City of Piqua, Ohio v. Federal Energy Regulatory Commission

Decision Date21 September 1979
Docket NumberNo. 78-1487,78-1487
Citation610 F.2d 950,198 U.S.App.D.C. 8
Parties, 33 P.U.R.4th 89 The CITY OF PIQUA, OHIO, Petitioner, v. FEDERAL ENERGY REGULATORY COMMISSION, Respondent, Dayton Power and Light Company, Intervenor.
CourtU.S. Court of Appeals — District of Columbia Circuit

Lynn N. Hargis, Asst. Gen. Counsel, Federal Energy Regulatory Commission, Washington, D. C., with whom Howard E. Shapiro, Sol., Federal Energy Regulatory Commission, Washington, D. C., was on brief, for respondent.

J. Richard Tiano, Richard M. Merriman, Robert S. Waters, Washington, D. C., and M. A. Gribler, Dayton, Ohio, were on brief, for intervenor.

Before TAMM and MacKINNON, Circuit Judges, and AUBREY E. ROBINSON, Jr., * United States District Judge for the District of Columbia.

Opinion for the court filed by Circuit Judge TAMM.

TAMM, Circuit Judge:

In this case, we review two orders of the Federal Energy Regulatory Commission (FERC or Commission): one allowing a rate increase, for good cause shown, to take effect prior to filing with the Commission, 1 and the other reversing the Commission's rejection of a filing for a firm power rate increase. 2 We affirm both orders as authorized by statute and supported by substantial evidence.

I.

Intervenor Dayton Power and Light Company (DP&L) supplied partial requirements electric service to petitioner City of Piqua, Ohio (Piqua or City) under an Interconnection Agreement (Agreement). The Agreement was to terminate on May 9, 1977. One week prior to that date, Piqua and DP&L submitted to the Piqua City Commission, as required by Ohio law, a negotiated modification to the Agreement increasing rates to be charged for various kinds of electric service. 3 DP&L, however, delayed its filing with the Commission while awaiting action by the Piqua City Commission. On July 18, 1977, the City Commission approved the negotiated contract "for the term of May 10, 1977 to March 10, 1978" with two additional changes: (1) extension of the Agreement to March 10, 1978, for municipal administrative reasons; and (2) continuation of the 5000 kilowatt (kw) firm power contract demand from May 10 through June 19, 1977, with an increase to 8000 kw from June 20, 1977, through March 10, 1978.

On August 5, 1977, DP&L submitted the new contract to the Commission for filing, stating that the Agreement had been modified to "remain in effect from May 10, 1977 through March 10, 1978" and requesting the Commission to "waive any requirements not already complied with under Section 35.13 of the Commission's Regulations and permit the modification to become effective on May 10, 1977." Dayton Power & Light Co., Docket No. ER77-546, DP&L Transmittal Letter from R.E. McCormick to Kenneth F. Plumb, Secretary, FPC, at 1, 3 (Aug. 5, 1977). By October 14, DP&L had cured deficiencies in its filing, as requested by the Commission. The Commission issued public notice of the filing on November 4, 1977.

One week later, the Commission issued an order accepting for filing Schedules B, C, and D of the proposed rate changes. The Commission, due to DP&L's delay in filing from May to August, denied its request for waiver of filing requirements and gave the schedules prospective application only. The Commission also rejected Schedule A as unsupported by appropriate cost data. DP&L sought rehearing of the Commission's refusal to waive the notice requirement, explaining that the Piqua City Commission's modification and review of the Agreement had delayed the rate change filing. DP&L further requested the Commission to reverse its rejection of Schedule A, offering cost data already before the Commission in another proceeding as justification for the increase.

On January 18, 1978, the Commission issued the first of the orders under review and reversed its rejection of Schedule A, finding that DP&L's submittal of cost data from another proceeding sufficiently justified the proposed firm power rates to Piqua. The Commission also found good cause for waiver of the prior notice requirement, in accordance with section 205(d) of the Federal Power Act (Act), 16 U.S.C. § 824d(d) (1976) 4 and section 35.11 of the Commission regulations. 5 In finding good cause for waiver, the Commission relied on three factors: (1) the delay due to Ohio statutory procedure requiring Piqua to submit the contract to its City Commission for approval; (2) Piqua's explicit agreement to a May 10, 1977, effective date for rate increases; and (3) the lack of objection to the May 10 date from any party at the time of DP&L's rate filing. Thus the Commission approved an effective date of May 10, 1977, for Schedules B, C, and D and an effective date of May 11, 1977, for Schedule A.

On April 3, 1978, the Commission issued the second order under review and denied rehearing. It rejected Piqua's argument that the January 18 order was unauthorized retroactive ratemaking and an abuse of discretion by the Commission. 6 This petition for review followed.

II.

Piqua challenges the Commission's assignment of a retroactive date to the rate increases as: (1) unauthorized by statute; (2) prohibited by the policy against retroactive ratemaking; and (3) unsupported by substantial evidence.

A. Statutory Authorization

The Commission relies upon section 205(d) of the Act as statutory authority for the Commission to allow the rates to take effect without requiring advance notice. As the Commission emphasizes, the Act requires that no rate may be changed without thirty days' notice "(u)nless the Commission otherwise orders." 16 U.S.C. § 824d(d). Further the Act provides that the "Commission, for good cause shown, may allow changes to take effect Without requiring the thirty days' notice herein provided for . . . ." Id. (emphasis added). Relying on this language, the Commission concludes that the Act gives it discretion, for good cause shown, to waive the prior notice requirement.

Piqua contends that Congress intended section 205(d) to be read narrowly. According to Piqua, the provision only allows the Commission to shorten the thirty days' notice period and to limit rate changes to a post-filing effective date. As additional support for its contention, Piqua offers a lexicographic analysis of the statute. Piqua particularly emphasizes that congressional use of "shall" and "to be" in section 205(d) conclusively denoted futurity, thus authorizing only prospective rate changes.

Such a grammatical nicety is neither persuasive nor dispositive. 7 Moreover, Piqua's literal interpretation renders the statute too restrictive. The language of section 205(d) is certainly not so clear or unambiguous as to bind us to give effect to the literal meaning. See Caminetti v. United States, 242 U.S. 470, 485, 37 S.Ct. 192, 61 L.Ed. 442 (1917). Therefore, we must consider the policies underlying the Act, for the "intention prevails over the letter, and the letter must if possible be read so as to conform to the spirit of the Act." 2A Sutherland Statutory Construction § 46.07, at 65 (4th ed. 1973). Due consideration of the agency interpretation 8 of section 205(d) is also appropriate. 9

The primary purpose of section 205(d) is to notify the Commission of changes in rates and schedules between parties to a utilities contract. United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U.S. 332, 339-40, 76 S.Ct. 373, 100 L.Ed. 373 (1956). 10 A change in rates cannot take place without first filing notice with the Commission. Once notice has been filed, the Commission can investigate and review the rate change to ensure that it serves the public interest. The effective date of the rate change is left to the discretion of the Commission. As this court has stated, "(s)ection 205 purports to dictate not When contractually-authorized rate increases Can be made operative but only that they Cannot become operative at any time without compliance with the statutory procedure." City of Kaukauna v. FERC, 189 U.S.App.D.C. 215, 218, 581 F.2d 993, 996 (1978) (footnote omitted).

We must also consider the policies underlying section 205(d). One such policy is to recognize private contractual arrangements between parties to a utility agreement. 11 The Supreme Court, discussing this issue, declared, "(W)e should bear in mind that (the Act) evinces no purpose to abrogate private rate contracts as such. To the contrary, by requiring contracts to be filed with the Commission, the Act expressly recognizes that rates to particular customers may be set by individual contracts." United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U.S. at 338, 76 S.Ct. at 378. Deference to the parties' contractual arrangements, according to the Court, does not impair the regulatory powers of the Commission. The Commission at any time can conduct hearings on a contract rate and modify it if unreasonable. 12

The Commission's interpretation of section 205(d), authorizing rates without requiring advance notice, for good cause shown, furthers these policies. DP&L submitted the rates for review and thereby provided the public an opportunity to comment. The Commission reviewed and approved the schedule rates, thus ensuring that the public would not be overcharged and "enhanc(ing) the stability of electric supply arrangements in the future between Piqua and Dayton." Dayton Power & Light Co., Docket No. ER77-546, Order Denying Rehearing and Amending Prior Order, at 8 (Apr. 3, 1978). Moreover, the Commission, in enforcing the effective date negotiated by Piqua and DP&L, is merely honoring the intent of the parties, rather than abrogating a private rate contract. This result is consistent with the principle that, within the regulatory framework, "the effective date of any consensual rate hike is a matter committed to agreement by the parties." City of Kaukauna v. FERC, 189 U.S.App.D.C. at 218, 581 F.2d at 996.

B. Retroactive Ratemaking

Piqua argues the Commission's orders and interpretation of section 205(d) violate...

To continue reading

Request your trial
40 cases
  • Arkansas Louisiana Gas Company v. Hall
    • United States
    • U.S. Supreme Court
    • 2 July 1981
    ...has been made cognizant." City of Cleveland v. FPC, 174 U.S.App.D.C. 1, 10, 525 F.2d 845, 854 (1976). See City of Piqua v. FERC, 198 U.S.App.D.C. 8, 13, 610 F.2d 950, 955 (1979). Not only do the courts lack authority to impose a different rate than the one approved by the Commission, but th......
  • Boston Edison Co. v. F.E.R.C.
    • United States
    • U.S. Court of Appeals — First Circuit
    • 6 June 1988
    ...579 F.2d at 667; see also FPC v. Hope Natural Gas Co., 320 U.S. 591, 618, 64 S.Ct. 281, 295, 88 L.Ed. 333 (1944); City of Piqua v. FERC, 610 F.2d 950, 954 (D.C.Cir.1979). As Justice Frankfurter explained, the Act did not give the Commission power to order make-whole refunds for past unreaso......
  • Iowa Network Services, Inc. v. Qwest Corp.
    • United States
    • U.S. District Court — Southern District of Iowa
    • 17 August 2005
    ...or even authorized by an agency violate the rule against retroactivity, "a cardinal principal of ratemaking." City of Piqua v. FERC, 610 F.2d 950, 955 (D.C.Cir.1979). According to Qwest, if an agency may not authorize retroactive application of rates and terms, neither may a carrier do so 6......
  • In re PJM Interconnection, LLC
    • United States
    • Federal Energy Regulatory Commission
    • 27 July 2023
    ... ... , EL23-19-001 United States of America, Federal" Energy Regulatory Commission July 27, 2023 ... \xC2" ... 831 F.2d 1135, 1141 (D.C. Cir. 1987); City of Piqua v ... FERC , 610 F.2d 950, 954 (D.C ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT