful under the ordinances of the City of Idaho Falls...."

After approximately four months had elapsed under the lease, the landlord received a letter from the chief electrical inspector of the City of Idaho Falls. The letter, addressed to the landlord with copies to the tenants and to the city fire department, listed thirty-one "electrical violations and deficiencies" found during an inspection of the subject property. The violations and deficiencies included numerous instances of improper wiring, inadequate receptacles, missing outlet covers, and loose or open wiring. The inspector's letter advised that the corrections "must be made within fifteen days from receipt" of the letter. The landlord forwarded the letter to the tenants, who then engaged a contractor, Loc Electric, to remedy all the violations and deficiencies. The contractor performed the work as requested, but the tenants failed to pay. A claim of lien for labor and materials was filed of record against the property. When the landlord similarly failed to pay, the contractor successfully sued to foreclose the lien.

On appeal from the summary judgment, our threshold inquiry is whether the record discloses any "genuine issue of material fact." I.R.C.P. 56(c). Because the events recited above are uncontroverted, it appears that no genuine factual issue exists. We turn, then, to the next inquiry--whether, upon these facts, the contractor was entitled to judgment as a matter of law.

The contractor's claim of lien was grounded in I.C. § 45-501, which provides, in pertinent part, as follows:

Every person performing labor upon, or furnishing materials to be used in the ... alteration or repair of ... any structure has a lien ... for the work or labor done or materials furnished, whether done ... or furnished at the instance of the owner of the building ... or his agent. [Emphasis supplied.]

As a general principle, a tenant is not the "agent" of the landlord, for the purpose of § 45-501, merely by virtue of a lessor-lessee relationship. See generally Anno., 74 A.L.R.3d 330, 334-43 (1976). However, this principle has two closely related corollaries in Idaho. First, a landlord's interest in real property may be subjected to a lien, for work performed by agreement with the tenant, if the lease specifically requires the tenant to see that the work is done. E.g., Gem State Lumber Co. v. Union Grain & Elevator Co., 47 Idaho 747, 278 P. 775 (1929). Second, the landlord's interest may be subjected to a lien if he requests the work to be done. Parker v. Northwestern Investment Co., 44 Idaho 68, 255 P. 307 (1927). The latter corollary applies to any case where the landlord has done "some act in ratification of, or consent to [,] the work done and the furnishing of material and labor." Bunt v. Roberts, 76 Idaho 158, 161, 279 P.2d 629, 630 (1955).

In the present case, the district court did not distinguish between these two corollaries. However, the court held that the general requirements imposed by the lease--that the tenants "maintain" the premises, and that they refrain from any unlawful use of the premises--were rendered "specific" in their application when the landlord forwarded to the tenants the city's letter enumerating thirty-one corrections needed in the electrical system on the premises. This view of the case invokes the first corollary, that a landlord's interest is lienable if the lease specifically requires the work in question. The court also held that the landlord's act of forwarding the city's letter to the tenants represented "a ratification or a consent for the work to be done." This view would bring the case within the second corollary.

The landlord argues, in effect, that application of either corollary rests upon the district court's implicit determination that the tenants were expected to take remedial action in response to the city's letter. The landlord contends that such a determination relates to a question of fact, and is precluded by the rule that a party resisting summary judgment is entitled to have the record construed, and all reasonable...

To continue reading

Request your trial
17 cases
  • Idaho Lumber, Inc. v. Buck
    • United States
    • Court of Appeals of Idaho
    • December 3, 1985
    ...landlord, for the purpose of [I.C.] § 45-501, merely by virtue of a lessor-lessee relationship." Christensen v. Idaho Land Developers, Inc., 104 Idaho 458, 459, 660 P.2d 70, 71 (Ct.App.1983). See also Bunt v. Roberts, 76 Idaho 158, 279 P.2d 629 (1955). The burden of proving agency rests upo......
  • Scott v. Castle
    • United States
    • Court of Appeals of Idaho
    • April 26, 1983
    ...settled law to the facts. There was no showing that the trial court misapplied the law. Compare Christensen v. Idaho Land Developers, Inc., --- Idaho ---, 660 P.2d 70 (Ct.App. March 8, 1983). In our view, this appeal was brought and pursued unreasonably and without foundation. Accordingly, ......
  • Hieb v. Minnesota Farmers Union
    • United States
    • Court of Appeals of Idaho
    • November 15, 1983
    ...unreasonably or without foundation. Scott v. Castle, 104 Idaho 719, 662 P.2d 1163 (Ct.App.1983); Cf. Christensen v. Idaho Land Developers, Inc., 104 Idaho 458, 660 P.2d 70 (Ct.App.1983). Accordingly, no attorney fees on appeal will be The judgment as to Minnesota Farmers Union is reversed. ......
  • Remington v. State, 21539
    • United States
    • Court of Appeals of Idaho
    • September 7, 1995
    ...time on appeal. See Baldner v. Bennett's, Inc., 103 Idaho 458, 460, 649 P.2d 1214, 1216 (1982); Christensen v. Idaho Land Developers, Inc., 104 Idaho 458, 460, 660 P.2d 70, 72 (Ct.App.1983). Having found that Remington's application for post-conviction relief was improperly dismissed, we re......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT