Christhilf v. City of Baltimore

Decision Date26 January 1927
Docket Number87.
Citation136 A. 527,152 Md. 204
PartiesCHRISTHILF ET AL. v. MAYOR AND CITY COUNCIL OF CITY OF BALTIMORE.
CourtMaryland Court of Appeals

Appeal from Superior Court of Baltimore City.

"To be officially reported."

Action by Francis D. Christhilf and others, trading as Christhilf Ensey & Firor, against the Mayor and City Council of the City of Baltimore. Judgment on demurrer for defendant, and plaintiffs appeal. Affirmed.

Argued before BOND, C.J., and URNER, ADKINS, OFFUTT, DIGGES, and PARKE, JJ.

Raphael Walter, of Baltimore (Sykes, Nyburg, Goldman & Walter, of Baltimore, on the brief), for appellants.

Charles C. Wallace, City Sol., and John Henry Lewin, Asst. City Sol both of Baltimore (George E. Kieffner, Asst. City Sol., of Baltimore, on the brief), for appellee.

PARKE J.

The appellants entered into a contract on March 31, 1922, with the mayor and city council of Baltimore to build a public highway for a certain reward. On June 1, 1925, the appellants brought an action against the municipality for damages alleged to have been sustained by the appellants, without its fault, by delay in the performance of the contract through the failure and refusal of the municipality to exercise reasonable effort and diligence to secure the rights of way on which the work under said contract was to be done. The contract was in writing and was made a part of the declaration. The demurrer to the declaration was sustained and the appellants declined to amend and appealed from the judgment on demurrer.

The appellants constructed the highway as they agreed, so the right of way was acquired, and, since there is no charge of fraud, corruption, or bad faith on the part of the appellee the sole ground for the action is that the municipality failed and refused to exercise reasonable effort and diligence in its securing the right of way. The contractors engaged to construct the road for the contract price according to the terms of that contract, and, having completed the construction and been paid as promised, they now endeavor to recover a good bit of money beyond the agreed compensation upon the theory that the circumstances under which they had constructed the highway were, by the unreasonable inaction of the appellee, rendered materially different from those which the parties had contemplated at the inception of the contract, and, so, the loss the contractors thus sustained was not a contingency which the parties had covered by the stipulations of the contract. The soundness of this theory hinges on what is found within the four corners of the contract.

The contractors were advised by the written instrument they signed that the appellee did not then own the right of way upon which the appellants were to build the highway, but that it was the appellee's intention to acquire the roadbed before the work began. The appellee, however, did not expressly agree that it would acquire the right of way before the work began, nor within any period of time, nor with what diligence it would endeavor to secure the roadway, but both the contracting parties did take into consideration the probability of not only a delay, but also a failure in securing the necessary right of way. This is manifested by stipulations which relate to such contingencies and at once provide a certain degree of protection to the contractor and total immunity for the municipality in the event of either contingency occurring. By paragraph 36 of the specifications forming a part of the contract it is agreed that, "if the contractor is delayed or obstructed in the prosecution or completion of the work because of the failure or inability of the city to obtain title to or possession of any land or property, necessary for the prosecution or completion of the work hereunder, he shall be entitled to such an extension of time for the completion of the work...

To continue reading

Request your trial
1 cases
  • Matthews v. Kernewood, Inc.
    • United States
    • Court of Appeals of Maryland
    • January 11, 1945
    ......          Appeal. from Circuit Court of Baltimore City; William L. Henderson,. Judge. . .          Suit by. Clyde V. Matthews and ... contract for them. Cowan, Inc., v. Meyer, 125 Md. 450, 466, 94 A. 18; Christhilf v. Baltimore, 152 Md. 204, 209, 136 A. 527. One who conveys a part of a tract of. land by deed ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT