Church v. Callanan Indus.

Decision Date19 November 2002
Citation752 N.Y.S.2d 254,99 N.Y.2d 104,782 N.E.2d 50
PartiesNED S. CHURCH, an Infant, by WENDY SMITH, His Guardian ad Litem, et al., Appellants, v. CALLANAN INDUSTRIES, INC., et al., Defendants, and SAN JUAN CONSTRUCTION AND SALES COMPANY, Respondent. (And a Third-Party Action.)
CourtNew York Court of Appeals Court of Appeals

Michael J. Hutter, Albany, and Thorn Gershon Tymann and Bonanni, LLP, for appellants.

D'Agostino, Krackeler, Baynes & Maguire, P.C., Menands (Arete K. Sprio of counsel), for respondent.

William D. Fireman, P.C., New York City (William D. Fireman of counsel), for New York State Trial Lawyers Association, amicus curiae.

Nolan & Heller, LLP, Albany (Terence J. Burke and Frederick W. Clark III of counsel), for Empire State Subcontractors Association, amicus curiae.

Couch White, LLP, Albany (James J. Barriere and Stephen M. Buhr of counsel), for Associated General Contractors of America, New York State Chapter, Inc. and another, amici curiae.

Chief Judge KAYE and Judges SMITH, CIPARICK, WESLEY, ROSENBLATT and GRAFFEO concur.

OPINION OF THE COURT

LEVINE, J.

Plaintiff Ned Church, age nine, received catastrophic spinal injuries December 26, 1992, when the driver of a Volkswagen Jetta in which he was a rear seat occupant fell asleep at the wheel. The vehicle veered off the southbound traffic portion of the New York State Thruway near milepost marker 132.7, careened down a nontraversable embankment and crashed in a V-shaped ditch at the bottom. The Thruway site where the vehicle left the highway was within a 22-mile resurfacing and safety-improving project, which was completed in 1986 pursuant to an agreement between the Thruway Authority and Callanan Industries, Inc., as general contractor.

Pursuant to its contract with the Thruway Authority, Callanan agreed, by a date certain, to "construct and complete in the most substantial and workmanlike manner, the construction, improvement or reconstruction of the project" identified in the project plans and specifications. The project specifications called for the removal of some 275 feet of existing guiderail in the vicinity of milepost marker 132.7 and its replacement by a longer (312.5 feet) guiderail system. The contract documents also contemplated Callanan's use of subcontractors on the project.

In a related agreement, the Thruway Authority engaged the construction engineering firm of Clough, Harbour & Associates as project "Engineer" to inspect and supervise Callanan's compliance with the contract plans and specifications. Under the Thruway Authority's agreement with Callanan, the engineer's recommendation was required before final acceptance of the contractor's work.

Callanan entered into a subcontract with defendant San Juan Construction and Sales Company for the installation of the guiderail system in question. The subcontract incorporated the general contract by reference. It also stipulated that "[a]ll drawings, * * * certifications [and] approvals of the Subcontractor shall be submitted for approval of the Architect or Engineer," that is, "the person appointed by the Owner to supervise the work of the Contractor on behalf of the Owner." In addition, Callanan reserved the right to demand at any time that San Juan furnish evidence of its ability to fully perform the subcontract in the manner and within the time specified in the subcontract.

Suit was brought on behalf of the infant plaintiff against Callanan, San Juan and Clough Harbour. The gravamen of the action was both the negligent failure to complete the full 312.5 feet of new guiderailing called for by the Callanan general contract and the San Juan subcontract, and Clough Harbour's negligent inspection and approval of the installation despite such noncompletion. Specifically, the complaint alleged that (1) San Juan installed only some 212 of the 312.5 feet of guiderailing called for by the contracts; (2) the missing portion of the guiderail installation included the place where the Jetta went out of control and left the highway; and (3) as a result of the negligent noncompletion of the guiderail installation, the infant plaintiff incurred devastating injuries when the Jetta crashed at the bottom of the embankment.

After joinder of issue and discovery, Callanan and San Juan moved for summary judgment dismissing the complaint, based in part on the contention that, as purely contracting parties with respect to installation of the guiderailing, they owed no duty to plaintiffs. Plaintiffs' response was that both defendants undertook a duty to perform safety improvements and were liable for their "negligent performance of these improvements [which] directly caused Ned Church's injuries." Plaintiffs described the duty claimed here as follows: "It is well established law that where one undertakes work on a public highway which if not done carefully will create dangerous conditions to the general public, he is under a duty to use requisite care and that duty cannot be delegated." They submitted opinion evidence that, had the guiderailing been completed in accordance with the Callanan and San Juan contracts, the Jetta would have been prevented from plunging down the embankment and crashing at the bottom, thereby causing the infant plaintiff's serious injuries. Supreme Court denied the motion for summary judgment. On appeal from that denial, the Appellate Division reversed and granted summary judgment to San Juan (285 AD2d 16).1 After further proceedings not relevant to this appeal, a final judgment was entered at Supreme Court.

The case is before this Court as of right, pursuant to CPLR 5601 (d), on the basis of the two-Justice dissent at the Appellate Division. We now affirm.

The threshold and dispositive question on this appeal is whether San Juan owed the infant plaintiff a duty of care. The existence and scope of a duty of care is a question of law for the courts entailing the consideration of relevant policy factors (see Hamilton v Beretta U.S.A. Corp., 96 NY2d 222, 232 [2001]). In this case, any duty San Juan had with respect to the installation of guiderailing at milepost marker 132.7 on the southbound Thruway arose exclusively out of San Juan's contractual undertakings set forth in its subcontract with Callanan. In other words, San Juan had no preexisting duty imposed by law to install guiderailing at that point on the Thruway.

Beginning with Chief Judge Cardozo's landmark decision in H.R. Moch Co. v Rensselaer Water Co. (247 NY 160 [1928]), we have consistently held that, ordinarily, breach of a contractual obligation will not be sufficient in and of itself to impose tort liability to noncontracting third parties upon the promisor (see Eaves Brooks Costume Co. v Y.B.H. Realty Corp., 76 NY2d 220, 226 [1990]). Rather, the injured party is relegated to contractual remedies, if any. This reflects generally accepted legal principles, largely derived from Moch. "[I]f the alleged obligation to do or not to do something that was breached could not have existed but for a manifested intent [to contract], then contract law should be the only theory upon which liability would be imposed" (Prosser and Keeton, Torts § 92, at 656 [5th ed] [emphasis in original]).

As more extensively discussed in Espinal v Melville Snow Contrs. (98 NY2d 136, 139-141 [2002]), our cases have nevertheless thus far identified three sets of circumstances, as exceptions to the general rule, in which a duty of care to noncontracting third parties may arise out of a contractual obligation or the performance thereof. In such cases, the promisor is subject to tort liability for failing to exercise due care in the execution of the contract. The first is where the promisor, while engaged affirmatively in discharging a contractual obligation, creates an unreasonable risk of harm to others, or increases that risk (see id. at 139, 141-142 ["a defendant who undertakes to render services and then negligently creates or exacerbates a dangerous condition may be liable for any resulting injury" (citing Moch, 247 NY at 167)]). Moch describes that conduct, subjecting the promisor to tort liability, as "launch[ing] a force or instrument of harm" (247 NY at 168; see Cubito v Kreisberg, 51 NY2d 900 [1980], affg for reasons stated in op below 69 AD2d 738 [1979]).

The second set of circumstances giving rise to a promisor's tort liability is where the plaintiff has suffered injury as a result of reasonable reliance upon the defendant's continuing performance of a contractual obligation (see Espinal, 98 NY2d at 140 ["where the plaintiff detrimentally relies on the continued performance of the contracting party's duties"]; see also Prosser and Keeton, supra at 658; Restatement [Second] of Torts § 324A [c]).

Third, we have imposed tort liability upon a promisor "where the contracting party has entirely displaced the other party's duty to maintain the premises safely" (Espinal, 98 NY2d at 140 [citing Palka v Servicemaster Mgt. Servs. Corp., 83 NY2d 579, 589 (1994)]). In contrast to the first exception, the promisor under such circumstances may indeed be liable for failing to make conditions safer for the injured party.

Plaintiff fails to qualify under any of the...

To continue reading

Request your trial
248 cases
  • Braverman v. Bendiner & Schlesinger, Inc.
    • United States
    • New York Supreme Court Appellate Division
    • August 6, 2014
    ...... at 169, 159 N.E. 896) ]; see Church v. Callanan Indus., 99 N.Y.2d 104, 112, 752 N.Y.S.2d 254, 782 N.E.2d 50 [“failure to install ......
  • Gottesman v. Graham Apartments, Inc., 65447/2011.
    • United States
    • New York Civil Court
    • April 5, 2015
    ...Laboratory Specialists, Inc., 22 N.Y.3d 1, 977 N.Y.S.2d 676, 999 N.E.2d 1121 (2013) ; Church ex rel. Smith v. Callanan Industries, Inc., 99 N.Y.2d 104, 752 N.Y.S.2d 254, 782 N.E.2d 50 (2002) ; Sheila C. v. Povich, 11 A.D.3d 120, 781 N.Y.S.2d 342 (1st Dept 2004). “Negligence arises from a br......
  • Corwin v. NYC Bike Share, LLC
    • United States
    • U.S. District Court — Southern District of New York
    • March 1, 2017
    ...a contractual obligation, creates an unreasonable risk of harm to others, or increases that risk." Church v. Callanan Indus., Inc. , 99 N.Y.2d 104, 111, 752 N.Y.S.2d 254, 782 N.E.2d 50 (2002) ; see also Guzman v. Wackenhut Corp. , 394 Fed.Appx. 801, 803 (2d Cir. 2010) (summary order).On the......
  • Santos v. DEANCO Servs., Inc.
    • United States
    • New York Supreme Court Appellate Division
    • July 13, 2016
    ...condition (see Fung v. Japan Airlines Co., Ltd., 9 N.Y.3d 351, 361, 850 N.Y.S.2d 359, 880 N.E.2d 845 ; Church v. Callanan Indus., 99 N.Y.2d 104, 112, 752 N.Y.S.2d 254, 782 N.E.2d 50 ; Espinal v. Melville Snow Contrs., 98 N.Y.2d at 142, 746 N.Y.S.2d 120, 773 N.E.2d 485 ; Javid v. Sclafmore C......
  • Request a trial to view additional results
1 books & journal articles
  • Recent New York appellate decisions will impact municipal tort litigation.
    • United States
    • Fordham Urban Law Journal Vol. 30 No. 3, March 2003
    • March 1, 2003
    ...Affleck v. Buckley, 758 N.E.2d 651, 653-54 (N.Y. 2001). (21.) Id. (22.) Id. at 654. (23.) Id. at 653 (24.) See Church v. Callanan Indus., 782 N.E.2d 50, 52 (N.Y. 2002); Espinal v. Melville Snow Contractors, 773 N.E.2d 485, 488 (N.Y. 2002). (25.) Church, 782 N.E.2d at 53. (26.) Alston v. Sta......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT