Coat Corporation of America v. United States, 48250.

Decision Date15 July 1952
Docket NumberNo. 48250.,48250.
Citation105 F. Supp. 832,123 Ct. Cl. 176
PartiesCOAT CORPORATION OF AMERICA v. UNITED STATES.
CourtU.S. Claims Court

Edwin J. McDermott, Philadelphia, Pa., for plaintiff.

Kendall M. Barnes, Washington, D. C., with whom was Asst. Atty. Gen. Holmes Baldridge, for defendant.

Before JONES, Chief Judge, and LITTLETON, WHITAKER, MADDEN and HOWELL, Judges.

WHITAKER, Judge.

Plaintiff sues on a contract with the defendant's Quartermaster Corps to furnish 7,500 officers' raincoats at $5.50 each, which was allegedly modified by a supplemental agreement raising the price to $9.15 each. Defendant claims the supplemental agreement was executed without authority and that it is not bound by it.

The original contract was dated December 14, 1944. It called for delivery of the entire quantity by February 20, 1945. In Article 5 the contract authorized the Government to terminate it if the coats were not delivered on time. This article appears in a note below.1

By February 27, 1945, plaintiff itself had delivered 6,371 coats, but all of them, except 100, had been rejected. In addition, plaintiff had delivered through a subcontractor 2,095 coats, of which 137 had been rejected. No further coats were delivered, apparently because plaintiff learned defendant intended to terminate the contract.

On March 13, 1945, defendant wired plaintiff that its right to deliver 5,400 coats under the contract was being terminated because of the delay. Formal notice to this effect was mailed on May 1.

For the 2,058 acceptable coats delivered, plaintiff has been paid the contract price of $5.50 each. It claims the revised price of $9.15 under the supplemental agreement.

This supplemental agreement recited the provisions of article 26 of the original contract providing for a revision of the price, and stated that it was executed under the authority of the First War Powers Act, 50 U.S.C.A.Appendix, § 601 et seq. Article 26, quoted in the footnote below,2 provides for a revision in the price based upon the actual experience of the contractor in producing 30 percent of the articles.

The supplemental agreement was entered into on May 16, 1945, a little over two months after the telegram terminating the contract as to 5,400 of the coats and about two weeks after the formal notice terminating it. It amended the original contract "to provide for furnishing and delivering the unterminated portion of 2,100 raincoats * * * at a unit price of $9.15 in lieu of $5.50." This contract is quoted in full in Finding 5, and also in the note below.3

When this contract was entered into 2,058 of the 2,100 coats had been delivered. According to its letter the price of $9.15 applied only to the balance of 42 coats, but plaintiff says it was intended to apply to the 2,058, and it probably was. We do not decide this question, however, because we think the contract was executed without authority and, hence, is invalid.

The original contract called for a revision in the price only after 30 percent of the articles had been delivered. Plaintiff had defaulted on its contract and the contract had been terminated before delivery of so many. Thirty percent was 2,250; plaintiff's total deliveries were 2,058. The contract did not contemplate a revision in price where the contract was terminated for the contractor's default before it was fully, or at least substantially, performed. Article 26, providing for a revision in price after delivery of 30 percent of the articles, said, the Government and the contractor "recognize that the costs of performing that part of the contract will not be typical for the remainder of the contract, but will provide sufficient information and experience to permit revision of the price."

It is significant that defendant purchased 400 of the remainder of the coats which plaintiff did not deliver at $5.67 each, and 5,000 at $6.37 each, whereas the price under the supplemental contract was $9.15 each.

Where the contractor had defaulted before delivery of the 30 percent, the revision-of-price provision did not come into play. Experience shows that ordinarily the cost of producing the first 30 percent of articles called for in a contract is greater than that of producing the remainder. The revised price was intended to apply to 100 percent of the contract and not merely to 30 percent thereof, or less. The Government contracted to revise the price if it got its entire order, not just a small part of it.

The plaintiff was not entitled to the revision under the original contract. Therefore, the supplemental contract was without consideration to the Government. Army Procurement Regulation No. 3 provides:

"Except as otherwise specifically provided in these Regulations, approval by the Director, Purchases Division, Headquarters, Army Service Forces, will be required for each supplemental agreement or change order which does not involve the receipt by the Government of adequate legal consideration, or which modifies or releases an accrued obligation owing directly or indirectly to the Government including accrued liquidated damages or liability under any surety or other bonds. * * * The Director, Purchases Division, will signify his approval by manual execution of the supplemental agreement or change order, where such instrument is submitted, or where such instrument is not submitted, by memorandum, indorsement, letter or telegram in response to the request for approval. * * *"

This is published in 9 Federal Register, page 8390, and, therefore, under Section 7 of the Federal Register Act, 49 Stat. 502, 44 U.S.C.A. § 307, it was notice to all the world.

Plaintiff has not shown that the contracting officer had such authority.

Plaintiff is not entitled to recover. See MacLaren Sportswear Co. v. United States, 101 F.Supp. 885, 121 Ct.Cl. 396.

Defendant has filed six counterclaims. Its sixth one is on the excess of what it cost to secure the remainder of the coats undelivered by plaintiff over the original price at which plaintiff agreed to deliver them. Defendant is...

To continue reading

Request your trial
3 cases
  • Star-Kist Foods v. Chicago, Rock Island & Pac. RR
    • United States
    • U.S. District Court — Northern District of Illinois
    • February 6, 1984
    ...be thereby affected. Federal Crop Insurance Corp. v. Merrill, 332 U.S. 380, 68 S.Ct. 1, 92 L.Ed. 10 (1947); Coat Corp. of America v. U.S., 123 Ct.Cl. 176, 196, 105 F.Supp. 832 (1952); Lynsky v. U.S., 130 Ct.Cl. 149, 153, 126 F.Supp. 453 (1954), 9 Wright & Miller, § 2410. Absent fraud or mis......
  • Wolfson v. United States
    • United States
    • U.S. Claims Court
    • March 20, 1974
    ...502, 44 U.S.C. § 1507. This court has recognized this principle on several occasions. See, e.g., Coat Corp. of America v. United States, 123 Ct.Cl. 176, 196, 105 F.Supp. 832, 834 (1952); Lynsky v. United States, 130 Ct.Cl. 149, 153, 126 F.Supp. 453, 456 As mentioned earlier, after plaintiff......
  • Winston Bros. Company v. United States
    • United States
    • U.S. Claims Court
    • April 14, 1972
    ...§§ 1505, 1507 (1970); Lynsky v. United States, 126 F.Supp. 453, 456, 130 Ct.Cl. 149, 153 (1954); Coat Corp. of America v. United States, 105 F.Supp. 832, 834, 123 Ct.Cl. 176, 196 (1952). Defendant relies heavily on the ASPR to support its proposition that insurance taken out by the contract......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT