City of Albertville, Ala. v. UNITED STATES FIDEL. & G. CO.
Decision Date | 11 February 1960 |
Docket Number | No. 17746.,17746. |
Parties | CITY OF ALBERTVILLE, ALABAMA, Appellant, v. UNITED STATES FIDELITY & GUARANTY COMPANY, Appellee. |
Court | U.S. Court of Appeals — Fifth Circuit |
Maurice F. Bishop, Birmingham, Ala., T. J. Carnes, Albertville, Ala., for appellant.
S. R. Starnes, Birmingham, Ala., Spain, Gillon & Young, Birmingham, Ala., of counsel, for appellee.
Before RIVES, Chief Judge, and BROWN and WISDOM, Circuit Judges.
The appellee, The United States Fidelity & Guaranty Company, sued the appellant, City of Albertville, Alabama, seeking to recover $38,100 (and the interest thereon) which the appellant had withheld as liquidated damages (381 days at $100 per day) under a provision of a contract between appellant and appellee's principal requiring completion of the contract within a stated time (150 days extended to 164 days). Appellee claimed that the provision was void because it was impossible to complete the contract within the stated time. The case was tried before a jury which returned a verdict in favor of the plaintiff in the amount claimed, $38,100 to which was added interest calculated by the Clerk in the amount of $5,689.95; and judgment was rendered in favor of the appellee against the appellant for the total sum of $43,668.95. This appeal is from that judgment.
Appellee's principal, C. N. Mason, entered into a contract with the City of Albertville for the construction of a sanitary sewer extension. Appellee was the surety on Mason's performance bond and on his bond guaranteeing payment of labor and materials. Prior to bidding on the job, Mason secured a copy of the plans and specifications prepared by the appellant's engineer, which later became a part of the contract. The specifications called for the laying of about twenty miles of sanitary sewer pipe. Appellant's engineers had estimated the quantity of rock to be excavated at 5000 cubic yards. Actually, it proved to be a little more than three times that amount. The theory upon which the appellee recovered judgment was that it was impossible to excavate such a large amount of rock and to complete the contract within the 164 days.
Pertinent parts of the specifications1 and of the bid proposal2 are quoted in the margin.
Mason's total bid was $346,882.76, included in which was a unit price of $3 per cubic yard on the estimated 5000 cubic yards of rock excavation. Mason's bid proposal was accepted and incorporated into the contract which provided in part:
There was no contention that the quantity or hardness of the rock, or any other circumstance, rendered ultimate performance of the contract impossible or so impractical as to excuse the contractor. In fact, before the institution of this suit the contract had been finally and completely performed except for the time period, as to which there was an admitted overrun of 381 days.
The issue decided by the jury's verdict may be understood from the following portion of the Court's charge to the jury:
The district court, in its charge, adopted what is referred to by Professor Williston as "the modern defense of impossibility," to the effect that, "* * * impossibility means not only strict impossibility but impracticability because of extreme and unreasonable difficulty, expense, injury or loss involved." A.L.I., Restatement of Contracts, Sec. 454. According to Professor Williston and to the Restatement of Contracts, of which he was the Reporter, that modern doctrine applies to partial impossibility, that is, to impossibility to perform part of the performance promised. 6 Williston on Contracts, rev. ed., § 1956; 2 Restatement of Contracts, § 463. Williston undertakes to trace the process of evolution of the rule from the early cases accepting "a strict rule which will require the parties, when they form a contract, to foresee its consequences as accurately as possible, though at the expense of serious hardship to one of them if unforeseen circumstances render it impossible under such circumstances," to the modern rule which he advocates giving an excuse under such circumstances. According to Professor Williston:
6 Williston on Contracts, rev. ed., § 1931.
The Supreme Court of Alabama has not yet adopted this so-called modern doctrine, nor written one way or the other on it. Its decisions to date tend to hold a promisor strictly to the literal terms of his promise. Stone v. Dennis, 1836, 3 Port. 231, 241, 242; Lee v. Cochran, 1908, 157 Ala. 311, 47 So. 581, 582; Marx v. Kilby Locomotive & Machine Works, 1909, 162 Ala. 295, 50 So. 136, 137; Capital Fertilizer Co. v. Ashcraft-Wilkinson Co., 1918, 202 Ala. 92, 79 So. 484, 487.3
For example, in Stone v. Dennis, supra, the Alabama Court said:
3 Port. 231, 241, 242.
Again, in Lee v. Cochran, supra, the Supreme Court of Alabama spoke as follows:
47 So. 581, 582.
In Marx v. Kilby Locomotive & Machine Works, supra, the Supreme Court of Alabama refused to relieve the locomotive works from its promise to "overhaul a locomotive thoroughly and put it in first-class running order" for the sum of $1,250.00 to be borne share and share alike by the contracting parties, for whose joint account it was agreed that the locomotive might later be sold at a price of $2,500.00. The Court held insufficient, as an excuse for nonperformance, a plea that inherent and hidden defects in the locomotive had been discovered by reason of which it would have taken about $3,000.00 or more to have made said engine marketable, and then it would have been worth only about $2,000.00 or $2,250.00, and would then have been a losing investment for both of the parties.
Encouraged...
To continue reading
Request your trial-
Phillips v. Amoco Oil Co.
...Mills should not be confused with the defense of "impossibility of performance." As noted in City of Albertville v. United States Fidelity & Guaranty Co., 272 F.2d 594 (5th Cir.1959), Alabama law has traditionally refused to recognize the "impossibility of performance" as a defense to a con......
-
Pruitt v. Pruitt
...for an affirmative charge is the substantial equivalent of a motion for a directed verdict, City of Albertville v. United States Fidelity and Guaranty Co., 272 F.2d 594 (5th Cir. 1960), and '(t)echnical precision is not necessary in stating grounds for the motion so long as the trial court ......
-
Gelber v. Sheraton-Hawaii Corp.
...we have considered this specification of error. 3 Psinakis v. Psinakis, 3 Cir., 221 F.2d 418; Albertville v. United States Fid. & Guar. Co., 5 Cir., 272 F.2d 594, 84 A.L.R.2d. 1. See Deponte v. Ulupalakua Ranch, supra. We have carefully reviewed the evidence adduced at the trial and find pl......
-
Hawkins v. First Fed. Sav. and Loan Ass'n
...15 Ala.L.Rev. 582 (1963). The Fifth Circuit has correctly interpreted our law in this area in City of Albertville, Ala. v. United States Fidelity & Guaranty Company, 272 F.2d 594 (1959). However, this court has recognized an exception to the strict rule. In the words of Greil Brothers Co. v......