Clipper v. Sprenger, 136 September Term, 2005.
Citation | 399 Md. 539,924 A.2d 1160 |
Decision Date | 08 June 2007 |
Docket Number | No. 136 September Term, 2005.,136 September Term, 2005. |
Parties | CLIPPER WINDPOWER, INC., et al. v. Paul C. SPRENGER, et al. |
Court | Court of Special Appeals of Maryland |
Miles H. Mitchell, Deputy Gen. Counsel (Susan Stevens Miller, Gen. Counsel, Baltimore, MD), on brief; Jeffrey A. Lamken (David A. Super of Baker Botts, L.L.P., Washington, DC), on brief, for Petitioners.
John J. Coyle, Jr. (Hidey, Coyle & Monteleone, Cumberland, MD), on brief, for Respondents.
Argued Before BELL, C.J., RAKER,
*WILNER, CATHELL, HARRELL, BATTAGLIA and GREENE, JJ.
This case arises out of a dispute over the construction of a wind turbine facility in Garrett County, Maryland. On March 26, 2003, the Public Service Commission (the "Commission"), one of the petitioners, entered a final order (Order No. 78354) granting Clipper Windpower, Inc. ("Clipper"), the other petitioner (collectively "the petitioners"), a Certificate of Public Convenience and Necessity ("CPCN") for the construction of a 101 megawatt ("MW") wind turbine facility. On April 24, 2003, by letter signed by Eric Tribbey, on behalf of, and as its representative, Friends of Backbone Mountain ("Friends") requested a rehearing.1 That request was denied (Order No. 78617). Thereafter, Tribbey, one of the respondents, acting on his own behalf, filed a petition in the Circuit Court for Baltimore City for judicial review2 of both orders (Case No. 24-C-036366). This action for judicial review was consolidated with the judicial review action initiated by Paul C. Sprenger, Russell W. Bounds, and Troy Gnegy, the other respondents (collectively "the respondents"), who also filed petitions for judicial review (Case No. 24-C-036325).
Clipper and the Commission each filed a motion to dismiss, asserting that the respondents' petitions for judicial review were untimely.3 The Circuit Court agreed and, therefore, dismissed the actions for judicial review. The respondents noted an appeal to the Court of Special Appeals, which, in an unreported opinion, reversed the judgment of the Circuit Court.
We granted the petitions for writ of certiorari filed by both Clipper and the Commission, Clipper Windpower v. Sprenger, 391 Md. 577, 894 A.2d 545 (2006), to address:
"Whether PUC § 3-114(c) limits the right to request rehearing solely to `a party in interest' that has properly intervened as such in the Commission's proceedings, and is thus distinguishable from PUC § 3-202(a) which provides a right to judicial review to `a party or person in interest ... dissatisfied by a final decision or order of the Commission ...'?"[4]
While, to be sure, the right to judicial review of orders and decisions of the Commission is available to "a party or person in interest ... dissatisfied by a final decision or order of the Commission ...," PUC § 3-202(a),5 we conclude that only a "party in interest" may seek rehearing under PUC § 3-114. To be a "party in interest," if the requestor was not a party, the requestor must have intervened properly, pursuant to PUC § 3-106,6 thus becoming a "party" to the proceeding.
On August 26, 2002, Clipper filed an application with the Commission seeking authorization to build a wind turbine facility for the purpose of generating electricity. As required, Clipper notified the public, by publishing a notice in both The Republican and The Cumberland Times-News, generally circulated newspapers in Garrett County, on the successive weeks of September 26, 2002, September 30, 2002, October 3, 2002, and October 6, 2002, of its application to build the facility, and the date, time, and location of a scheduled pre-hearing conference.
The wind turbine facility was to be composed of up to 67 individual turbines. Each turbine would consist of a free-standing tower approximately 262 feet in height. A rotor, having a diameter not in excess of 262 feet (80m) (39m blades), would be attached to the tower. The maximum combined height would be approximately "394 ft (120 m) with one blade in the vertical position." Clipper's executive summary of its proposal for the facility implied that some, but not all, of the turbines would be of that size and stated that all 67 turbines may not need to be built depending upon "factors ... not identified prior to [the] start of construction." In addition to the tower and the blade, each turbine would consist of a foundation anchoring it to the ground and a transformer that would collect the power from the turbines and transfer it to a substation through an "underground electrical collection system." All-weather gravel service roads would be built from existing hardtop roads and the cables associated with the electrical collection system were to be buried alongside such service roads. The total project area would cover approximately 10.8 miles and would be constructed on Backbone Mountain extending from "Wild Turkey Rock at an elevation of 3,228 ft (984 m) above sea level southwestward to Allegheny Heights at 3,200 ft (975 m)." Although three other sites were surveyed, Allegheny Heights was selected "because of wind resource potential and favorable site characteristics (primarily contiguous, well-exposed areas and proximity to three transmission lines)."7
An adjudicatory hearing regarding Clipper's proposal, at which attendance was high, "standing room only," was held. Clipper, the Department of Natural Resources's Power Plant Research Program, the staff of the Commission, and the Office of People's Counsel were the named parties to the proceeding. Pursuant to PUC § 3-106, four individual members of the public intervened and were granted party status.8 Among those in attendance were respondents Eric Tribbey and Russell Bounds, who also testified. Although both Tribbey and Bounds submitted citizen comment letters following the conclusion of the hearing, neither they, nor Friends, sought to intervene.
The hearing examiner issued a proposed order that contained and recommended settlement conditions to which all of the parties had agreed, which the Commission subsequently adopted. It issued a final order (Order No. 78354) approving Clipper's plan.
Tribbey, then, writing on behalf of Friends, submitted a letter to the Commission requesting a rehearing.9 The Commission, by Order No. 78617, denied the request, explaining:
Order No. 78617 (internal footnotes omitted). Thus, the Commission concluded that Friends was not a "party in interest" under PUC § 3-114 because it had not properly intervened under PUC § 3-106. The Commission also determined that it already had fully considered the issues presented for rehearing in the original proceedings and it was not necessary to readdress them or to address them further.11
Thereafter, as we have seen, Tribbey, on his own behalf, and...
To continue reading
Request your trial-
Mcglone v. State
... ... City of Annapolis, 402 Md. 587, 613-14, 937 A.2d 242, 258 (2007); Magnetti v. Univ. of Md., 402 Md. 548, 565, 937 A.2d 219, 229 (2007); Clipper Windpower, Inc. v. Sprenger, 399 Md. 539, 554, 924 A.2d 1160, 1168 (2007)." ... Id. at 426, 952 A.2d at 270 ... ...
-
Halici v. Gaithersburg
... ... Our primary goal in construing a statute is to ascertain the legislature's intent. Clipper Windpower, Inc. v. Sprenger, 399 Md. 539, 553, 924 A.2d 1160 (2007). "Ordinary, popular understanding of the English language dictates ... ...
- Schreyer v. Chaplain
-
Himes v. Anderson
... ... Our primary goal in construing a statute is to ascertain the legislature's intent. Clipper Windpower v. Sprenger, 399 Md. 539, 553, 924 A.2d 1160 (2007). "If the statutory language is clear and unambiguous, we need not look beyond the ... ...