City of Dardanelle & Yell Cnty. Wildlife Fed'n, Inc. v. Dep't of Transp., 4:14-cv-98-DPM

Decision Date05 March 2018
Docket NumberNo. 4:14-cv-98-DPM,4:14-cv-98-DPM
PartiesCITY OF DARDANELLE and YELL COUNTY WILDLIFE FEDERATION, INC. PLAINTIFFS v. DEPARTMENT OF TRANSPORTATION; FEDERAL HIGHWAY ADMINISTRATION; ARKANSAS STATE HIGHWAY & TRANSPORTATION DEPARTMENT; RIVER VALLEY REGIONAL INTERMODAL AUTHORITY; and DEPARTMENT OF DEFENSE, United States Army Corps of Engineers, Little Rock District DEFENDANTS
CourtU.S. District Court — Eastern District of Arkansas
ORDER

A stumble at the threshold prevents this Court from addressing, at this point, the deep issues in the complaint by Dardanelle and the Yell County Wildlife Federation about the planned intermodal facility in the Russellville Bottoms along the Arkansas River.

First, the unopposed motion to supplement the administrative record, No 162, is granted. The Court appreciates the Defendants' effort to locate the contract between the River Valley Regional Intermodal Facilities Authority and Parsons Infrastructure and Technology Group and bring it into the record. This agreement, though, confirms a problem rather than eliminating one.

Second, when a contractor is used to prepare an environmental impact statement, this non-governmental actor must "execute a disclosure statement prepared by the lead agency . . . specifying that [the contractor has] no financial or other interest in the outcome of the project." 40 C.F.R. § 1506.5(c).* This statement is in service of the government's regulatory duty to avoid conflicts of interest as it fulfills its National Environmental Protection Act obligations. Ibid. In 2004, when Parsons was retained, neither the Federal Highway Administration nor the Corps of Engineers prepared such a statement for Parsons. The contractor didn't prepare one either. The Authority and Parsons made the deal about who would draft the environmental impact statement. The Highway Administration had, by then, indicated that it would not move forward without this full environmental study. And Judge Billy Roy Wilson had preliminarily enjoined the Corps from doing so. All this was because the slack water harbor was only a part of the intermodal facility project, which aimed to bring together river, rail, and highway-related facilities. No. 4:03-cv-176-BRW, Order No 8.

The Authority/Parsons contract appears to be a form agreement for Arkansas State Highway and Transportation Department projects that will be funded, at least in part, by federal dollars. FHWA 13476-13551. The contract contains certifications. Parsons certified three things: it hadn't paid anybody to get the contract; it hadn't promised (as a condition for getting the contract) to hire anybody to do some of the work; and it hadn't made, or promised to make, any contribution or donation to secure the contract. FHWA 13531. These certifications echoed a covenant in the agreement. FHWA 13493. In the second certification, the Authority confirmed that Parsons hadn't been required to hire anybody, or pay anybody, to get the contract. FHWA 13532.

The record is, at this point, unclear about who prepared the Authority/Parsons contract and its appended certifications. Put that issue to one side. What is clear is that these certifications don't suffice under 40 C.F.R. § 1506.5(c). Parsons didn't say that it had no financial interest in whether this intermodal facility got approved. And Parsons didn't say that it had no other interest in the project's outcome. The absence of a compliant disclosure statement violated NEPA's implementing regulations.

Third, the Court is unpersuaded by the Defendants' arguments for overlooking this gap in the record.

The issue was not waived. The law's requirement is clear. No citizen need have spoken to preserve the right to complain about this kind of noncompliance. Department of Transportation v. Public Citizen, 541 U.S. 752, 764-65 (2004). To their credit, the Highway Administration, and later the Corps, caught this gap during the last stages of their reviews. FHWA 8771; COE 1052. Inquiries were made. The Arkansas State Highway and Transportation Department assured the Highway Administration that it had the proper disclosure statement on file. FHWA 8777. All it had, though, was the no-bribes certifications. The inquiries had been prompted in part by a 2006 public comment about possible conflicts of interest. FHWA 5147-5151. The comment was not directed at Parsons, but it cited 40 C.F.R. § 1506.5, and spoke generally about firms and people who might "gain from their involvement in the location, study, construction[,] or need of a proposed project." FHWA 5151. And the...