Colorado Environments, Inc. v. Valley Grading Corp.

Decision Date23 August 1989
Docket NumberNo. 18933,18933
Citation779 P.2d 80,105 Nev. 464
PartiesCOLORADO ENVIRONMENTS, INC., now known as Bilbray Industries, a Nevada corporation, Appellant, v. VALLEY GRADING CORPORATION, Respondent.
CourtNevada Supreme Court
OPINION

PER CURIAM:

On February 28, 1983, appellant Colorado Environments, Inc., now known as Bilbray Industries (CEI), entered into a contract with respondent Valley Grading Corporation (Valley). Pursuant to the terms of the contract Valley was to construct certain on-site and off-site improvements, including two flood retention dams, in a proposed subdivision CEI was preparing to develop in Laughlin. The contract was silent as to the date on which construction was to begin, and CEI did not expressly condition its performance upon obtaining the permits necessary to commence the project. When the parties executed the contract, CEI informed Valley that the subdivision's plans were in the final approval stage with Clark County's Public Works Department (Public Works) and that construction would commence within two weeks.

Contrary to what CEI had indicated, work on the subdivision did not begin within two weeks. Public Works withheld its final approval of the subdivision plans when concerns arose over CEI's proposed use of "earth-filled" or pervious core dams, rather than impervious core dams as CEI indicated in its initial flood control study. By early April, 1983, CEI decided to abandon the flood retention dam concept and opted for an armored drainage channel instead. On April 12, 1983, CEI and Valley executed a second contract in which Valley agreed to construct the drainage channel. The total price for the two contracts was $1,593,670.

In the interim between Spring and Fall of 1983, Valley bid and performed other projects with CEI's approval. In September, 1983, CEI informed Valley that construction on the Laughlin subdivision would begin October 1, 1983. Thereafter, CEI again revised the commencement date to November 1, 1983. On October 24, 1983, Valley, apparently fearing yet another postponement, wrote to CEI and demanded that work commence within fifteen days, or that the contracts be cancelled and it receive 20% of the contract price as damages. CEI did not respond to the demand in writing, but, sometime after November 1, 1983, CEI's president, Robert Bilbray, informed Valley that he was accepting bids from other contractors to perform the work. In a letter dated November 16, 1983, Valley expressed its continued willingness to perform the two contracts and characterized CEI's "bid shopping" as unethical.

CEI again contacted Valley about performing the Laughlin contracts in April, 1984. The possibility of Valley performing the work ended, however, when Valley refused to reduce its contract price by $100,000 as Bilbray demanded. Valley brought the suit that is the subject of this appeal in mid-June, 1984. Thereafter, CEI awarded the construction contracts to another company who commenced work in December, 1984. Following trial on Valley's breach of contract action, a jury found in Valley's favor and awarded it compensatory damages in the amount of $1,035,600. The jury's award included damages for lost profits ($521,449) and standby equipment or delay damages ($514,151). 1 This appeal ensued.

At trial, CEI contended, among other things, that governmental interference prevented it from performing its contracts with Valley and that its performance was contingent upon an implied condition, i.e., that governmental regulations or orders would not prevent its performance within a reasonable time. CEI therefore offered proposed jury Instruction No. 17. The proposed instruction provided: "An implied condition operates where parties enter into a ocntract [sic] on the assumption that some thing essential to its performance will occur." The district court refused to give the proposed instruction because it believed that the concept of implied conditions was adequately covered in another instruction and that the proposed instruction would confuse the jury. CEI now contends that the district court erred in refusing to give proposed Jury Instruction No. 17. We disagree.

It is a party's right to have the jury instructed on the theories of its case which are supported by the evidence. Beattie v. Thomas, 99 Nev. 579, 583, 668 P.2d 268, 271 (1983). Where other instructions inform the jury of information contained in a proposed instruction, however, the trial court should not give the latter. Id. Instruction No. 16, the instruction that the district court gave on contract conditions, provided:

Performance of a contract may be subject to conditions and performance need not take place until the conditions are fulfilled. Such conditions may be express or implied. By the phrase "express condition" is meant a provision which is specifically agreed to by the parties either orally or in writing. By the term "implied condition" is meant a term or condition which is recognized by the parties to exist and to bind them in their action despite the fact that it is not expressly spelled out or agreed to by the parties. Such terms are often said to arise by implication from the terms which were expressly enumerated in the contract and agreed to or from practice with the industry or business within which the proposed contract performance would take place. Nonoccurrence of the condition, express or implied, excuses the parties from performing the contract, unless one of the parties is responsible for that nonoccurrence.

(Emphasis supplied).

The message conveyed by the above emphasized language in Instruction No. 16 is essentially the same as that contained in CEI's proposed instruction. Instruction No. 16 adequately informed the jury of the concept of implied conditions. Therefore, the proposed instruction would have been redundant. Moreover, unlike the instruction that the district court gave, the proposed instruction did not fully inform the jury that performance is not excused when a party is responsible for the nonoccurrence of the condition. Thus, and as the district court believed, the proposed instruction could have confused the jury. Accordingly, we believe that the district court did not err in refusing to give proposed jury Instruction No. 17.

CEI also contends that the district court erred by giving Instruction No. 18 which provided:

A party to a contract may be relieved of his duty to perform under a contract, either temporarily or permanently, when the party's performance is rendered impossible by unforeseen events or occurrences.

Under Nevada law, one who contracts to render a performance for which government approval is required has the duty of obtaining such approval and the risk of its refusal is on him. Where the requirement of government approval is foreseeable, and is not addressed in the contract, the failure to obtain such approval by the party seeking it does not justify the party's breach of the agreement, or his failure to perform.

Moreover, where a government regulation does not prohibit performance, but only renders it more costly or difficult to perform, the defense of impossibility of performance does not apply.

Although CEI admits that the requirement of securing the permits to construct was foreseeable, it contends that the second paragraph of the instruction informed the jury that Public Works' refusal to issue the necessary permits provided no excuse or justification for CEI's failure to perform. Therefore, argues CEI, the instruction required the jury to reject CEI's theory of defense. Again, we disagree.

Instruction No. 18, which was based on our decision in Nebaco, Inc. v. Riverview Realty, 87 Nev. 55, 482 P.2d 305 (1971), is a correct statement of the law applicable to this case. See Hawkins v. First Fed.Sav. and Loan Ass'n, 280 So.2d 93 (1973); see also 6 Corbin, Corbin on Contracts § 1347, at 435 (1962) ("Ordinarily, when one contracts to render a performance for which a governmental license or permit is required it is his duty to get the license or permit so that he can perform. The risk of inability to obtain it is on him; and its refusal by the government is no defense in a suit for breach of his contract.") (quoted in Hawkins, 280 So.2d at 97). The first paragraph of Instruction No. 18 clearly informed the jury that if CEI's performance was rendered impossible by unforeseen events or occurrences, then CEI would be relieved, either temporarily or permanently, of its contractual obligations. Thus, the instruction did not require the jury to reject CEI's argument that performance of the contract was rendered impossible by unforeseen governmental requirements that CEI did not cause itself. Rather, and contrary to CEI's argument that Instruction No. 18 required the application of a presumption, the instruction required the jury to determine a factual question, viz. whether the delay in approval of CEI's plans resulted from unforeseeable events or occurrences. The jury decided this question against CEI. From our review of the record, the jury's deciding as it did is more attributable to the evidence Valley produced at trial than any supposed deficiency in the instruction. Valley produced abundant evidence from which the jury could have found that CEI's own corner and cost cutting measures, as well as its refusal to cooperate with Public Works, caused the...

To continue reading

Request your trial
18 cases
  • Coleman v. Strohman
    • United States
    • Wyoming Supreme Court
    • November 21, 1991
    ... ... Ins. Service, Inc. v. Jericho Plantation, Inc., 481 So.2d 343 ... Town of Oro Valley, 163 Ariz. 527, 789 P.2d 394 (1990); White v ... 124, 768 P.2d 845 (1988); Colorado Environments, Inc. v. Valley Grading Corp., 105 ... ...
  • Countrywide Home Loans, Inc. v. Thitchener
    • United States
    • Nevada Supreme Court
    • September 11, 2008
    ... ... See NRAP 3A(b)( l ); Lee v. GNLV Corp., 116 Nev. 424, 996 P.2d 416 (2000) ... 5. Topaz ... 9. See Colorado Environments v. Valley Grading, 105 Nev. 464, 472, 779 ... ...
  • Rd. & Highway Builders, LLC v. N. Nev. Rebar, Inc.
    • United States
    • Nevada Supreme Court
    • August 9, 2012
    ... ... Colorado Environments v. Valley Grading, 105 Nev. 464, 47071, 779 ... ...
  • Mobilizegreen, Inc. v. Cmty. Found. for the Capital Region
    • United States
    • D.C. Court of Appeals
    • January 27, 2022
    ... ... 41 U.S.C. 6305(a) ; Vermont Yankee Nuclear Power Corp. v. Entergy Nuclear Vermont Yankee, LLC , 683 F.3d 1330, ... Env'ts, Inc. v. Valley Grading Corp. , 105 Nev. 464, 779 P.2d 80, 82 (1989) ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT