Condon v. South Side R. R. Co.
Decision Date | 27 April 1858 |
Citation | 55 Va. 302 |
Parties | CONDON v. SOUTH SIDE R. R. Co. |
Court | Virginia Supreme Court |
The agreement between a rail road company and a contractor provides: And whereas the above work must be inspected and received, it is hereby agreed that the engineer of the company or some one appointed by him, shall be the inspector of said work, shall determine when this contract is complied with according to its just and fair interpretation, and the amount of the same, and all disputes and difficulties arising under the same; and his decision shall be obligatory and conclusive between the parties to this contract, without further recourse of appeal. HELD:
1. The decision of the engineer is conclusive upon the parties: And this in relation to the price of a species of excavation not mentioned in the specifications.
2. Such a contract is legal and binding on the parties.
This was an action of assumpsit in the Circuit court of the city of Petersburg, brought by David Condon against the South Side Rail Road Company. The plaintiff had been a contractor to execute the work on a section of the road of the company; and the only question was, Whether, under the contract between the parties, the action of the engineer in determining the character and fixing the price of removing certain rock, was conclusive upon the parties? The case is stated in the opinion of Judge MONCURE. There was a judgment for the defendant in the Circuit court: and thereupon Condon applied to this court for a supersedeas, which was allowed.
J Alfred Jones, for the appellant, referred to Harrison v The Great Northern R. Co. 8 Eng. L. & E. R. 469; Wilson v. York & Maryland Line R. R. Co. 11 Gill & John. 58; United States v. Robeson, 9 Peters' R. 319; Mansfield & Sandusky R. R. Co. v Veeder & Co. 17 Ohio R. 385; 2 Tuck. Com 30-35; 2 Story's Equ. Jur. § 1053-1056.
Joynes, for the appellee, cited Scott v. Avery, 20 Eng. L. & E. R. 327; S. C. 36, Id. 1; United States v. Robeson, 9 Peters' R. 319; Morgan v. Birnie, 23 Eng. C. L. R. 414; Milner v. Field, 1 Eng. L. & E. R. 531; Glenn v. Leith, 22 Eng. L. & E. R. 489; Grafton v. Eastern Counties R. Co. Id. 557; Northampton Gas-Light Co. v. Parnell, 29 Id. 229; Worsley v. Wood, 6 T. R. 710; Mason v. Harvey, 20 Eng. L. & E. R. 541; Leadbetter v. Etna Ins. Co. 13 Maine R. 265; Kidwell v. Baltimore & Ohio R. R. Co. 11 Gratt. 676; Phil. Wilm. & Balt. R. R. Co. v. Howard, 13 Howard's U.S. R. 307; Delaware & Hudson Canal Co. v. Dubois, 15 Wend. R. 87; Ranger v. Great Western R. R. Co. 27 Eng. L. & E. R. 35; Sherman v. Mayor, & c. of New York, 1 Comstock's R. 316; Boston Water Power Co. v. Gray, 6 Metc. R. 131, 181; Kleine v. Catara, 2 Galli. R. 61; Head v. Muir & Long, 3 Rand. 122; Hollingsworth v. Lupton, 4 Munf. 114; Pollard v. Lumpkin, 6 Gratt. 398; Bassett's adm'r v. Cunningham's adm'r, 9 Gratt. 684; Underhill v. Van Cortlandt, 2 John. Ch. R. 339; Pleasants, & c. v. Ross, 1 Wash. 156; Taylor's adm'r v. Nicolson, 1 Hen. & Munf. 67; Butler v. Mayor, & c. of New York, 1 Hill's R. 489.
This is a supersedeas to a judgment of the Circuit court of Petersburg, rendered in an action of assumpsit brought by the plaintiff in error, David Condon, against the defendants in error, the South Side rail road company, on a contract between them, whereby the said Condon agreed to excavate, embank and construct sections Nos. 38 and 40 of the South Side rail road, according to certain specifications, and the said company agreed to pay for the work at certain rates, and in a certain manner, prescribed by the contract. The main, if not the only, object of the action, was to recover eighty cents per cubic yard for twelve thousand six hundred and sixty-two cubic yards of excavation, instead of the price allowed therefor in the final estimate of the engineer of the company, to wit, eighty cents per yard for two hundred and sixty cubic yards, thirty-five cents per yard for five thousand seven hundred and ninety-six cubic yards, and forty cents per yard for the remaining six thousand six hundred and six cubic yards thereof. The declaration contains three counts, all of which are special counts. There is little material variance between them. There was a general demurrer to the declaration, which was sustained by the court, and judgment thereupon rendered for the defendants: to which judgment the supersedeas in this case was awarded.
The contract is set out in totidem verbis in each count of the declaration. It embodies the specifications according to which the work was agreed to be done, but which it is unnecessary to detail. Under the head of " Items to be estimated and mode of estimating," is the following among other statements:
" All materials necessarily excavated for the road way, ditches or common road, will be estimated and paid for by the cubic yard, under the following heads, viz: Common excavation, Loose rock, Solid rock, and Slate that requires blasting.
Common excavation will include sand, clay, gravel, soft rock, loam, and all other earthy matter, also detached rock intermixed, which do not contain more than three cubic feet each.
Loose rock will include all detached rocks containing more than three and less than twenty-seven cubic feet each.
Solid rock will include all rock in masses containing more than one cubic yard, which requires blasting.
Slate--all slate which requires blasting."
The contract then proceeds:
" And the South Side rail road company covenant and agree to pay to the said party of the second part when the above contract shall have been faithfully complied with, at the following rates, to wit:
Section No. 38, 9 1/4 cents per cubic yard for common excavation.
Section No. 38, 9 1/4 cents per cubic yard of embankment.
At the engineer's estimate for loose rock.
Section No. 38, 80 cents per cubic yard for every yard solid rock.
At the engineer's estimate for slate rock.
Section No. 38, $3 per cubic yard of every yard of dry stone drains.
And they will make their payments in the following manner, that is to say: On or about the 1st day of every month during the progress of this contract, the company aforesaid will pay 80 per cent. of the relative value of such work as may be done, to be judged of by their engineer, and at such places as their said engineer may appoint, until the whole of the work herein contracted for shall have been finished agreeably to contract, and shall have been accepted by their said engineer as so finished and completed, when the balance due shall be forthwith paid to the said party of the second part."
Then follow sundry other provisions, of which the last is the following:
making the whole amount to the sum of ten thousand four hundred and thirty-eight dollars and sixty-one cents; and that the determination and classification of the said Gordon were adopted and adhered to by said Sandford, the chief engineer of the defendants: whereupon the plaintiff says that the said classification is contrary to the terms of the contract, and illegal and...
To continue reading
Request your trial-
Williams v. Chicago, Santa Fe And California Railway Co.
...the engineers misconstrued the contract or acted fraudulently. In the language of the Supreme Court of Virginia, in Condon v. Railroad, 55 Va. 302, 14 Gratt. 308, "Was it not for the engineer to decide under which of the heads enumerated in the contract the said rock should be classified; a......
-
JOHN W. DANIEL & COMPANY, INC. v. Janaf, Incorporated
...award after its rendition. Big Vein Pocahontas Co. v. Browning, 137 Va. 34, 120 S.E. 247; Corbin v. Adams, 76 Va. 58; Condon v. South Side R. Co., 14 Grat. 302, 55 Va. 302; Bernhard v. Jones, 156 Va. 476, 159 S.E. 82. The last cited case goes further in stating that where action by the arbi......
-
Emporia Concrete & Construction Co. v. Board of Com'rs of Granville County
... ... S.E. 832, Sweet v. Morrison, 116 N.Y. 19, 22 N.E ... 276, 15 Am. St. Rep. 376, Condon v. Railway Co., 55 ... Va. 302, and other cases of their class, but we think they ... have no ... ...
-
Emporia Concrete & Constr. Co v. Bd. Of Com'rs Of Granville County
...v. McArthur, 154 N. C. 122, 69 S. E. 832, Sweet v. Morrison, 116 N. Y. 19, 22 N. E. 276, 15 Am. St. Rep. 376, Condon v. Railway Co., 55 Va. 302, and other cases of their class, but we think they have no bearing upon the question now before us. If there had been a final estimate, or even if ......